Case Study: Temporary Power for Large Scale Residential Construction

Temporary Power

Ever wonder how large construction projects with sales offices and show suites get power when there is only a generator or temporary power established on the construction site?TheBC Safety Authority (BCSA) pays close attention to these types of installations, since fire alarms, sprinklers, and other building code safety systems are not up and running during the construction phase of the project.

Recently, a BCSA safety officer conducted an assessment of a large multi-family residential site under construction. Working collaboratively with electrical contractors, other trades, safety officials, utilities, and building departments to reach safety solutions is an important part of a BCSA safety officer’s role.

During the inspection, several significant hazards were found.Most notably, townhouses had been energized using the temporary construction service, creating a risk of overload to the service. Had these dwellings become occupied, this could have resulted in a serious fire and shock hazard.

An additional hazard was created by the power cable used to provide power from the temporary distribution system to the townhouses, which was not installed with the necessary mechanical protection.Construction sites typically have heavy machinery operating and it is imperative that the power cables be installed in a manner that protects them from mechanical damage.A break in the armoured cable can result in either a fire (if combustible material is near by) or a shock hazard if the bonding provisions have been compromised.

Addressing the hazards
The safety officer first documented his findings in a certificate of inspection and contacted the electrical contractor to develop a plan to rectify the identified non-compliances.The contractor submitted an application for a variance, as required by the Safety Standards Act, to energize the show rooms and sales offices.The variance included a request to energize a specific portion of the site, and outlined the wiring method used to provide power to this area of the site, and the signage required at strategic locations on the site, including mark ups on the site’s safety plans.The safety officer granted the variance and the electrical contractor completed the installation and the obligations outlined in the variance.

To reduce the safety hazards on the site, branch circuits inside each dwelling had all unnecessary circuit conductors disconnected from circuit breakers. The heavy loads such as space heating, furnaces, dryers, ranges were also disconnected.The safety officer then informed BC Hydro and the electrical contractor that a “hold connection” be placed on the permanent installation permit.This ensures that when the permanent installation is ready for power, the necessary work is completed to transfer and disconnect the temporary power in the showrooms to remove the risk of a possible back feed.

When dealing with sites that have both permanent and temporary electrical systems, closely review your electrical code, specifically the stating that interconnection of temporary power installations and permanent installations shall not be interconnected unless by special permission.

This article was first published online by the BC Safety Authority, http://safetyauthority.ca.

 

Related Articles


Latest Articles

  • efficiencyPEI once again Recognized as National Leader in Energy Efficiency

    efficiencyPEI once again Recognized as National Leader in Energy Efficiency

    August 25, 2025 efficiencyPEI was recognized with a national award for its work in providing Islanders with energy efficiency information and programs.  The ENERGY STAR® Canada Awards acknowledge outstanding contributions to protecting the environment through superior energy achievements. This year, efficiencyPEI received the Advocate of the Year award.  efficiencyPEI has won a total of 10 ENERGY STAR… Read More…

  • Ontario Solar Incentives with Essex Energy

    Ontario Solar Incentives with Essex Energy

    August 20, 2025 Essex Energy is helping municipalities, universities and colleges across Ontario take advantage of incentives under Ontario’s Retrofit DER Program including solar photovoltaic (PV) systems. What’s Available Significant rebates available to eligible businesses and institutional organizations deploying rooftop or parking lot solar PV systems. These incentives are paid upon completion of the project, accelerating project… Read More…

  • Beyond the Bid: How Modern Estimating Solutions Drive Contractor Success

    Beyond the Bid: How Modern Estimating Solutions Drive Contractor Success

    August 18, 2025 By Brooke Stewart In today’s fast-paced construction landscape, electrical contractors are constantly pressured to keep their estimates competitive, often at the expense of healthy profit margins. Compounding this challenge are rising material costs, a shortage of skilled labor and siloed data, all of which make it increasingly difficult to stay competitive and… Read More…

  • Hammond Power Solutions Helps EFC Champion Sustainability as First Carbon Neutral Sponsor at Annual Industry Conference

    Hammond Power Solutions Helps EFC Champion Sustainability as First Carbon Neutral Sponsor at Annual Industry Conference

    August 18, 2025 By Electro-Federation Canada Did you know that carbon emissions from this year’s Annual Industry Conference were offset? With the help of Hammond Power Solutions (HPS), EFC took an important step toward reducing our environmental impact by offsetting the emissions associated with the event. This milestone reflects a growing commitment within the electrical… Read More…


Changing Scene

  • New Solar Lighting Manufacturer, Solvic Joins Contact Delage

    New Solar Lighting Manufacturer, Solvic Joins Contact Delage

    August 25, 2025 Contact Delage are excited to announce the addition of a new trusted partner to their lineup: Solvic, an innovative manufacturer specializing in solar lighting. This new partnership reflects Contact Delage’s ongoing commitment to offering sustainable, high-performance solutions tailored to real-world applications. With Solvic, they’re expanding their range of autonomous solar products—perfect for lighting… Read More…

  • CMEQ Welcomes the Announcement of a $250M Investment for Training the Next Generation

    CMEQ Welcomes the Announcement of a $250M Investment for Training the Next Generation

    August 25, 2025 Hydro-Québec and the Ministry of Education (MÉQ) will jointly invest $250 million to encourage more young people to enroll, in particular, in the electricity training program (DEP) within the Vocational Training Centers. “This is excellent news that will ultimately allow all electrical contractors to benefit from a larger pool of labor to… Read More…

  • Hydro-Québec Calls for Energy Efficiency Measures

    Hydro-Québec Calls for Energy Efficiency Measures

    August 25, 2025 Hydro-Québec is reiterating various energy efficiency requests to the Régie de l’énergie. These measures include a residential program offering access to smart thermostats at $0, available to both homeowners and tenants. Hydro-Québec also wishes to offer financial support for the purchase of solar panels of $1,000 for each kW installed, subject to… Read More…

  • Prompt Payment Regulations Come into Force on 8 September in Quebec

    Prompt Payment Regulations Come into Force on 8 September in Quebec

    August 25, 2025 Quebec’s prompt payment legislation, the Regulation respecting payments and the rapid settlement of disputes in construction work by the Government of Quebec, is scheduled to come into force on September 8, 2025. This new regulation establishes a regime for the timely payment of sums of money owed to companies involved in carrying out… Read More…