Guide to the Canadian Electrical Code, Part I — Instalment 6

Electrical Grounding

 

William (Bill) Burr

The CE Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. In this article: Section 10 — Grounding and bonding.

Section 10 — Grounding and bonding

Section 10 is a general section of the Code and applies to all installations unless amended by other Sections of the Code. It’s Scope outlines requirements for:

• grounding of electrical systems and service equipment
• bonding of non-current-carrying metal parts of equipment and conductor enclosures, together and to ground
• the use of ungrounded systems and neutral grounding devices

Special terminology used in this section and found throughout the code include bonding, bonding conductor, ground, ground fault, ground fault detection, ground fault protection, grounded, grounding, grounding conductor, grounding electrode, and grounding system.

These are all thoroughly defined in Section 0. In general terms, bonding refers to a low impedance permanent connection of all non-current-carrying metal parts together, and grounding refers to a permanent low impedance connection to the earth.

The stated object of Section 10 is to provide rules for

• bonding metal parts and systems together and to the grounded system conductor to reduce the danger of electric shock and property damage, providing a low impedance path for fault current back to the source, and establishing an equipotential plane to minimize potential difference between non-current carrying metal parts

• grounding the electrical system and bonding of non-current carrying metal parts to earth to minimize any potential difference to earth

• using an ungrounded system or a neutral grounding device in the system to provide alternates to a solidly grounded system, and minimizing any damage from a single fault by limiting the magnitude of the fault current.

System and circuit grounding rules 10-102 to 10-116 provide guidance on when and where, as well as exceptions to, grounding specific two-wire dc systems, three-wire DC systems, AC systems, electric arc furnaces, electric crane circuits, isolated circuits, circuits of less than 50V, and instrument transformer circuits.

Once you have determined your specific grounding needs, Grounding connections for systems and circuits rules 10-200 to 10-212 provide specific detailed guidance on how to ground various systems. Appendix B also contains some helpful diagrams.

Conductor enclosure bonding rules 10-300 to 10-304 are guidelines for when and where to bond metal enclosures for service conductors, underground service conductors, as well as enclosures for other than service conductors.

Equipment bonding rules 10-400 to 10-414 provide the varying requirements for when and where to bond all metal non-current carrying parts of fixed equipment general, fixed equipment, specific, non-electrical equipment, portable equipment, instrument transformer cases, cases of instruments, meters, and relays-operating voltage 750v or less, cases of instruments, meters, and relays-operating voltage over 750V, as well as non-metallic wiring systems.

The Bonding methods rules 10-600 to 10-626 will guide you through the steps needed to ensure an effective continuous, low-impedance bonding connection when Bonding service equipment, Metal armour or tape of service cable, Bonding at other than service equipment, Loosely jointed metal raceways, bonding jumpers, short sections of raceway, fixed equipment, portable equipment, pendant equipment, bonding equipment to the grounded system conductor (bonding to ground), and electrolytic-type water heaters. Helpful suggestions are also contained in the Appendix B notes.

Rule 10-700 Grounding electrodes sets out the requirements for establishing a grounding connection through the use of electrodes. There are specific rules for various grounding electrodes including manufactured grounding electrodes (both rod electrodes and plate electrodes), field-assembled ground electrodes, and in-situ grounding electrodes forming part of the existing infrastructure. Rule 10-702 sets out spacing and interconnection requirements for grounding electrodes where more than one grounding electrode exists at the building including those electrodes used for signal circuits, radio, lightning protection, communication, community antenna distribution systems, and any other purpose. Rules 10-704 and 10-706 deal with railway track electrodes and the use of lightning rod system conductors and grounding electrodes.

Rules 10-800 to 10-820 are rules governing continuity, material selection, sizing, and installation of grounding and bonding conductors. The size of a grounding conductor is determined by the type of system, either AC or DC. The size of a bonding conductor as determined by Table 16A or 16B depends on the size of the associated circuit conductor (Table 16A) or on the size of the associated bus-bar (Table 16B).

Once you have installed the correct type and size of bonding and grounding conductor, pay close attention to the connection of these conductors as specified in rules 10-900 to 10-906 Grounding and bonding conductor connections. The continuity and safety of a low-impedance path to reduce the danger of electric shock and property damage, and providing a low impedance path for fault current back to the source, depends on adequate and sound connections.

The final two subjects of Section 10 deal with grounding and bonding of lightning arresters and the installation of neutral grounding devices.

In the next installment we will be discussing Section 12 — Wiring methods.

Read the rest of the instalments in the series:
Part 1: Guide to the CE Code, Part I – A Roadmap (Installment 1 in a Series)
Part 2:
A Road Map to the CE Code, Part I – Installment 2
Part 3: Guide to the Canadian Electrical Code, Part I – Installment 3
Part 4: A Road Map to the CE Code, Part 1 – Installment 4
Part 5: Guide to the Canadian Electrical Code, Part I — Installment 5
Part 6: Guide to the Canadian Electrical Code, Part I — Installment 6
Part 7: Guide to the Canadian Electrical Code, Part I — Installment 7
Part 8: Guide to the Canadian Electrical Code, Part I — Installment 8
Part 9:
Guide to the Canadian Electrical Code, Part I — Installment 9
Part 10: Guide to the Canadian Electrical Code, Part 1 – Installment 10
Part 11: Guide to the Canadian Electrical Code, Part 1 – Installment 11


 

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com.

 

Related Articles


Latest Articles

  • Efficiency Nova Scotia Rebates

    Efficiency Nova Scotia Rebates

    January 24, 2025 NEW Up to 75% of product costs in rebates for energy efficient products or interest-free financing for up to 24 months. Get rebates Before You Buy, at the counter, or After You Buy with mail-in and instant rebates. Before you Buy Instant Rebates No paperwork required. Save at the counter when you… Read More…

  • The Drive Towards Energy-Efficient Data Centres

    The Drive Towards Energy-Efficient Data Centres

    Data centres are the backbone of our digital world. They serve as the foundation for various online activities like streaming, e-commerce, website/app usage, Digital transformation. Read More…

  • Multi-Unit Construction Intentions Push Down the Residential Sector for November 2024 Building Permits

    Multi-Unit Construction Intentions Push Down the Residential Sector for November 2024 Building Permits

    January 20, 2025 The total value of building permits issued in Canada decreased by $739.5 million (-5.9%) to $11.7 billion in November, a second consecutive monthly decline. The residential sector led the decrease, followed by the non-residential sector. On a constant dollar basis (2017=100), the total value of building permits issued in November declined 5.8% from the previous… Read More…

  • Ontario Save On Energy Home Renovation Savings Program

    Ontario Save On Energy Home Renovation Savings Program

    January 20, 2025 On January 7, the Government of Ontario announced 14 new and expanded energy-efficiency programs, including the Home Renovation Savings Program, as part of a new $10.9 billion investment in energy efficiency to help families and businesses save money. Save on Energy and Enbridge Gas, with endorsement from the Ontario government, have partnered to… Read More…


Changing Scene

  • Agence Ricard Welcomes New Business Development Specialist for the South Shore of Montreal 

    Agence Ricard Welcomes New Business Development Specialist for the South Shore of Montreal 

    January 24, 2025 Agence Ricard is proud to announce the arrival of Fred Dozois as new business development specialist for the South Shore of Montreal. With over 10 years of experience in the electrical industry, Fred brings an impressive wealth of knowledge and skills that will strengthen the team at Ricard.  Recognized for his expertise,… Read More…

  • Graybar Transforming Branches From Coast to Coast

    Graybar Transforming Branches From Coast to Coast

    January 24, 2025 Exciting transformations are happening at Graybar Canada. Across the nation, Graybar branches are getting a refreshed look, inside and out. These updates reflect their dedication to maintaining modern, welcoming spaces that showcase the strength of their brand and world class manufacturer partners. From sleek new shelving to vibrant wall murals, these renovations are designed… Read More…

  • New Address for Franklin Empire London, ON Branch

    New Address for Franklin Empire London, ON Branch

    January 24, 2025 Franklin Empire are pleased to announce the new address of their London, Ontario branch. Address:552 Newbold StreetLondon, Ontario N6E 2S5 Source Read More…

  • Ontario Launches Regional Economic Development Through Immigration Pilot Program 

    Ontario Launches Regional Economic Development Through Immigration Pilot Program 

    January 24, 2025  The Ontario government has launched the Regional Economic Development through Immigration (REDI) pilot program to target highly-skilled immigration for four rural and northern regions with a high demand for skilled labour: Lanark, Leeds and Grenville, Sarnia-Lambton, and Thunder Bay. REDI enables local employers in these communities to attract up to 800 additional… Read More…