Canada Energy Regulator Approval – Interconnection Project with Maine Gets the Final Green Light

EIN 27 hydro quebec 400

The Canada Energy Regulator (CER) issued the permit authorizing the construction and operation of the Appalaches–Maine Interconnection line. This infrastructure will link to the New England Clean Energy Connect (NECEC) line, whose construction began in Maine in February 2021. The project now has all the permits required for construction, from Saint-Adrien-d’Irlande in Québec to the City of Lewiston in Maine.

The CER’s authorization comes after a 21-month evaluation, which included a period for public comment.

“This green light recognizes the significant work carried out to date by our teams and our partners in the communities,” underscored Sophie Brochu, President and CEO of Hydro-Québec. “We are going ahead with a project that respects the highest environmental and engineering standards, and that has been favorably received by the various host communities.”  

Work will begin in the coming weeks, with commissioning slated for 2023. The Québec government authorized the project on April 7, 2021, whereas the Commission de protection du territoire agricole and the Régie de l’énergie gave their approvals in December and July 2020, respectively.  

The new Appalaches–Maine–NECEC line will carry 1,200 megawatts of Québec hydroelectricity to New England.  The interconnection will supply Massachusetts with 9.45 terawatthours of clean Québec hydropower. In addition, through an agreement signed with Maine last summer, Maine will receive 0.5 terawatthours annually for 20 years.

The route selected in Québec for the 320-kV direct current line extends 100 km between Appalaches substation in Saint-Adrien-d’Irlande (near Thetford Mines) and a connection point in the municipality of Frontenac in Estrie on the Québec–Maine border. The project also calls for the installation of a converter at Appalaches substation, which will convert alternating current to direct current to supply the new interconnection. The length of the line route in Maine is 233 km.

Source

 

Related Articles


Latest Articles


Changing Scene

  • Siemens to Establish Global AI Manufacturing Technologies R&D Center for Battery & EV Production in Canada

    Siemens to Establish Global AI Manufacturing Technologies R&D Center for Battery & EV Production in Canada

    May 26, 2025 Siemens will invest CAD $150 million over five years to establish a Global AI Manufacturing Technologies Research and Development (R&D) Center for Battery Production in Canada. The new R&D center, located initially at Siemens Canada’s head office in Oakville, as well as in Toronto and Kitchener-Waterloo, Ontario, will focus on developing cutting-edge AI manufacturing technologies with an initial emphasis… Read More…

  • Honda Postponing Ontario EV Supply Chain Investment by Two Years

    Honda Postponing Ontario EV Supply Chain Investment by Two Years

    May 26, 2025 Honda is postponing its plan to invest in a comprehensive EV supply chain in Ontario. The CBC reported that the investment is being push back by two years. “Due to the recent slowdown of the EV market, Honda Motor has announced an approximate two-year postponement of the comprehensive value chain investment project in Canada…. Read More…

  • Serge Leblanc Named Sonepar Canada Interim President

    Serge Leblanc Named Sonepar Canada Interim President

    May 26, 2025 George McClean, former President of Sonepar Canada, has decided to leave Sonepar for an opportunity outside of the electrical industry. Serge Leblanc, current President of Lumen Canada, has been appointed interim President of Sonepar Canada. Leblanc will manage both responsibilities until a successor is named.  Leblanc joined Lumen in 1997 and has… Read More…

  • Ontario Building and Construction Tradeswomen Head to Queens Park to Advocate for Safer, More Inclusive Job Sites

    Ontario Building and Construction Tradeswomen Head to Queens Park to Advocate for Safer, More Inclusive Job Sites

    May 26, 2025 On Monday, May 26, the Ontario Building and Construction Tradeswomen (OBCT), will host its first-ever Advocacy Day at Queen’s Park. Tradeswomen from across the province will gather to meet with Members of Provincial Parliament, including Minister of Labour David Piccini, to advocate for progress in the skilled trades for tradeswomen. OBCT’s top priorities include:… Read More…