Hydro-Québec Issues Tender Call for 1,500 MW of Wind Power

April 3, 2023

As part of its distribution operations and in keeping with Québec government regulations, Hydro-Québec issued a tender call for 1,500 megawatts (MW) of electricity generated from wind power to meet the long-term electricity needs of its Québec customers.

The selected projects will help meet Québec’s growing demand for electricity. As per its Electricity Supply Plan 2023–2032, Hydro-Québec anticipates an increase in Québec’s electricity demand of 25 terawatthours (TWh), or 14% over the 2022–2032 period.

Projects must be carried out in the areas identified by Hydro-Québec so that commissioning and connection to the grid can take place between December 1, 2027, and December 1, 2029, in compliance with a Québec government Order in Council.

The minimal requirements for bidders include the obligation to show that the proposed project has the support of the host community. All submissions must therefore include a certified true copy of a resolution passed by the community in question.

Contracts must be approved by the Régie de l’énergie.

Below are a few key dates from the schedules in the tender package:
  • Pre-bid meeting for potential bidders: April 4, 2023 (online)
  • Technical meeting: April 5, 2023 (online)
  • Submission deadline: no later than 4 p.m. (Eastern time) on September 12, 2023

This call for tenders may be amended according to the Régie de l’énergie’s ruling in relation to Hydro-Québec’s application for approval of bid evaluation criteria and their weightings, characteristics of the product sought, and minimum requirements of the call for tenders for 1,500 MW of wind energy (A/O 2023-01).

Hydro-Québec has appointed the firm Raymond Chabot Grant Thornton to assist in the tendering process and serve as its official representative.

More Information

Information regarding calls for tenders launched by Hydro-Québec as part of its distribution activities is provided here: https://www.hydroquebec.com/electricity-purchases-quebec/.

For further information: Hydro-Québec, Media relations, 514 289-5005

Source

Related Story

Hydro-Québec Accepts Seven Projects Totaling Nearly 1,150 MW of Wind Power

Hydro-Québec has accepted seven bids for a total of 1,303.36 megawatts (MW) of installed capacity under the two calls for tenders launched on December 13, 2021. One of the calls for tenders was for a block of 480 MW from renewable energy sources and the other one was for a block of 300 MW generated from wind power.

Related Articles


Latest Articles


Changing Scene

  • Federal Investment to Add 989 New Montreal Homes

    Federal Investment to Add 989 New Montreal Homes

    November 18, 2024 The federal government is providing nearly $364 million to help build 989 new homes in Montreal. The announcement took place at 5200 rue de la Savane, in Montreal, which received $100 million dollars through the Apartment Loan Construction Program (ACLP) to build 303 homes and will be operated by Olymbec. This rental building, named Lynk, is designed to… Read More…

  • ABB and NIEDAX Group Announce Completion of Joint Venture with the Formation of Abnex Inc.

    ABB and NIEDAX Group Announce Completion of Joint Venture with the Formation of Abnex Inc.

    November 18, 2024 ABB completed the previously announced 50/50 joint venture with Niedax Group. The Abnex Inc. joint venture (JV) will broaden solutions and advance opportunities in the rapidly growing North American cable management market. Integrating engineering and manufacturing capabilities of ABB’s Installation Products Division with Niedax Group will enable the newly formed company to deliver a… Read More…

  • Ontario Building More Electric Vehicle Charging Stations

    Ontario Building More Electric Vehicle Charging Stations

    November 18, 2024 The Ontario government is building over 1,300 new electric vehicle (EV) charging ports in small and medium-sized communities, marking a major milestone in the province’s plan to increase access to EV chargers outside of large urban centres and support the electrification of transportation across the province. As the province continues to see… Read More…

  • Ontario Investing Over $74 Million Through Next Round of Skills Development Fund Capital Stream

    Ontario Investing Over $74 Million Through Next Round of Skills Development Fund Capital Stream

    November 18, 2024 The Ontario government is launching the second round of its Skills Development Fund (SDF) Capital Stream starting November 29, with over $74 million in available funding to build, expand and retrofit training facilities for workers in the trades, including construction, manufacturing technology and health care. The government is also investing nearly $5 million from the first… Read More…