Keeping the roof open: Retrofit of Rogers Centre’s retractable roof

Rogers Centre

The Rogers Centre’s roof and its systems had been meticulously maintained from the outset; however certain parts and components had been discontinued over the years, making the original technology outdated and difficult to maintain. As time went on, opening and closing the roof became more challenging. “I always equate it to this: Not many people are still driving a car they had 20 years ago,” said Dave McCormick, Engineering Manager, Rogers Centre.

The roof, which consists of three moving panels and one fixed piece, is 282 feet high at its center and covers 8 acres. Two of the panels slide under the fixed panel, then the final panel rotates around the stadium and into place until the four panels resemble a stack of plates. When opening or closing the roof, it has to be capable of quickly, reliably, and precisely moving 11,000 tons of steel in winds up to 40 miles per hour blowing from varying directions.

“As much as fans love seeing the sky, in this stats-heavy game, baseball fans also believe the Blue Jays do better when the roof is open which has made the roof an integral part of the game and the fan experience,” said Mark Niesner, Director of Operations and Organizational Development, New Electric, the general contractor for the Rogers Centre’s roof-related renovations.

To continue meeting the expectations of fans and promoters, the roof’s infrastructure required significant upgrades, including a new OT (Operations Technology) network and control system, which help management determine when to close the roof and provide them the ability to once again do so reliably. “Basically, what this project was about was getting this structure and the operating system back to a state where it can sustain for the next 15 to 20 years,” explained McCormick.

Successful replacement of the aging stadium roof OT network and controls system was completed through a number of organizations working in partnership. New Electric, acting as prime and electrical contractor, provided project management, electrical solutions and mechanical support. Rockwell Automation and Cisco provided product and technical expertise. Gerrie Electric provided product and assisted in testing and design. JMP Engineering provided the knowledge, experience and execution of the design installation and commissioned the entire control system.

Rogers Centre selected the team due to their combined proven expertise in successfully delivering critical projects. It was also important to Rogers that the partners had the ability to locally service and support the system during and over the life of the roof. For over 10 years, New Electric has managed Rogers Centre’s requirements, for everything from the roof and its power and control systems to its concession stands and ATMs, lights and the Blue Jays’ locker rooms. As a result, New Electric really understands Rogers Centre, its culture and unique requirements.

“Looking ahead, Rogers Centre committed to leading edge, proven technology to meet today’s standards,” said Steve Szamocki, Executive Vice President of Sales and Marketing, JMP Engineering. “Twenty-five years ago, this technology was leading edge but increasingly, these legacy systems had become a challenge to support effectively and efficiently.”

“Rockwell Automation is excited to have our PowerFlex® variable frequency drive solutions and ControlLogix® PLC’s be a cornerstone of this highly visible and critical roof modernization project,” said Mike Laszkiewicz, Vice President & General Manager, Power Control Business, Rockwell Automation. “Rogers Centre will now be able to achieve greater efficiency and reliability by integrating the roof system with the network and our control system, a vision that Rockwell Automation calls the Connected Enterprise.”

Completion of this retrofit required approximately two years, $10 million and close to 30 people simultaneously working full-time on the renovation. Thanks to the upgrades, the roof once again performs optimally, easily and with absolute reliability. To help Rogers Centre keep fans dry, New Electric also installed a rooftop weather station that tracks weather systems to predict when the rain or cold front will arrive.

While the opening and closing still requires a full crew to operate safety, the control system now only needs one person to monitor the process. The entire process can be completed with a 46% speed improvement as compared to the legacy control system. Also, of significant value to Rogers Centre, the enhanced functionality of the modern control system and its supporting OT network provides fault tolerance, self-diagnostics, and reporting previously not available, allowing the operator an easy and quick way to trouble-shoot and rectify any issues, should they arise.

“As general contractors, we can take on far more than the electrical and had the resources to accommodate Rogers Centre’s incredibly full event schedule,” said Niesner. “We don’t come in to just hook up wires – we’re here to help Rogers Centre give the fans a fantastic experience.”

New Electric

Related Articles


Latest Articles

  • Resilient but Not Ready: Affordability, Trade and Workforce Barriers Limit Alberta’s Retrofit Supply Chain

    Resilient but Not Ready: Affordability, Trade and Workforce Barriers Limit Alberta’s Retrofit Supply Chain

    July 30, 2026 Alberta’s building retrofit sector is ready to scale and could generate $5.8 billion in GDP and support 24,000 jobs with $2.5 billion in annual investment — but only if governments, utilities, and industry align on a clear, coordinated strategy. Resilient but Not Ready shows that while Alberta’s retrofit supply chain is adaptable and… Read More…

  • Lighting 101: How to Choose the Right LED Replacement

    Lighting 101: How to Choose the Right LED Replacement

    July 30, 2026 By EB Horsman & Son Not all LED replacements are created equal. Whether you’re replacing a single light fixture in your home or upgrading lighting throughout your building, choosing an equivalent LED replacement isn’t always as simple as matching the wattage or colour temperature. Many homeowners, contractors, facility managers, and property managers… Read More…

  • Lighting an Industrial Facility: Designing for Safety, Productivity & Performance

    Lighting an Industrial Facility: Designing for Safety, Productivity & Performance

    July 30, 2026 By CSC LED When planning an industrial facility, lighting is often discussed by fixture type—high bays, wall packs, flood lights, emergency lighting, and so on. In reality, successful lighting design starts by understanding how each space is used. Every area of an industrial property has different visual requirements. A parking lot prioritizes… Read More…

  • Gescan Milwaukee Tent Events

    Gescan Milwaukee Tent Events

    July 30, 2026 Take advantage of exclusive event‑day pricing, live hands‑on demos with Milwaukee Specialists, and explore new and featured solutions across power tools, lighting, safety, batteries, and accessories. Enjoy food, giveaways, and prize draws happening at the branch for ONE DAY ONLY! BONUS ITEMS: Visit one of Gescan’s participating locations starting at 7:00 am, don’t… Read More…


Changing Scene

  • Copper Thefts on Bell’s Network Surge 78% at the Mid-Year Mark

    Copper Thefts on Bell’s Network Surge 78% at the Mid-Year Mark

    July 30, 2026 Copper theft continues to rise across Canada, with serious consequences for communities and the critical services they rely on. In the first half of 2026, Bell has seen a surge in theft and vandalism targeting telecommunications infrastructure, causing service outages that can disrupt Internet, TV and phone services — and, most importantly,… Read More…

  • Electrozad Launches Enhanced Digital Solutions with Improved eCommerce Website and New Mobile App

    Electrozad Launches Enhanced Digital Solutions with Improved eCommerce Website and New Mobile App

    July 30, 2026 Electrozad, a Sonepar company, is proud to announce the launch of its newly enhanced eCommerce website and new mobile app, marking a significant milestone in the Electrozad’s digital evolution and commitment to delivering the best customer experience. The digital platforms are now available to customers across Southwestern Ontario, making it easier and… Read More…

  • Seacliff Electric Introduce New Regional Manager for Calgary Operations

    Seacliff Electric Introduce New Regional Manager for Calgary Operations

    July 20, 2026 Seacliff Electric are pleased to announce that Joe Niosi has accepted the position of Regional Manager for their Calgary operations. “Joe has been an important member of our team and brings extensive experience in the electrical construction industry, project execution, leadership, and team development. Through his time as our Service & Special… Read More…

  • Electrical Safety Authority Welcomes Federal Action on Copper Theft, Citing Deadly Risks to Public and Workers

    Electrical Safety Authority Welcomes Federal Action on Copper Theft, Citing Deadly Risks to Public and Workers

    July 20, 2026 New sentencing provisions recognize serious public safety consequences of crimes targeting electrical infrastructure. The Electrical Safety Authority (ESA) welcomes the federal government’s implementation of provisions within the Bail and Sentencing Reform Act (Bill C-14) that strengthen consequences for crimes that damage or interfere with essential infrastructure, including copper theft. Copper theft is a growing challenge… Read More…