Ontario Making it Easier to Build Electric Vehicle Charging Stations

Government of Ontario

The Ontario government is making it easier to build and connect new public electric vehicle (EV) chargers to the province’s world-class clean electricity grid. Starting May 27, 2024, all local utilities will follow a streamlined process for EV charging connections that will make it easier to set up new charging stations and support the adoption of electric vehicles in Ontario.

“As the number of EV owners in Ontario continues to grow, our government is making it easier to put shovels in the ground to build the critical infrastructure needed for drivers to charge their vehicles where and when they need to,” said Todd Smith, Minister of Energy. “This is just another step we are taking to reduce red tape, increase EV adoption, and use our clean electricity supply to support the electrification of Ontario’s transportation sector.”

Today, each of Ontario’s 58 local electricity utilities have different procedures for connecting new public EV charging stations, with different timelines, information requirements and responsibilities for customers.

In response to Minister Smith’s Letter of Direction, which called on the Ontario Energy Board (OEB) to take steps to facilitate the efficient integration of EV’s into the provincial electricity system, the OEB issued provincewide, streamlined procedures that all local utilities must follow for installing and connecting new EV charging infrastructure. This new procedure includes the implementation of standardized forms, timelines, and information requirements which will make it easier for EV charging providers to deploy chargers in all regions of the province.

“Our government is paving the way to an electric future by building the EV charging infrastructure drivers need, where they need it,” said Prabmeet Sarkaria, Minister of Transportation. “By increasing the accessibility of public EV charging stations across the province, including for rural and northern communities, we are providing more sustainable and convenient travel options for drivers.”

“Having attracted over $28 billion in automotive investments in the last three years, our province is a leading jurisdiction in the global production and development of EVs,” said Vic Fedeli, Minister of Economic Development, Job Creation and Trade. “By making it easier to build public charging infrastructure, our government is supporting Ontario’s growing end-to-end EV supply chain and ensuring EV drivers can confidently and conveniently power their journeys.”

This initiative is part of the government’s larger plan to support the adoption of electric vehicles and make EV charging infrastructure more accessible, which includes:

  • The EV ChargeON program – a $91 million investment to support the installation of public EV chargers outside of Ontario’s large urban centres, including at community hubs, Ontario’s highway rest areas, carpool parking lots, and Ontario Parks.
  • The new Ultra-Low Overnight price plan which allows customers who use more electricity at night, including those charging their EV, to save up to $90 per year by shifting demand to the ultra-low overnight rate period when provincewide electricity demand is lower.
  • Making it more convenient for electric vehicle (EV) owners to travel the province with EV fast chargers now installed at all 20 renovated ONroute stations along the province’s busiest highways, the 400 and 401.

The initiative also builds on the government’s Driving Prosperity: The Future of Ontario’s Automotive Sector plan which aims to create a domestic EV battery ecosystem in the province and position Ontario as a North American automotive innovation hub by working to support the continued transition to electric, low carbon, connected and autonomous vehicles.


Quick Facts

  • As of December 2023, there are more than 150,000 EVs registered in Ontario, including both battery-electric vehicles (BEV) and plug-in hybrid electric vehicles (PHEV). By 2030, there are expected to be more than one million EVs on the road in Ontario.
  • The Ontario Energy Board’s new Electric Vehicle Charging Connections Procedures (EVCCP) applies to public charging connections including those found along highways and at service centres, workplace charging, multi-residential buildings and charging stations used for EV fleets.
  • On February 16, 2024, the OEB issued the final EVCCP that establishes requirements which LDCs must follow under the Distribution System Code (DSC). The amendments will come into force on May 27, 2024.

Source

Related Articles


Latest Articles

  • Lever Connectors and Twist-Ons: How to Decide Which is Right for the Job

    Lever Connectors and Twist-Ons: How to Decide Which is Right for the Job

    There are many different types of wire connectors, and sometimes it can be hard for electricians to determine which one is best to use. Read More…

  • Winnipeg Information Bulletin: Low-Risk Voice, Data, Video & Security System Installations

    Winnipeg Information Bulletin: Low-Risk Voice, Data, Video & Security System Installations

    September 17, 2026 Certain types of installations may qualify for a low-risk voice, data, video (VDV) and security system electrical permit. For information related to regular VDV/security system installations, see winnipeg.ca/vdvsystems. Applications must be submitted through Permits Online. Electrical permits and inspections are needed for certain installations of security and similar alarm systems. This makes… Read More…

  • What Type of Outdoor Light Do I Need for My Application?

    What Type of Outdoor Light Do I Need for My Application?

    September 17, 2026 By Stanpro The right outdoor light starts with the space you need to illuminate and how that space is used. For commercial projects, parking lots and large exterior areas point toward area lights; entrances and building perimeters toward wall-mounted or security lighting; signs, facades and targeted areas toward flood lights; pathways toward… Read More…

  • Alberta Employers and Tradespeople Share their Perspectives

    Alberta Employers and Tradespeople Share their Perspectives

    September 16, 2026 In Alberta’s skilled trades labour market employers and tradespeople are facing growing pressure from tariffs, rising costs, hiring challenges and labour mobility barriers. CAF-FCA’s new report, Hiring, Mobility and Needed Supports: Alberta Employers and Tradespeople Share Their Perspectives, takes a closer look at what’s happening on the ground. Based on surveys of… Read More…


Changing Scene

  • Government of Canada Introduces Legislation to Transform how Canada Builds

    Government of Canada Introduces Legislation to Transform how Canada Builds

    October 2, 2026 The world is changing rapidly. In response, Canada is focused on what we can control: building a stronger, more independent, and more sustainable economy. We are leveraging our strengths and moving with speed to open new markets, strengthen supply chains, accelerate projects, and unlock our natural resources. As we build, we are… Read More…

  • Ontario Awards Construction Contract for New Little Current Swing Bridge

    Ontario Awards Construction Contract for New Little Current Swing Bridge

    October 2, 2026 The Ontario government has named a construction manager for the Little Current Swing Bridge replacement project. The new bridge will replace the existing bridge on Highway 6 connecting Manitoulin Island to the mainland, providing reliable, year-round access to the provincial highway network and making it easier for workers and families to connect… Read More…

  • Construction Starting on new Pitt Meadows Secondary School in BC

    Construction Starting on new Pitt Meadows Secondary School in BC

    October 2, 2026 Construction is beginning on the new Pitt Meadows Secondary school, which will provide students with a safer and more modern environment to learn. “Pitt Meadows is a vibrant community with a bright future and I’m proud that the local high school will soon better reflect the community it serves,” said Lisa Beare,… Read More…

  • Major Construction Underway at Woodbine GO Station

    Major Construction Underway at Woodbine GO Station

    October 2, 2026 Major construction is underway at Woodbine GO Station, marking another significant milestone in the Ontario government’s plan to provide two-way, all-day service across core segments of the GO Transit network. Crews are now building station platforms that will connect thousands of daily riders to the Kitchener GO Line, Union-Pearson (UP) Express and… Read More…