STANDATA Interpretation 2021 CE Code, Section 12 -Installation of Boxes, Cabinets, Outlets, and Terminal Fitings

Janaury 22, 2024

Industry has requested clarification/interpretation on the phrase “equivalent device” as described in CE Code, Part I Rule 123000 1) and how it relates to conduit fittings.

Interpretation

The term “equivalent device” in rule 12-3000 1) includes “conduit fittings” in special applications (i.e., connection to solenoids, photocells, etc.). Wire leads from these devices must be integral to the device. Where the device has a bonding conductor and the conduit fitting has no provisions for attaching a bonding conductor, a separate bonding conductor must be provided in the conduit system to the fitting. The fitting must also comply with the requirements of Rule 12-3034 maximum number of insulated conductors in a box and Table 22 regarding the volume limitations.

This INTERPRETATION is applicable throughout the Province of Alberta.

View the full STANDATA HERE

Code References C22.1:21 – 2021 Canadian Electrical Code, Part I

12-3000 Outlet boxes (see Appendix B)

1) A box or an equivalent device shall be installed at every point of outlet, switch, or junction of conduit, raceways, armoured cable, or non-metallic-sheathed cable.

12-3034 Maximum number of insulated conductors in a box (see Appendix B)

1) Boxes shall be of sufficient size to provide usable space for all insulated conductors contained in the box, subject to the following:

a) an insulated conductor running through a box with no connection therein shall be considered as one insulated conductor;

b) each insulated conductor entering or leaving a box and connected to a terminal or connector within the box shall be considered as one insulated conductor;

c) an insulated conductor of which no part leaves the box shall not be counted; and

d) No. 18 and No. 16 AWG fixture-wires supplying a luminaire mounted on the box containing the fixture-wires shall not be counted.

Δ 2) Except as specified in Subrule 3) and subject to the details given in Subrule 1), boxes of the nominal dimensions given in Table 23 shall not contain more insulated conductors of a given size than permitted by the Table, and the number of conductors shall be reduced for each of the following conditions as applicable:

a) one insulated conductor, of the largest size in the box, for each fixture stud or hickey within the box;

b) one insulated conductor, of the largest size terminated under the conductor connector, for every pair of conductor connectors with insulating caps; and

c) two insulated conductors for each flush-mounted device on a single strap within the box.

3) Where a box contains a device having a dimension greater than 2.54 cm between the mounting strap and the back of the device, the total usable space shall be reduced by the space occupied by the device, calculated as 32 cm3 multiplied by the depth of the device in centimetres.

4) Subject to the details given in Subrules 1) and 3), boxes having nominal dimensions or volume other than those shown in Table 23, or any box containing insulated conductors of different sizes, shall have the amount of usable space per insulated conductor as specified in Table 22, but the number of insulated conductors so calculated shall be reduced for each of the conditions of Subrule 2) as applicable with the exception of Subrule 2 b), provided that such exception is based on the size of the largest insulated conductor that is included with every pair of conductor connectors.

5) The total usable space in a box considered under Table 22 shall be considered to be the internal volume of the box and shall disregard any space occupied by locknuts, bushings, box connectors, or clamps.

6) Where sectional boxes are ganged, or where plaster rings, extension rings, or raised covers are used in conjunction with boxes, ganged or otherwise, and are marked with their volume measurement, the space in the box shall be the total volume of the assembled sections.

Go HERE for more information on all STANDATA publications

Related Articles


Latest Articles


Changing Scene

  • Federal Investment to Add 989 New Montreal Homes

    Federal Investment to Add 989 New Montreal Homes

    November 18, 2024 The federal government is providing nearly $364 million to help build 989 new homes in Montreal. The announcement took place at 5200 rue de la Savane, in Montreal, which received $100 million dollars through the Apartment Loan Construction Program (ACLP) to build 303 homes and will be operated by Olymbec. This rental building, named Lynk, is designed to… Read More…

  • ABB and NIEDAX Group Announce Completion of Joint Venture with the Formation of Abnex Inc.

    ABB and NIEDAX Group Announce Completion of Joint Venture with the Formation of Abnex Inc.

    November 18, 2024 ABB completed the previously announced 50/50 joint venture with Niedax Group. The Abnex Inc. joint venture (JV) will broaden solutions and advance opportunities in the rapidly growing North American cable management market. Integrating engineering and manufacturing capabilities of ABB’s Installation Products Division with Niedax Group will enable the newly formed company to deliver a… Read More…

  • Ontario Building More Electric Vehicle Charging Stations

    Ontario Building More Electric Vehicle Charging Stations

    November 18, 2024 The Ontario government is building over 1,300 new electric vehicle (EV) charging ports in small and medium-sized communities, marking a major milestone in the province’s plan to increase access to EV chargers outside of large urban centres and support the electrification of transportation across the province. As the province continues to see… Read More…

  • Ontario Investing Over $74 Million Through Next Round of Skills Development Fund Capital Stream

    Ontario Investing Over $74 Million Through Next Round of Skills Development Fund Capital Stream

    November 18, 2024 The Ontario government is launching the second round of its Skills Development Fund (SDF) Capital Stream starting November 29, with over $74 million in available funding to build, expand and retrofit training facilities for workers in the trades, including construction, manufacturing technology and health care. The government is also investing nearly $5 million from the first… Read More…