Prince Edward Island has begun on one of the largest construction projects in its history — replacing and upgrading undersea electrical connections between PEI and New Brunswick.
The Interconnection Upgrade Project, a joint effort with the federal government, will allow PEI to import electricity from New Brunswick through two new 180 MW submarine cables, overhead transmission lines, substation upgrades and more. The submarine cables will be owned by the province and leased to and operated by Maritime Electric. Project costs have been estimated at between $120 million and $140 million.

When the existing submarine cables were installed nearly 40 years ago, the electricity load was 95 MW. In 2015, it peaked at 262 MW. PEI has no natural energy supply sources and relies on off island sources for cost-effective and reliable energy supply. While the province has developed significant wind energy supply, this supply requires back up for times when there is no wind.

The project offers at least five benefits:
• enabling future electrical growth on PEI
• improving reliability for customers
• reducing reliance on fossil-fueled generation
• creating a secure, reliable connection to the mainland
• providing access to a more economic energy supply

What’s involved

The project requires
• installation of two 180 MW submarine cables between Borden, PEI and Cape Tormentine, NB, (16.5 km) in the Northumberland Strait
• construction of 60 km of new overhead transmission line between Cape Tormentine and Memramcook
• construction of a substation extension at Borden, PEI

The project also includes:
• two landfall sites (where the submarine cable trench is brought ashore)
• two termination sites (for converting submarine cables to overhead transmission lines or substation)
• upgrading of the New Brunswick Power Corporation (NB Power) substation in Memramcook, NB

The first construction phase involves pre-trenching. This process involves a marine excavator called a Starfish and two mechanical marine dredges: one at PEI’s Borden-Carleton site and the other at New Brunswick’s Cape Tormentine site.

On the Cape Tormentine side the Starfish will be used excavate approximately 600 metres from shore into the Northumberland Strait. Once that distance is reached the Starfish will be shipped to the PEI side and the mechanical marine dredge will continue to excavate to the 1.8 km mark offshore.

The Starfish will be in operation for 12 hours daily for excavation. The two mechanical marine dredges will be working 24 hours per day on excavation. This process, expected to take 6-8 weeks, will ensure there are no rock obstructions along the route when the cable is laid in mid October.

The two cables will be installed under the seabed in separate trenches, up to 200 m apart. In water depths of greater than 12 m the cables will be buried at 0.6 m, while in areas of less than 12 m of water the cable will be buried at approximately 2 m. Excavating within the marine environment will involve trenching with excavators in water depths up to 2 m and a trenching remotely operated vehicle (TROV) with a saw cutter for the remaining sections. Exclusion zones around the cables are not planned. There will be no fishing restrictions. Once the cables have been installed, navigation charts will be updated.

The entire project is scheduled for completion in late spring or early summer 2017.

 

 

Related Articles


Latest Articles


Changing Scene

  • Saskatchewan Investing in Skills Training

    Saskatchewan Investing in Skills Training

    March 28, 2025 Guided by Building the Workforce for a Growing Economy: the Saskatchewan Labour Market Strategy, the Ministry of Immigration and Career Training is investing more than $117.0 million in programs and services. “We continue to make training available for Saskatchewan people to prepare for the record number of jobs being created by our growing… Read More…

  • New Skilled Trades and Technology Building for the New Saskatchewan Polytechnic Joseph A. Remai Saskatoon Campus Proceeding to Request for Proposals

    New Skilled Trades and Technology Building for the New Saskatchewan Polytechnic Joseph A. Remai Saskatoon Campus Proceeding to Request for Proposals

    March 28, 2025 Three teams are advancing to the next stage of procurement for the new Skilled Trades and Technology building for the Saskatchewan Polytechnic, Joseph A. Remai Saskatoon Campus. Upon procurement completion, the successful proponent will be awarded the design and construction of the new Trades building under a Design-Build agreement.  “This project is… Read More…

  • New Brunswick Legislation Introduced to Support Interprovincial Labour Mobility

    New Brunswick Legislation Introduced to Support Interprovincial Labour Mobility

    March 28, 2025 The New Brunswick government has introduced legislative amendments to improve labour mobility and reduce interprovincial barriers. “With potential tariff-related disruptions and an uncertain economic climate, workers and businesses need the ability to adapt quickly to quickly changing circumstances,” said Jean-Claude D’Amours, acting minister of post-secondary education, training and labour. “A flexible and… Read More…

  • New Brunswick Electric Vehicle Incentive Will End July 1

    New Brunswick Electric Vehicle Incentive Will End July 1

    March 28, 2025 The New Brunswick provincial government will end its Electric Vehicle Incentive Program on July 1. “This rebate program made it possible for many New Brunswickers to buy an electric vehicle during their introduction to the market, and is helping reduce greenhouse gas emissions,” said Finance and Treasury Board Minister René Legacy, who… Read More…