OPG Celebrates the Early Completion of Darlington Unit 3

July 18, 2023

The second of four OPG refurbished reactors now re-connected to Ontario’s electricity grid

Ontario Power Generation (OPG) has achieved a major milestone by successfully connecting Darlington Nuclear Generating Station’s Unit 3 to Ontario’s electricity grid, 169 days ahead of schedule. This world-class project performance demonstrates OPG’s expertise and commitment to completing the station’s four-unit refurbishment safely, with quality and on budget, by the end of 2026.

Unit 3 is now the second Darlington unit to undergo complete refurbishment and is operating at 100 percent capacity, providing clean, reliable energy for Ontarians during these peak summer months. The early return of Unit 3 will produce an extra 3 terawatt-hours of energy, enough to power 350,000 homes for an entire year. It will also reduce up to 1 megatonne of greenhouse gas emissions, or the equivalent of taking 300,000 cars off the road for an entire year.

Unit 2 was completed in early June 2020. Thanks to the quality of refurbishment work, in the three years since its return to service, Unit 2 has experienced a record 529-day continuous run. This is industry-leading performance for a CANDU reactor post-refurbishment. Overall generation was also 10 plus percent better than target.

Unit 1 refurbishment, expected to be completed mid-2025, is approximately 60 percent complete and is currently in the reassembly phase. Unit 4, the last of Darlington’s four reactors, will come offline shortly to begin its refurbishment.

Once complete, a refurbished Darlington Nuclear Generating Station will provide more than 30 years of carbon-free power. The Refurbishment project, together with the station’s extended operation, will generate approximately $90 billion in economic benefits for Ontario and create an average of 14,200 jobs annually across the province.

Quick Facts

Quotes

“Through this project, OPG is demonstrating that with detailed planning and preparation, large nuclear projects can be completed not only on-time, but ahead of time and with great quality,” said Ken Hartwick, OPG’s President and CEO. “This would not be possible without the performance, expertise, and commitment from our refurbishment project team, project partners, industry experts, energy professionals, and skilled tradespeople.”

Ken Hartwick, OPG’s President and CEO

“The successful refurbishment of Darlington’s Unit 3 ahead of schedule and on-budget will help power the next major international investment in Ontario, the new homes we are building, and industries as they grow and electrify,” said Todd Smith, Minister of Energy. “It’s also proof that this province can deliver the major energy projects we have planned to Power Ontario’s Growth on-time and on-budget, including building a total of four Small Modular Reactors at Darlington, and beginning pre-development work to site Canada’s first large-scale nuclear build in over three decades.”

Todd Smith, Minister of Energy

Source

Related Articles


Latest Articles


Changing Scene

  • LEDVANCE Canada Announces Leadership Updates

    LEDVANCE Canada Announces Leadership Updates

    February 19, 2026 LEDVANCE Canada is sharing two leadership updates that further strengthen support for customers and channel partners across the country. Lori Bagazzoli has been appointed Head of Strategic Sales – LEDVANCE Canada, with a focus on expanding support for the Project and Specification market and accelerating growth in strategic opportunities. In this role, Lori Bagazzoli Read More…

  • Franklin Empire Inc. Announces Acquisition of O’Neil Electric Supply, Strengthening its Presence in Ontario and Eastern Canada

    Franklin Empire Inc. Announces Acquisition of O’Neil Electric Supply, Strengthening its Presence in Ontario and Eastern Canada

    February 18, 2026 Franklin Empire Inc., a leading independent electrical distributor in Eastern Canada, is proud and excited to announce that it has entered into a definitive agreement to acquire O’Neil Electric Supply, an Ontario-based electrical distributor, subject to customary closing conditions, including receipt of required regulatory approvals. This strategic acquisition further strengthens Franklin Empire’s Read More…

  • Nominations Now Open for 8th Biennial MEET Innovation Awards

    Nominations Now Open for 8th Biennial MEET Innovation Awards

    February 13, 2026 The Mechanical Electrical Electronic Technology Show (MEET) is pleased to announce that the ‘MEET Innovation Awards’ will return as part of the 2026 edition of the show. The purpose of these awards is to recognize innovative products in the industry. Individuals and businesses are encouraged to nominate themselves or others by completing this online form no Read More…

  • 2026 ECABC Hall of Fame Nominations

    2026 ECABC Hall of Fame Nominations

    February 12, 2026 On June 2nd, ECABC will hold a Hall of Fame Induction Ceremony as part of their Awards Gala Dinner at the Association’s 2026 Conference and AGM in Kelowna. ECABC would like to invite you to nominate an extraordinary individual from the electrical industry to join the organizations esteemed Hall of Fame! Induction into the Read More…