Growth in Electricity Demand Expected to Continue in Québec

November 11, 2022

In the Electricity Supply Plan 2023–2032 (in French only) that it filed with the Régie de l’énergie, Hydro-Québec anticipates an increase of 25 terawatthours (TWh) or 14% in Québec’s electricity demand over the 2022–2032 period. 

This increase is due to several factors, many of which relate to the energy transition:

  • Organic growth: +4.3 TWh*
  • Building/industrial process conversion: +4.5 TWh
  • Emerging markets, including data centers (4.1 TWh), green hydrogen production (2.3 TWh), battery components for electric vehicles (1.2 TWh) and greenhouse farming (0.7 TWh): +8.9 TWh
  • New technologies:
    • Photovoltaic solar: −0.7 TWh
    • Transportation electrification: +7.8 TWh

*TWh: one billion kilowatthours

The sum of the values may differ from the total because of rounding.

Hydro-Québec has already begun to implement the necessary measures to meet the increased demand.

1. Energy efficiency and demand response tools

The anticipated growth takes into account significant energy efficiency efforts that will make it possible to curtail 8.9 TWh by 2032. Hydro-Québec programs such as the Efficient Heat Pump Program for residential customers and the Efficient Solutions Program for business customers will help optimize electricity use.

In addition, demand response tools will help us manage winter peaks, i.e., the coldest hours during the winter when electricity use rises sharply. In total, the tools available to our various customer segments will help curtail more than 3,000 megawatts (MW) in winter 2031-2032—the equivalent of the capacity of La Grande-4 generating station, the second largest among our 62 hydroelectric facilities in terms of capacity. Demand response tools include Hilo and dynamic pricing, as well as the Demand Response (DR) Option offered to business customers.

2. New calls for tenders

To meet the growing demand, Hydro-Québec will have to add energy and capacity to its supply portfolio. To that end, two new calls for tenders—one for 300 MW of wind power and the other for 480 MW of renewable energy—are already underway. Two more, for 1,000 MW of wind power and 1,300 MW of renewable energy, respectively, will be launched in the next few months, and others will follow in the coming years to meet the needs set out in the Electricity Supply Plan 2023–2032.

3. Proactive management of our generation resources

In recent years, Hydro-Québec has also taken steps to increase the capacity of its generating fleet and enhance other sources of supply to which it has access. These include commissioning Romaine-4 generating station, increasing the capacity of some of its existing hydroelectric facilities, creating a 3,000-MW portfolio of wind power projects and purchasing the output of generating stations owned and operated by Evolugen.

Request to suspend the allocation of electricity to the blockchain industry

Lastly, in light of the significant increase in the anticipated demand for electricity and the tightening energy and capacity balances, Hydro-Québec filed a request with the Régie de l’énergie regarding suspension of the allocation process to the blockchain industry. Under this process, approximately 270 MW were slated to be dedicated to cryptographic use over the short term, but the allocation of that amount of capacity to this use would increase pressure on current balances.

Source

Related Articles


Latest Articles

  • Take the Lesson

    Take the Lesson

    September 2, 2024 By Keith Sones, seasoned utility industry executive “I really don’t want to do this.” “You have to Keith. You have no choice. You can’t leave him hanging” replied my wife. I stared at the phone like a child looks at liver on their plate. They know you have to eat it but also… Read More…

  • Quebec Drives the Growth in Residential Building Construction in June, 2024

    Quebec Drives the Growth in Residential Building Construction in June, 2024

    Investment in building construction grew 2.8% to $21.4 billion in June, after a slight increase of 0.8% in May. These increases partly reflect April’s record high of $13.4 billion in total building permits value, since investment levels for a given period are driven by permits issued in prior months. The June increase in investment in building construction was primarily… Read More…

  • Western Memorial Regional Hospital Sets New Infrastructure Precedent and Receives LEED Silver Certification 

    Western Memorial Regional Hospital Sets New Infrastructure Precedent and Receives LEED Silver Certification 

    August 16, 2024 The new Western Memorial Regional Hospital in Corner Brook is home to Canada’s largest geothermal system, which has set a precedent for modern infrastructure for both Newfoundland and Labrador and North America. The geothermal field is approximately 600 feet below the hospital’s parking lot, and provides 100 per cent of the ground… Read More…

  • Brightening Communities: LED Technology in Action

    Brightening Communities: LED Technology in Action

    August 15, 2024 By Alex Price, Brand & Planning Manager, Current LightingTechnical Contributor: Gary Steinberg, Senior System Manager (Outdoor LED Fixtures), Current Lighting As the landscape of Canadian cities continues to evolve, the importance of outdoor lighting cannot be overstated. From enhancing public safety to promoting economic activity and fostering a sense of community, well-planned… Read More…


Changing Scene

  • Schneider Electric Launches SMART Buildings Division to Drive Sustainable Building Innovation in Canada

    Schneider Electric Launches SMART Buildings Division to Drive Sustainable Building Innovation in Canada

    Schneider Electric is transforming its Digital Buildings business in Canada with the launch of the SMART Buildings Division. This evolution marks a strategic move to deliver comprehensive solutions and services that support building owners and operators in achieving their decarbonization and sustainability goals. The demand for smart buildings is surging, driven by a global shift… Read More…

  • Introducing Alan Bearden as Interim President of Southwire Canada

    Introducing Alan Bearden as Interim President of Southwire Canada

    September 4, 2024 Southwire Canada is pleased to announce that Alan Bearden has been appointed Interim President. In this role, Alan will provide leadership and guidance for Southwire’s Canada-based organization, ensuring continuity and driving growth during this transitional period. Alan Bearden brings a wealth of experience to the position, having joined Southwire in 2008. Over… Read More…

  • A Partnership Between Electromag Graybar Canada and Phoenix Contact

    A Partnership Between Electromag Graybar Canada and Phoenix Contact

    September 3, 2024 Electromag Graybar Canada, a pioneer in industrial automation solutions and pneumatic products, is excited to announce a partnership with Phoenix Contact, a global leader in electrification, networking, and industrial automation. This collaboration, which initially began in the Langley and Ontario branches, is now expanding to Quebec. The alliance aims to provide cutting-edge… Read More…

  • Sonepar Announces the Retirement of William (Bill) C. Smith, Electrozad Director of Transitional Business

    Sonepar Announces the Retirement of William (Bill) C. Smith, Electrozad Director of Transitional Business

    September 2, 2024 William (Bill) C. Smith, Director, Transitional Business of Electrozad Supply Company Limited announced his retirement as of August 30th, 2024 after 49 years of leadership. Bill began his electrical career working part-time at Electrozad Supply while completing a Sales & Marketing Program at St. Clair College.  After his first full-time position in… Read More…