The CE Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. In this article: Section 4. It is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook, but will hopefully provide some help in navigating the code.

Section 4 – Conductors

The definition of conductor, from Section 0, is a wire or cable, or other form of metal, installed for the purpose of conveying electric current from one piece of electrical equipment to another or to ground.

Section 4 deals with the selection of type, ampacity and installation conditions of insulated conductors. It is a general section and therefore it applies to all conductors supplying lighting, appliances and power circuits. The selection of other conductors, such as for control, grounding, emergency, safety, fire alarms, airport installations, renewable energy, communications, cathodic protection, and others, will be governed by individual sections covering these situations. Individual sections may also apply as general sections, or may have rules that reference or amend Section 4.

For example, Sections

• 6 — Services and service equipment
• 8 — Circuit loading and demand factors
• 10 — Grounding and bonding
• 12 — Wiring methods
• 14 — Protection and control
• 16 — Class I and Class II circuits
• 26 — Installation of electrical equipment

For this reason it is important to compare the rules in Section 4 with the rules governing conductors in the section dealing with your particular installation. For instance, Rule 4-002 requires that the minimum size for all copper conductors, except for flexible cord, equipment wire, or control circuit wire, and cable (which are specifically covered by other sections) is No.14 AWG and No. 12 AWG if aluminum. However, in Section 6, Rule 6-302 Installation of overhead consumer’s service conductors requires that the minimum size for overhead consumer’s service conductors is No.10 AWG copper or No. 8 AWG aluminum. Even though there are amendatory sections and rules later in the code, it is still important that you refer to Section 4 first when selecting and installing any conductor.

Conductor selection factors

When selecting a conductor there are a number of factors to be considered. Because of the complexity of conditions, you need to have a process to determine the correct type and size for your application. The first consideration is to choose the size of conductor you need based on the

• current it will be required to carry
• conditions under which it will be installed
• type of conductor or cable to be used

Rule 4-004 Ampacity of wires and cables contains 7 items each in subrules (1) and (2) covering scenario options each for copper and aluminum that need to be studied and chosen. In addition, there are 21 other factors in the subsequent subrules to be considered.

Although this may seem daunting at first, it is simply a matter of going through the list of options and conditions and choosing the ones that apply to your situation. Rule 4-004 will then direct you to the correct table and correction factor for your situation.In some cases you will be directed to use the IEEE 385 calculation method or the tabulated information tables in Appendix D. The IEEE 385 Standard Power Cable Ampacity Tables contains all pertinent equations and has the electrical/thermal analog circuit and calculation examples in the annex.

Once the right ampacity has been chosen or calculated, the next factor to consider, according to Rule 4-006, is the temperature limitations on the conductor ampacity you have chosen. Where the maximum conductor termination temperature is marked on the equipment, you will have already chosen the minimum size of conductor based on the correct temperature column of tables 1, 2, 3 or 4. Where the maximum conductor termination temperature is not marked on the equipment, the temperature to be used is: 600 C for equipment rated 100 A or less or marked for use with No.1 AWG or smaller conductors, or 750 C for equipment rated more than 100 A or marked for use with conductors larger than No. 1 AWG.

These conditions apply only to the first 1.2 meters of conductor length measured from the termination point of the equipment.One other condition to note when using a single conductor cable with a metal sheath or armour: induced voltages may cause the conductor insulation temperature to exceed its rating. In this case,Rule 4-010 Induced voltages and currents in metal armour or sheaths of single-conductor cables requires you to derate the conductor along with some other procedures to mitigate this situation.

The next important consideration outlined in Rules 4-008, 4-012, 4-014, 4-016, 4-018, 4-020, 4-040 and 4-042 is the selection of the type of insulated conductor, flexible cord, equipment wire or portable power cable. In some cases these rules will specify minimum sizes and ampacities for the various types.

Finally we go back to Rules 4-022, 4-024, 4-026, 4-028, 4-030, 4-032, 4-034, and 4-036, which provide for the use of a common neutral, installation, identification and use of neutral and identified conductors. Rule 4-038 Colour of conductorscovers the colouring of insulated grounding and bonding conductors, and where colour-coded circuits are required.

You will note that Section 4 does not apply to non-insulated grounding or bonding conductors. The use, size and ampacity of these conductors are covered by Section 10, which we will deal with in subsequent instalments.

In the next installment we will explore Section 6 — Services and service equipment.

Read the rest of the instalments in the series:

Part 1: Guide to the CE Code, Part I — A Roadmap (Instalment 1 in a Series)
Part 2:
A Road Map to the CE Code, Part I — Instalment 2
Part 3: Guide to the Canadian Electrical Code, Part I — Instalment 3
Part 4: A Road Map to the CE Code, Part 1 — Instalment 4
Part 5: Guide to the Canadian Electrical Code, Part I — Instalment 5
Part 6: Guide to the Canadian Electrical Code, Part I — Instalment 6
Part 7: Guide to the Canadian Electrical Code, Part I — Instalment 7
Part 8: Guide to the Canadian Electrical Code, Part I — Instalment 8
Part 9:
Guide to the Canadian Electrical Code, Part I — Installment 9
Part 10: Guide to the Canadian Electrical Code, Part 1 — Instalment 10
Part 11: Guide to the Canadian Electrical Code, Part 1 — Instalment 11


 

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com.

 

Related Articles


Latest Articles

  • Code Quiz: Section 26 – Installation of Electrical Equipment

    Code Quiz: Section 26 – Installation of Electrical Equipment

    April 7, 2025 By Bill Burr Section 26 – Installation of Electrical Equipment Receptacles Question: Rule 26-706 specifies that all receptacles of CSA configuration 5-15R and 5-20R installed in: …must have a particular feature, what is this feature? Source: CSA C22.1:24, Canadian Electrical Code, Part 1 – Safety Standard for Electrical Installations. © 2021 Canadian… Read More…

  • Guide to the Canadian Electrical Code, Part 1[i], 26th Edition – A Road Map: Section 32

    Guide to the Canadian Electrical Code, Part 1[i], 26th Edition – A Road Map: Section 32

    Section 32, as outlined in rule 32 -000 Scope, is a supplementary or amendatory section of the code and provides additional and specific requirements for the location, installation, wiring, and protection, of fire alarm systems… Read More…

  • Alberta Municipalities EV Charging Installation Rebate

    Alberta Municipalities EV Charging Installation Rebate

    April 4, 2025 Alberta Municipalities are proud to provide financial rebates for applicants to purchase and install electric vehicle charging stations in Alberta as part of the Electric Vehicle Charging Program (EVCP), funded by Natural Resources Canada (NRCan) & Alberta Municipalities.  The funding will cover up to 46% of your total project cost, which can… Read More…

  • Industry Legend Bill Smith Retires

    Industry Legend Bill Smith Retires

    April 4, 2025 By Electro-Federation Canada On March 25, Electrozad, a Sonepar Company, hosted a special retirement reception at Caesars Windsor for industry titan Bill Smith who marked an incredible 50-year career with the company.  The reception was held in the elegant Caesars Ballroom, which featured an array of food stations and elegant decor. In… Read More…


Changing Scene

  • NSAA Fee Change Effective April 1, 2025

    NSAA Fee Change Effective April 1, 2025

    As of April 1, 2025, the Nova Scotia Apprenticeship Agency’s fees have changed due to the 1% reduction in HST in Nova Scotia. NSAA noted on their website that due to the number of references across various pages, you may still come across old fee amounts as they work through updating their website. Here is… Read More…

  • Nominations Open for 2024 NETCO Leadership Excellence Award

    Nominations Open for 2024 NETCO Leadership Excellence Award

    Established in 2016, the NETCO Leadership Excellence award honours an industry training professional for his/her role for the success and their outstanding contributions to apprenticeship training and continuing electrical training. Read More…

  • Munded Partners with Kane Test Equipment in Atlantic Canada

    Munded Partners with Kane Test Equipment in Atlantic Canada

    April 4, 2025 Munden Enterprises has announced a partnership with Kane Test Equipment to bring their test and measurement solutions to Atlantic Canada. “We are now excited to announce a new and promising partnership with Kane Test Equipment. Kane Test Equipment brings innovative solutions that align with our dedication to providing the best tools for… Read More…

  • Nedco Announces Western Canadian Wire & Cable Sales Manager

    Nedco Announces Western Canadian Wire & Cable Sales Manager

    April 4, 2025 Don Blake has joined Nedco as their Western Canadian Wire & Cable Sales Manager. “With over 20 years of experience in the Wire & Cable industry, Don brings a wealth of knowledge and expertise to our Nedco West team,” said the company on LinkedIn. “His focus will be on expanding our product… Read More…