Nova Scotia Power Investing in Future Generation with Lequille Hydro Plant Upgrades

Nova Scotia Power

 

August 17, 2017

It’s been 49 years since the Lequille Hydroelectric System on the Allain River (formerly Lequille River) began generating electricity in the Annapolis Valley. The Lequille powerhouse was widely celebrated when it first opened in 1968 as it was constructed close to the site of North America’s first grist mill built in 1607.

“The Lequille River system has long been a source of transportation, food, milling, and electricity for First Nation and Nova Scotian communities,” said Wes Trimper, Hydro Superintendent with Nova Scotia Power. “We’re proud to be part of this community and this project will ensure customers are able to benefit from the continued production of clean, renewable electricity.”

The Lequille Hydro System consists of three storage reservoirs and a three-mile canal that diverts water flow to a concrete intake structure. A wood stave penstock attached to the intake structure conveys water to the Lequille hydroelectric generating facility, which contains a water wheel connected to a 13 megawatt generator. Lequille generates enough electricity each year to power 2,000 to 3,000 homes.

This year, Nova Scotia Power is investing nearly $4 million dollars to ensure the hydro facility’s reliability, safety and efficiency. Work taking place this year includes the refurbishment of the generator, replacement of the hydro system’s pipeline and switchgear, and installation of a new control system and instrumentation. It’s expected that this project will wrap up by the end of the year.

“We continually assess our facilities to determine if and when upgrades are needed to ensure we can safely and reliably deliver service to customers,” said Trimper. “This investment in Lequille will support Nova Scotia Power’s efforts to transition to more renewable energy generation.”

The public may notice an increase in equipment and activity along the Lequille hydro system while these upgrades are underway. Nova Scotia Power crews and contractors will be carrying out the project, including Annapolis Valley-based Brown Bros Excavating Limited who will be working on wood stave penstock replacement.

We appreciated the patience of Grand Lake residents and cottage owners while we lowered water levels at the beginning of the season to minimize lost generation over the course of this project. We do not anticipate further disruption to typical water levels at Grand Lake due to this project.

The public is advised to expect increased water flows through Allain Creek, as it is part of the hydro system spillway, and to take extra safety precautions near this waterway over the coming months.

Lequille is one of 33 hydroelectric generating stations located along 17 river systems across the province that provide a firm source of renewable energy and are an important part of Nova Scotia Power’s requirement to generate 40 per cent of electricity from renewable sources in 2020. In 2016, Nova Scotia Power reached a record 28 per cent of renewable electricity generation.

http://www.nspower.ca/en/home/newsroom/news-releases/nova-scotia-power-investing-in-future-generation-w.aspx

Related Articles


Latest Articles

  • Non-residential Construction Investment Continues to Reach Record Highs in January 2025

    Non-residential Construction Investment Continues to Reach Record Highs in January 2025

    April 18, 2025 Overall, investment in building construction rose 1.8% (+$393.7 million) to $22.1 billion in January. The residential sector increased 2.3% to $15.4 billion, while the non-residential sector was up 0.8% to $6.7 billion. Year over year, investment in building construction grew 5.7% in January. On a constant dollar basis (2017=100), investment in building construction increased 1.5% from the previous month to $13.2 billion… Read More…

  • BC Non-Residential Drives Growth, Multi-Family Component Drives Residential Decline in February Building Permits

    BC Non-Residential Drives Growth, Multi-Family Component Drives Residential Decline in February Building Permits

    April 18, 2025 In February, the total value of building permits issued in Canada increased by $371.3 million (+2.9%) to $13.1 billion. Gains in construction intentions were led by British Columbia’s non-residential sector. On a constant dollar basis (2017=100), the total value of building permits issued in February grew 3.2% from the previous month and was up 5.6% on… Read More…

  • Navigating Tariffs: Practical Strategies for ECABC Members

    Navigating Tariffs: Practical Strategies for ECABC Members

    April 18, 2025 Canadian businesses are facing uncertain and unprecedented risks created by tariffs on Canadian goods from the United States. The combination of the economic impact to BC’s economy from these tariffs, and the potential increase in the cost of construction materials and equipment as Canada is forced to respond with retaliatory tariffs, has… Read More…

  • Navigating Tariff Uncertainty as an Electrical Contractor

    April 15, 2025 By Matthew Biswas These three words put me into a catatonic shock – Supply Chain Disruption. It seems like just yesterday I was standing at a counter asking for products I’d bought 100’s of times before and being told they are on backorder with no expected delivery date. Circuit breakers, dimmers, panels,… Read More…


Changing Scene

  • Ontario Introduces Legistlation to Unlock Trade and Labour Mobility Within Canada

    Ontario Introduces Legistlation to Unlock Trade and Labour Mobility Within Canada

    April 18, 2025 As a next step in its plan to protect Ontario by unleashing the province’s economy, the Ontario government is introducing the Protect Ontario through Free Trade within Canada Act to unlock free trade and labour mobility within Canada. This legislation will, if passed, create new opportunities for job creation and investment attraction, supporting economic… Read More…

  • Ontario, P.E.I. Join Nova Scotia With Legislation to Remove Internal Trade Barriers

    Ontario, P.E.I. Join Nova Scotia With Legislation to Remove Internal Trade Barriers

    April 18, 2025 Prince Edward Island and Ontario have joined the Nova Scotia by introducing reciprocal legislation that will help foster an environment of mutual recognition of goods, services and labour mobility between these provinces. “Leaders across the country are expressing interest in removing trade barriers, and I’m very pleased that P.E.I. and Ontario have… Read More…

  • New Brunswick Signs MOU with Ontario to Reduce Trade and Labour Mobility Barriers

    New Brunswick Signs MOU with Ontario to Reduce Trade and Labour Mobility Barriers

    April 18, 2025 The governments of New Brunswick and Ontario have signed a memorandum of understanding on free trade and labour mobility. “Ontario is New Brunswick’s second-biggest trading partner, and we are excited to be building on the positive momentum to reduce internal trade barriers across Canada,” said Premier Susan Holt. “Today’s signing of this… Read More…

  • EFC Welcomes New Manufacturer Member: MegaResistors Corp.

    EFC Welcomes New Manufacturer Member: MegaResistors Corp.

    April 18, 2025 Founded in 2008, MegaResistors is a proudly Canadian company specializing in the design and production of high-quality power resistors, including grounding resistors, braking resistors and resistive load banks, tailored for demanding industry and mission critical applications. Their extensive line of products helps them meet the needs of the industry, from crane control… Read More…