Valard Construction Selected by Statnett for Construction of the Fjotland-Ertsmyra-Lyse-Duge Transmission Line

Valard Construction

May 18, 2016

Valard Construction announced that it has been selected by Statnett to construct the Fjotland-Ertsmyra-Lyse-Duge Transmission Line. The project is part of Statnett’s larger Vestre korridor or West Corridor Project.

Valard’s scope of work includes the construction of over 100 kilometers (km) of new 420 kilovolt (kV) alternating current (AC) transmission line and the decommissioning of approximately 90 km of existing 300 kilovolt (kV) transmission line. Construction is expected to begin later this year and is expected to be complete at the end of 2021.

“This project is a good fit given Valard’s extensive transmission construction experience as well as with our growth strategy,” said Adam Budzinski, President of Valard Construction. “We appreciate the confidence Statnett has placed in us for this project and look forward to continuing our positive relationship with them and the people of Norway.”

The project consists of over 100 km new 420 kV AC overhead transmission lines:
• Duge – Lyse 17 km
• Lyse – Tjørhom 25 km
• Tjørhom – Ertsmyra 27 km
• Ertsmyra – Fjotland 20 km
• Re-routing Lysebotn and Fjotland 12 km
• New line construction 2016‐2019

Other project details include:
• Decommissioning of approximately 90 km of existing 300 kilovolt (kV) transmission line
• High altitude construction areas
• Significant use of helicopters for construction and decommissioning
• Decommissioning 2019‐2021.

This contract has been awarded after being approved by Statnett’s Board of Directors.

 

 

Related Articles


Latest Articles


Changing Scene

  • CSA Group Receives Greater Toronto’s Top Employers Award for 10th Consecutive Year

    CSA Group Receives Greater Toronto’s Top Employers Award for 10th Consecutive Year

    December 15, 2025 For the tenth consecutive year, CSA Group has been awarded as one of Greater Toronto’s Top Employers for 2026 by Mediacorp Canada Inc. This milestone reflects CSA Group’s continued commitment to fostering a workplace culture that supports employee wellbeing, professional growth, and community engagement. CSA Group’s global headquarters, located in Toronto, offers… Read More…

  • Hydro Ottawa to Use AI-Enhanced Predictive Analytics to Improve Energy Efficiency

    Hydro Ottawa to Use AI-Enhanced Predictive Analytics to Improve Energy Efficiency

    December 15, 2025 With $6 million in federal funding, Hydro Ottawa is introducing the Ottawa Distributed Energy Resource Accelerator (ODERA) program. Through this program, Hydro Ottawa will use AI-enhanced predictive analytics to accurately forecast peak demand, which will then inform the real-time balancing of supply and demand. This will be achieved by using a technology… Read More…

  • Stanpro’s Katy’s Donation Day Breaks Record, Giving Back to Communities Across Canada

    Stanpro’s Katy’s Donation Day Breaks Record, Giving Back to Communities Across Canada

    December 15, 2025 Stanpro is proud to announce the results of its annual Katy’s Donation Day, held on December 3, 2025. This year, the initiative resulted in a record donation of over $100,000, making this the highest contribution in the history of this program. The funds raised will be distributed to over 80 charitable organizations… Read More…

  • EB Horsman Introduce Cory Carter as New Victoria Branch Manager

    EB Horsman Introduce Cory Carter as New Victoria Branch Manager

    December 15, 2025 EB Horsman is pleased to announce the appointment of Cory Carter as Branch Manager of our Victoria location, effective November 10, 2025. With over two decades of experience in the electrical, lighting, and retail industries, Cory brings a proven track record of leadership, sales growth, and customer relationship management. Throughout his career,… Read More…