Case Study: Guildford, BC’s Recreation Centre Aquatic Addition

December 12, 2016

The Guildford Recreation Centre Aquatic Addition expands an existing facility in Surrey, BC. The 7,000 square meter addition was designed as a destination aquatic facility for both recreation and therapeutic users, offering a 50m Federation Internationale de Natation (FINA) certified lap pool as well as a leisure pool that contains a therapeutic area, waterslide, family friendly hot tub, and children’s area.

The City of Surrey’s initial project objectives were to increase the value of the facility to the city and the community, reduce waste, and maximize efficiency. Surrey’s “Wood First Policy” was achieved in the design of the Guildford Recreation Centre Aquatic Addition, which incorporated the lighting and HVAC for the natatorium. Initially destined to be open web steel joist, the final product consists of three dimensional timber trusses. The trusses were pre-assembled offsite, which allowed for easier installation, reduced waste and cost, and saved construction time to help with the accelerated schedule. This solution became a defining feature of the Guildford Aquatic Centre.

The project earned an IES Edwin R. Guth Award for Interior Lighting Design. 

Project objectives, solutions and achievements

A primary goal of the Guildford Recreation Centre Aquatic Addition was to create a building that would provide the public of all ages with a welcoming swimming pool, where they can compete, exercise, play, and relax. The City of Surrey wanted the lap pool designed to FINA swimming pool guidelines in order to host FINA competitions within the facility, allowing both the public and competitors to enjoy their activities within the same versatile facility.

Electrical engineering design was of key importance to this project in order to meet the competition lighting levels as well as the architectural intent. Meeting the client’s objectives of an aesthetically pleasing and versatile swimming pool, while staying within the energy code requirements, and budget, required creative solutions to minimize equipment costs and maximize equipment efficiency.

AES Engineering Ltd. (AES) worked with other project team members, such as the architectural and mechanical teams, on how their system and design selections would ultimately govern the lighting design throughout the building. Working together in an integrated environment, AES proposed using indirect high efficiency lighting that would create a soft diffused light that would provide the swimming pool with a pleasant glare free light and competition lighting levels, while remaining within energy use requirements.

Light output was maximized through the use of lighting modelling software, high reflectivity paint, high efficiency luminaires, and optimal mounting angles.

Working closely with the multidisciplinary team allowed all systems within the trusses and coves to be configured such that maximum light output was achieved, resulting in a lower overall energy consumption throughout the facility. Various dimensions, angles, material types, and finishes were modelled for the coves and trusses to achieve optimum design characteristics and maximize light output. The resulting design provides the public with comfortable levels of lighting while using minimal amounts of energy.

Project management was crucial to keeping the project on schedule and on budget as the City of Surrey had set an accelerated timeline. In order to meet this, the project had to be designed in multiple packages. The foundation package was designed first, well in advance of the systems inside the building, while the second package contained the remainder of the project design. AES worked in a construction management environment, with contractors who could advise what materials would be available in time to fit the schedule. The prime consultant’s project schedule and AES’s internal deadlines allowed the project to reach substantial completion by the City of Surrey’s deadline.

Technical excellence/innovation: electrical

• Computer modelling — AES utilized various software tools to maximize the light output from both the coves and the trusses. Modelling of various lighting types at multiple angles and positions helped determine which luminaire and layout would provide the best light quality and efficiency within the trusses. To further increase the light output from the truss lighting system, high reflectivity paint was selected and specified by the architect, and the lights were mounted at optimal angles to maximize the amount of light reflected onto the pool. The resulting truss lighting system provides the swimming pool with a very pleasant and even light.

• Low voltage lighting controls — the use of low voltage (LV) lighting controls provided flexibility to the truss lighting system. Three levels of lighting have been implemented within the space to provide selection options to suit its current use. Traditionally, lights are switched in rows or groups, but the lights in the trusses have been configured to switch in an interweaving pattern so that an even light output is achieved no matter what level of light is selected. Providing an even illumination using a minimal number of lights reduces overall energy consumption without sacrificing comfort or safety. The LV system is also scheduled to sweep off all lights when not required, further reducing the carbon footprint of the facility. 

• LED lighting — another energy saving measure includes the use of LED underwater lights rather than traditional halogen lighting. The LV lighting system is also tied in to the underwater lights to provide two user selectable lighting levels.

• Occupancy sensors — working in combination with the LV lighting system, occupancy sensors within enclosed offices, meeting rooms, and washrooms, automatically turn off lights to provide maximum energy savings.

 

A sampling of project luminaires

Among the luminaires used for the project are the following:

• Bartco BFL206 Linear T5s

• Cole Lighting L500 LED Steplites

• Focal Point Avenue D MR 16

• Green Imagetech GX436 vapourproof luminaires

• Kenall Mighty Mac WCBU Series

• Lithonia Lighting AS1 LED, FEM 2s, 4s and 8s, MRP Omero LED, Saturn compact DTT fluorescent, 

• Metalumen Grande RM4DOD

• Pace Illumination Avante-Garde AGSM surface mount

• Paco Lighting Puac T5s and T8s

• Rigalite MHD2/MHDO Series

• Sistemalux Megaeos and Megabrique 

• USAI Lighting BeveLED 2.0

• Winona Winline 309W linear LEDs

 

Project members

• Electrical engineer: AES Engineering Ltd. 

• Project owner/client: City of Surrey 

• Architects: Bing Thom Architects, Shape Architecture 

• Prime consultant: Bing Thom Architects 

• Other consultants involved: The AME Consulting Group Ltd., Fast + Epp, 

• Turnbull Construction Project Managers 

• Contractors: Heatherbrae Builders 

• Photographer: Ema Peter

 

Related Articles


Latest Articles

  • G5 Series from Eralux Illuminates the Oshawa Library

    G5 Series from Eralux Illuminates the Oshawa Library

    November 25, 2024 Eralux is proud to present its latest project with the G5 Series at the Oshawa Library to improve the atmosphere and use of public spaces. Located in downtown Oshawa, Ontario, the library is a center for learning and creativity. Now that Eralux’s innovative lighting solution has been introduced, the library experience is… Read More…

  • Ontario Drives Growth in Residential Building Construction in September

    Ontario Drives Growth in Residential Building Construction in September

    November 25, 2024 Investment in building construction rose 2.1% to $21.6 billion in September, following a 0.2% increase in August. The residential sector increased 2.9% to $15.2 billion in September, while the non-residential sector edged up 0.3% to $6.4 billion. Year over year, investment in building construction grew 6.7% in September. On a constant dollar basis (2017=100), investment in building construction increased 1.6% from… Read More…

  • Ontario’s Institutional Construction Intentions Push up the Non-Residential Building Permits in September

    Ontario’s Institutional Construction Intentions Push up the Non-Residential Building Permits in September

    November 25, 2024 The total value of building permits in Canada increased by $1.3 billion (+11.5%) to $13.0 billion in September, reaching the second-highest level since the start of the new series in January 2017. Ontario’s construction intentions grew by $1.2 billion (+25.0%) to $5.9 billion in September 2024, leading gains in both the non-residential and residential sectors. On a constant… Read More…

  • Red Seal Self-Assessment Questions

    Red Seal Self-Assessment Questions

    November 25, 2024 Each trade’s self-assessment tool is available to help you understand your own readiness for challenging the Red Seal exam in that trade. It goes through all topics that are included in the trade’s standard (Red Seal Occupational Standard/National Occupational Analysis) and asks you to reflect on whether you have the experience and knowledge in each… Read More…


Changing Scene

  • EV ChargeON Community Sites Stream

    EV ChargeON Community Sites Stream

    November 25, 2024 Through the EV ChargeON Community Sites Stream, over 1,300 new EV charging ports have been approved at sites across the province. The Ontario government is investing $63 million to help build electric vehicle (EV) charging ports in communities with less than 170,000 people, including Indigenous communities. This will increase access to EV… Read More…

  • ITC Electrical Components Celebrates 30 Years of Service to the Electrical, Automation and OEM Market in Canada

    ITC Electrical Components Celebrates 30 Years of Service to the Electrical, Automation and OEM Market in Canada

    November 25, 2024 Celebrating its 30th anniversary, ITC Electrical Components has recently launched its new and improved website at www.itcproducts.com. After a successful 15-year career in the electrical components industry Luca Fontana founded ITC Electrical Components in 1994.  Since that time the company has grown from a home-based operation to a successful business with 15 employees and… Read More…

  • Eaton Canada Investing $15m to Expand Manufacturing Capacity

    Eaton Canada Investing $15m to Expand Manufacturing Capacity

    November 25, 2024 Eaton Canada is investing approximately $15 million to expand manufacturing capacity to meet growing demand for its electrical solutions driven by the ongoing electrification of Canada’s economy. These investments will expand the company’s low-voltage manufacturing footprint by 20%, increasing its ability to produce the switchboards, switchgear and panelboards needed to support Canada’s… Read More…

  • Bartle & Gibson Announces Partnership with Electric Avenue

    Bartle & Gibson Announces Partnership with Electric Avenue

    November 25, 2024 Bartle & Gibson Co. Ltd., a Western Canada-based premier plumbing, heating and electrical distributor, proudly announced a new regional partnership to distribute Electric Avenue, providers of convenient, affordable and easy-to-use smart charging solutions for residential and commercial use, across Western Canada. Electric Avenue was founded in 2021 with one simple mission: to… Read More…