Improving Arc Flash Prevention and Safety

November 14, 2016

By Steve Sullivan

Working among the electrical components in an enclosure comes with inherent risks. The power in any one enclosure can range from 2kw up to 200kw depending on the power density. One of the most common and dangerous risks is an arc flash (or flashover).

When an explosive release of energy erupts from a phase-to-phase or phase-to-ground arc fault, the results range from devastating to deadly. This air to ground electrical explosion is a critical concern.

The destructive force of an arc flash

The dangers from an arc flash are all too well known. When metal expands and vaporizes at the fault, it causes extreme heating of the air, upwards of 10,000°C/18,032°F. The concussive pressure wave can knock personnel off their feet; the ultraviolet light flash can cause blindness; the sound blast, deafness; and the molten metal and heat can cause second and third degree burns. The specific death toll has been estimated to be up to 1-2 people every day worldwide.

An arc flash can result from unsafe work procedures, accidental contact, or more systemic problems such as corrosion of components and connections or insulation failure. Arc flash prevention should be incorporated into any application from the beginning of the design process.

Minimizing arc flash exposure

Design and retrofit approaches can limit exposure by using components installed outside the enclosure to permit qualified personnel in personal protective equipment (PPE) to service equipment inside without opening the enclosure door. Interface flaps and window kits permit data retrieval, equipment monitoring or routine maintenance to be performed from outside. Collapsible fold down shelves be raised for use with laptops and monitoring equipment. External data pockets can hold wiring diagrams, operation manuals and other documents.

Arc flash protection

Sometimes components must be accessed from inside the enclosure. For example, Rittal’s arc flash solution keeps high and low voltage equipment within the confines of their own respective enclosures. Low voltage enclosures house equipment that is used for programming, data acquisition and system adjustment.

High voltage components are isolated within their own disconnect enclosure, while line side power is segregated within the power isolation enclosure. A partition wall acts as a barrier to high voltage line side power. An interlocking door system ensures that the high voltage enclosure cannot be opened while the disconnect switch is in “ON” position.

For additional safety, all interlocked doors and master door must be closed in order to re-energize the enclosure. This removes potential for accidental contact with the inline power when the disconnect enclosure is put in a safe power-off position, and locked and tagged out.

Minimizing exposure to line side power can help protect personnel from accidents. A qualified person wearing PPE and following appropriate safe work practices can perform visual inspections and tasks, such as diagnosis, testing, troubleshooting and voltage measurement with the door open even when the main enclosure is energized.

Safety is always your priority, so download Rittal’s Arc Flash and How to Prevent it free whitepaper for the first step towards arc flash prevention: http://info.rittalenclosures.com/arch-flash-lp-0.

Steve Sullivan is a training manager with Rittal. This article was first published online as a blog: http://blog.rittalenclosures.com/blog/author/steve-sullivan-training-manager.

 

Related Articles


Latest Articles


Changing Scene

  • Hammond Power Solutions Appoints Linda Nadeau Sanford as Western Regional Sales Manager

    Hammond Power Solutions Appoints Linda Nadeau Sanford as Western Regional Sales Manager

    May 12, 2025 Hammond Power Solutions (HPS), a leader in dry-type transformers and power quality solutions, is pleased to announce the appointment of Linda Nadeau Sanford as the new Western Regional Sales Manager. Linda will play a key part in driving sales and revenue across the Western Canada region. She will oversee territory management, advance… Read More…

  • Susanna Zagar, Ontario Energy Board CEO, Named EHRC’s 2025 Agent of Change

    Susanna Zagar, Ontario Energy Board CEO, Named EHRC’s 2025 Agent of Change

    May 12, 2025 Electricity Human Resources Canada (EHRC) is proud to announce Susanna Zagar (she/her), Chief Executive Officer of the Ontario Energy Board (OEB), as the recipient of the 2025 Agent of Change Award. This recognition celebrates Ms. Zagar’s remarkable leadership and commitment to diversity, equity and inclusion (DEI) in the electricity sector. Since stepping… Read More…

  • AD Reports Huge Jump in Member Sales Through Three Months of 2025

    AD Reports Huge Jump in Member Sales Through Three Months of 2025

    May 12, 2025 AD reports that member sales in the first three months of 2025 increased 23% to a record $24 billion across the group’s 14 divisions and three countries. AD welcomed over 550 new members in the first quarter through both organic growth and the IMARK Electrical merger. AD members also acquired another 10… Read More…

  • Legrand Introduces Wattstopper i3 Building Management Platform

    Legrand Introduces Wattstopper i3 Building Management Platform

    May 12, 2025 Legrand® has announced the launch of the Wattstopper i3 Platform, a next-generation lighting and building intelligence solution powered by KODE Labs, a global leader of advanced smart building technology.  The partnership positions Legrand to lead the lighting controls industry into a new era of unified experiences, seamless integrations, and data-driven control, making it easier… Read More…