Ontario’s Electricity System Ready for Winter

ieso

December 14, 2017

Ontario’s high-voltage power system has adequate generation and transmission resources to maintain reliability and meet the province’s forecasted electricity needs over the next 18 months. Ontario’s Independent Electricity System Operator’s (IESO) 18-Month Outlook report, released this December, assesses the grid’s reliability from January 2018 to June 2019.

“Continuing the trend of the last few years, we’re forecasting that Ontario will continue to experience flat growth in electricity demand,” said Leonard Kula, Vice-President, Procurement, Acquisition and Operations and Chief Operating Officer. “We attribute this mainly to Ontarians’ conservation efforts, generation on local distribution networks and the Industrial Conservation Initiative, which all work to reduce demand on the provincial power system and offset any expected growth we might see from increased population and economic expansion.”

During the Outlook timeframe, 1,335 megawatts (MW) of generation are expected to be added to the provincial power system: 1,000 MW of gas, 275 MW of wind, 50 MW of solar, and 10 MW of hydroelectric power. On local distribution networks, an additional 200 MW of solar will be added, bringing total wind and solar capacity on local distribution networks to over 3,300 MW. As a result of the province’s robust supply situation and flat yearly demand for electricity, the procurement phases of the IESO’s Feed-in-Tariff (FIT) and microFIT programs have come to an end. These programs have been instrumental in helping Ontario establish the clean energy supply mix it has today.

Ontario’s strong supply situation also means it is well-positioned to explore efficiencies that could be gained from market reforms. “The IESO is working to ensure that the many planned design changes improve how electricity is priced, scheduled and acquired to meet Ontario’s electricity needs reliably, transparently and at lowest cost,” said Kula.

And while the province has sufficient generation and transmission resources to maintain reliability, there is still a need for greater flexibility to respond quickly to changing conditions. To this end, the IESO has secured two new energy storage facilities, representing 55 MW of regulation service that will help to balance supply and demand on a second-to-second basis. These new storage facilities represent one of the largest reductions in per-unit regulation costs since Ontario’s electricity market opened in 2002 – a sign of the increased performance and cost-effectiveness of emerging technologies in Ontario.

About the 18-Month Outlook

The IESO’s 18-Month Outlook reports on the adequacy of Ontario’s generation and transmission resources to meet the province’s forecasted electricity needs over the next 18 months. The report looks at a variety of factors including weather forecasts, new planned generation and the health of the province’s transmission infrastructure. It sets out a forecast for provincial electricity demand and measures the system’s preparedness to maintain reliable operations.

http://www.ieso.ca/en/corporate-ieso/media/news-releases/2017/12/ontario-electricity-system-ready-for-winter

Related Articles


Latest Articles

  • Ottawa Day 2026: EFC Members Engage with Parliamentarians on Canada’s Electricity Future

    Ottawa Day 2026: EFC Members Engage with Parliamentarians on Canada’s Electricity Future

    March 16, 2026 By Electro-Federation Canada Following EFC’s recent update on our 2026 Ottawa Day, we are pleased to share photo highlights from two days of engagement on Parliament Hill, where members met with federal decision-makers to discuss the future of Canada’s electricity system. More than 40 EFC member leaders and Government Relations representatives travelled Read More…

  • Industrial Construction Intentions Drive Increase in Non-Residential Sector in January

    Industrial Construction Intentions Drive Increase in Non-Residential Sector in January

    March 13, 2026 In January, the total value of building permits issued in Canada increased $607.0 million (+4.8%) to $13.3 billion. The increase was led by the non-residential sector (+$464.0 million) and supported by the residential sector (+$143.0 million). On a constant dollar basis (2023=100), the total value of building permits issued in January rose 4.3% from the previous month Read More…

  • Multi-Unit Construction Drives Growth in December Residential Construction Investment, 2025 Review

    Multi-Unit Construction Drives Growth in December Residential Construction Investment, 2025 Review

    March 13, 2026 The total value of investment in building construction increased $442.9 million (+1.9%) to $23.7 billion in December. The residential sector grew 2.4%, while the non-residential sector edged up 0.6%. Year over year, investment in building construction grew 12.2% in December. On a constant dollar basis (2023=100), the total value of investment in building construction in December rose 1.7% Read More…

  • 5 Strategic Reasons to Attend the Lumen Exhibition

    5 Strategic Reasons to Attend the Lumen Exhibition

    March 13, 2026 In a market where deadlines are tight and projects are increasingly complex, staying competitive is no longer just about technical skills. It also depends on having the right tools, the right information, and the right partners by your side. The Lumen Exhibition is more than just an event—it’s a strategic lever designed to Read More…


Changing Scene

  • Blackstone Announces Agreement to Acquire Arlington Industries

    Blackstone Announces Agreement to Acquire Arlington Industries

    March 20, 2026 Blackstone and Arlington Industries announced that funds managed by Blackstone Energy Transition Partners have entered into a definitive agreement to acquire Arlington. Founded in 1949, Arlington designs and manufactures a range of electrical products such as fittings, enclosures and other components. The company’s innovative solutions are used across commercial, industrial and data Read More…

  • A New Guillevin.com, Designed to Simplify Your Purchasing Experience

    A New Guillevin.com, Designed to Simplify Your Purchasing Experience

    March 16, 2026 Guillevin.com was built as a digital working tool, designed to support the way their customers plan, search for, and purchase products today. The goal is simple: to offer a fast, reliable, and intuitive online platform capable of supporting real-world operations; both on the job site and in the office. A platform built around Read More…

  • Nova Scotia Strengthens Housing Legislation to Accelerate Supply

    Nova Scotia Strengthens Housing Legislation to Accelerate Supply

    March 13, 2026 Amendments to existing legislation will mean more housing, improved efficiency in the sector and better alignment of related agencies. The changes extend the Executive Panel on Housing in the Halifax Regional Municipality and give the Minister of Housing new authority to ensure housing projects aren’t delayed. “We are strengthening how we plan, Read More…

  • BC Introduces Public Sector Construction Projects Procurement Act

    BC Introduces Public Sector Construction Projects Procurement Act

    March 13, 2026 Kiel Giddens, MLA for Prince George-Mackenzie and Critic for Labour, has introduced the Public Sector Construction Projects Procurement Act, legislation aimed at ensuring publicly funded construction contracts are awarded through labour-neutral, merit-based procurement. “Here’s the simple question: if labour shortages are driving cost overruns, why would government limit who can work on public projects?” Read More…