Ontario’s Electricity System Moves Forward with Largest Energy Storage Procurement Ever in Canada in 2023

June 1, 2023

System

Independent Electricity System Operator announces 739 MW of energy storage projects to support reliability and sustainability goals.

the Independent Electricity System Operator (IESO) announced it is moving forward with the procurement of seven new energy storage projects to provide 739 MW of capacity. After years of stable supply, Ontario’s electricity system is in the early stages of a dramatic transformation to support decarbonization and economic growth.

Electricity demand in Ontario is set to increase significantly in the next two decades as the economy grows and many fossil fuel-dependent processes switch to electricity. The IESO forecasts electricity demand to increase two per cent annually over the next 20 years.

Growing Ontario’s Storage Capability

The IESO is offering contracts to seven battery storage facilities located throughout the province, varying in size from 5 MW to 300 MW. These facilities will serve to meet both province-wide and local needs in a number of key locations. The majority of these selected proposals have partnered with Indigenous communities, with five of the seven having at least 50 per cent economic interest from these communities. These projects complement the recent agreement for the 250 MW Oneida Energy Storage Facility and conclude the first of two stages within the procurement.

Storage facilities charge up during off-peak hours, taking advantage of Ontario’s clean energy supply mix, and inject energy back into the grid when it is needed most. As a result, the grid will benefit from using more non-emitting energy at peak. Grid-scale energy storage also offers the potential to provide critical flexibility to help keep the system in balance.

Natural Gas as a Transitional Resource

The IESO is also leveraging natural gas generation by securing 586 MW from expansions and upgrades at existing sites. Natural gas currently plays a pivotal role in supporting grid reliability – with the ability to respond to changing system needs in ways other forms of supply can’t.

In its Pathways to Decarbonization report, the IESO identified the potential to eliminate emissions from Ontario’s electricity system – but only after a transition that sees natural gas generation maintain reliability until nuclear refurbishments are complete and new non-emitting technologies such as storage mature.

Over the next few months, the IESO will also launch new energy-efficiency programs and announce new hydrogen projects, further positioning the province’s electricity system to decarbonize.

Additional Resources

Fast Facts

  • Ontario currently has 228 MW in storage capacity on the grid, generated mostly at the pumped storage Sir Adam Beck facility in Niagara.
  • By 2026, the IESO anticipates that Ontario will have at least 1,217 MW of storage capacity participating in the IESO’s electricity market – in addition to smaller storage installations that serve local communities, businesses and homes.
  • Additional selected proponents with storage projects from this current procurement may be announced this summer. The IESO will also seek further energy storage supply in a procurement to begin later this year.

Quotes

“Today’s announcement of the largest energy storage procurement ever in Canada, positions Ontario as a leader in integrating renewable energy sources into our grid. We recognize the vital role energy storage plays in the decarbonization effort and in ensuring a stable and reliable energy supply.”

“This important announcement also highlights the affordability of energy storage solutions, demonstrating that they can compete on cost with other resources. By investing in energy storage, we can meet our growing energy needs while also driving economic growth and reducing our carbon footprint. At the IESO, we remain committed to pioneering innovative energy solutions that can help us build a cleaner, more sustainable energy future.”

– Lesley Gallinger, President and CEO of the IESO

Source

Related Articles


Latest Articles

  • Stephanie Medeiros on EV Infrastructure in Canada, Innovative Technologies, Well-Planned Charging Networks, & Commercial Fleets

    Stephanie Medeiros on EV Infrastructure in Canada, Innovative Technologies, Well-Planned Charging Networks, & Commercial Fleets

    September 3, 2026 By Blake Marchand In this Q&A with Stephanie Medeiros, the Head of Mobility at Schneider Electric Canada provides insight into her perspective on EV charging infrastructure in Canada, factors that will contribute to growing EV adoption, grid modernization for commercial fleets, the role of Vehicle-to-Grid and other innovative approaches to electrification. The focus of… Read More…

  • LEDVANCE: Understanding Light Beam Angles

    LEDVANCE: Understanding Light Beam Angles

    September 3, 2026 Light Beam Angles: How It Affects Different Types of Lighting, Where It Is Applied & What to Consider When Choosing the Right One Beam angle is important in lighting design. It determines how light spreads within a space and influences both functionality and atmosphere. By understanding beam angles, you can achieve both… Read More…

  • ITC 101 Series: Why Certifications (UL, CSA) Matter in Industrial Components

    ITC 101 Series: Why Certifications (UL, CSA) Matter in Industrial Components

    September 2, 2026 By ITC Electrical Components When selecting industrial electrical components, certification is more than a logo on a datasheet. A certification mark indicates that a product or component has been independently evaluated against specified requirements for its intended market. In North America, selecting products with the appropriate certification can affect regulatory acceptance, equipment… Read More…

  • Project Spotlight: Leigh Square Fountain

    Project Spotlight: Leigh Square Fountain

    September 2, 2026 In spring 2025, the City of Port Coquitlam unveiled a transformed Leigh Square, reimagined as a vibrant, accessible, and welcoming gathering place in the heart of downtown. At the heart of the renewed plaza, a Bellagio-style programmable dancing fountain is integrated directly into the paving—three interlocking rings where jets rise, fall, and… Read More…


Changing Scene

  • 2026 Ontario Apprenticeship Awards Call for Nominations

    2026 Ontario Apprenticeship Awards Call for Nominations

    September 3, 2026 Skilled Trades Ontario is proud to open nominations for the 2026 Ontario Apprenticeship Awards, recognizing outstanding apprentices, journeypersons, organizations and skilled trades leaders who are helping strengthen Ontario’s apprenticeship system. Award recipients will be announced at the Ontario Apprenticeship Summit on November 4, 2026, at the Toronto Congress Centre. Nominations must be submitted… Read More…

  • Bartle & Gibson Announces New Partnership with Hubbell Canada

    Bartle & Gibson Announces New Partnership with Hubbell Canada

    September 3, 2026 Bartle & Gibson Co. Ltd., an Alberta-based premier plumbing, heating and electrical distributor and Hubbell Canada have announced a new regional partnership enabling increased access to Hubbell Canada’s end-to-end electrical product portfolio across Western Canada. “With our strong presence in the west through 31 branches and counting located in Alberta, Saskatchewan, British… Read More…

  • Bartle & Gibson Opens Salmon Arm Location

    Bartle & Gibson Opens Salmon Arm Location

    September 3, 2026 Bartle & Gibson opened their new Salmon Arm location on July 20th. The Salmon Arm location features: This site is strategically positioned in the city of Salmon Arm, located near to the busy Picadilly Mall.  Salmon Arm branch is located at: 621- 10 Street SW Salmon ARM, BC V1E 1T1 Photo Source Read More…

  • MacKinnon Magnetics Announces Partnership with Resilient Sales Corporation in Northeastern Ontario

    MacKinnon Magnetics Announces Partnership with Resilient Sales Corporation in Northeastern Ontario

    September 3, 2026 MacKinnon Magnetics is pleased to welcome Resilient Sales Corporation as their newest sales agency partner. Resilient Sales will represent MacKinnon Magnetics across Northeastern Ontario, including the Districts of Muskoka and Parry Sound. Key markets include Sudbury, North Bay, Timmins, Kirkland Lake, Sault Ste. Marie, Huntsville, Bracebridge and Parry Sound. “This partnership expands… Read More…