Guide to the Canadian Electrical Code, Part I – Instalment 3

Electrical Conductors

William (Bill) Burr

The CE Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. In this article: Section 4. It is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook, but will hopefully provide some help in navigating the code.

Section 4 – Conductors

The definition of conductor, from Section 0, is a wire or cable, or other form of metal, installed for the purpose of conveying electric current from one piece of electrical equipment to another or to ground.

Section 4 deals with the selection of type, ampacity and installation conditions of insulated conductors. It is a general section and therefore it applies to all conductors supplying lighting, appliances and power circuits. The selection of other conductors, such as for control, grounding, emergency, safety, fire alarms, airport installations, renewable energy, communications, cathodic protection, and others, will be governed by individual sections covering these situations. Individual sections may also apply as general sections, or may have rules that reference or amend Section 4.

For example, Sections

• 6 — Services and service equipment
• 8 — Circuit loading and demand factors
• 10 — Grounding and bonding
• 12 — Wiring methods
• 14 — Protection and control
• 16 — Class I and Class II circuits
• 26 — Installation of electrical equipment

For this reason it is important to compare the rules in Section 4 with the rules governing conductors in the section dealing with your particular installation. For instance, Rule 4-002 requires that the minimum size for all copper conductors, except for flexible cord, equipment wire, or control circuit wire, and cable (which are specifically covered by other sections) is No.14 AWG and No. 12 AWG if aluminum. However, in Section 6, Rule 6-302 Installation of overhead consumer’s service conductors requires that the minimum size for overhead consumer’s service conductors is No.10 AWG copper or No. 8 AWG aluminum. Even though there are amendatory sections and rules later in the code, it is still important that you refer to Section 4 first when selecting and installing any conductor.

Conductor selection factors

When selecting a conductor there are a number of factors to be considered. Because of the complexity of conditions, you need to have a process to determine the correct type and size for your application. The first consideration is to choose the size of conductor you need based on the

• current it will be required to carry
• conditions under which it will be installed
• type of conductor or cable to be used

Rule 4-004 Ampacity of wires and cables contains 7 items each in subrules (1) and (2) covering scenario options each for copper and aluminum that need to be studied and chosen. In addition, there are 21 other factors in the subsequent subrules to be considered.

Although this may seem daunting at first, it is simply a matter of going through the list of options and conditions and choosing the ones that apply to your situation. Rule 4-004 will then direct you to the correct table and correction factor for your situation.In some cases you will be directed to use the IEEE 385 calculation method or the tabulated information tables in Appendix D. The IEEE 385 Standard Power Cable Ampacity Tables contains all pertinent equations and has the electrical/thermal analog circuit and calculation examples in the annex.

Once the right ampacity has been chosen or calculated, the next factor to consider, according to Rule 4-006, is the temperature limitations on the conductor ampacity you have chosen. Where the maximum conductor termination temperature is marked on the equipment, you will have already chosen the minimum size of conductor based on the correct temperature column of tables 1, 2, 3 or 4. Where the maximum conductor termination temperature is not marked on the equipment, the temperature to be used is: 600 C for equipment rated 100 A or less or marked for use with No.1 AWG or smaller conductors, or 750 C for equipment rated more than 100 A or marked for use with conductors larger than No. 1 AWG.

These conditions apply only to the first 1.2 meters of conductor length measured from the termination point of the equipment.One other condition to note when using a single conductor cable with a metal sheath or armour: induced voltages may cause the conductor insulation temperature to exceed its rating. In this case,Rule 4-010 Induced voltages and currents in metal armour or sheaths of single-conductor cables requires you to derate the conductor along with some other procedures to mitigate this situation.

The next important consideration outlined in Rules 4-008, 4-012, 4-014, 4-016, 4-018, 4-020, 4-040 and 4-042 is the selection of the type of insulated conductor, flexible cord, equipment wire or portable power cable. In some cases these rules will specify minimum sizes and ampacities for the various types.

Finally we go back to Rules 4-022, 4-024, 4-026, 4-028, 4-030, 4-032, 4-034, and 4-036, which provide for the use of a common neutral, installation, identification and use of neutral and identified conductors. Rule 4-038 Colour of conductorscovers the colouring of insulated grounding and bonding conductors, and where colour-coded circuits are required.

You will note that Section 4 does not apply to non-insulated grounding or bonding conductors. The use, size and ampacity of these conductors are covered by Section 10, which we will deal with in subsequent instalments.

In the next installment we will explore Section 6 — Services and service equipment.

Read the rest of the instalments in the series:

Part 1: Guide to the CE Code, Part I — A Roadmap (Instalment 1 in a Series)
Part 2:
A Road Map to the CE Code, Part I — Instalment 2
Part 3: Guide to the Canadian Electrical Code, Part I — Instalment 3
Part 4: A Road Map to the CE Code, Part 1 — Instalment 4
Part 5: Guide to the Canadian Electrical Code, Part I — Instalment 5
Part 6: Guide to the Canadian Electrical Code, Part I — Instalment 6
Part 7: Guide to the Canadian Electrical Code, Part I — Instalment 7
Part 8: Guide to the Canadian Electrical Code, Part I — Instalment 8
Part 9:
Guide to the Canadian Electrical Code, Part I — Installment 9
Part 10: Guide to the Canadian Electrical Code, Part 1 — Instalment 10
Part 11: Guide to the Canadian Electrical Code, Part 1 — Instalment 11


 

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com.

 

Related Articles


Latest Articles

  • Lighting Case Study: Metro Toronto Convention Centre

    Lighting Case Study: Metro Toronto Convention Centre

    September 27, 2024 Goal: Upgrade the outdated 350-450-Watt metal halide lighting technology at the Metro Toronto Convention Centre (MTCC) with high-performing, energy-efficient, long-lasting, and low-maintenance LED fixtures from LEDVANCE Products Installed: 1,431 200-Watt UFO High Bay Fixtures from LEDVANCE, which are ideal replacements for metal halide lighting Benefits: LEDVANCE LEDs slashed the MTCC’s previous lighting… Read More…

  • The Consulting Engineer’s Guide to Advanced Electric Boiler Technology

    The Consulting Engineer’s Guide to Advanced Electric Boiler Technology

    September 27, 2024 An international boiler expert helps industry professionals take advantage of high voltage electrode boilers’ virtually 100% efficient, zero-emission capabilities, providing guidance on selection and installation For consulting engineers tasked with planning, designing, and supervising construction projects for a wide range of industries, advanced electric boilers – particularly high voltage electrode boilers –… Read More…

  • Just Getting Started – Discussing Milwaukee’s 100 Year Anniversary with President of Milwaukee Tool Canada, John Myers

    Just Getting Started – Discussing Milwaukee’s 100 Year Anniversary with President of Milwaukee Tool Canada, John Myers

    September 23, 2024 By Blake Marchand It goes without saying that the Milwaukee brand is historic. Their longevity is a testament to company culture and innovation. As this year marks Milwaukee’s 100th anniversary, the company held a tree planting ceremony earlier in the year to mark the milestone, planting 100 trees in partnership with Tree… Read More…

  • ECABC Provides Platform Recommendations to BC Political Parties

    ECABC Provides Platform Recommendations to BC Political Parties

    September 23, 2024 The Electrical Contractors Association of British Columbia has provided three platform policy recommendations to each of BC’s major political parties in advance of the October 19, 2024 provincial election: implementing prompt payment legislation, increasing capital and operating funding to support electrical apprentices, and naming a Minister responsible for construction in their Cabinet…. Read More…


Changing Scene

  • NOARK Partners With Innovelec, to Power the Electrical Industry in Western Canada

    NOARK Partners With Innovelec, to Power the Electrical Industry in Western Canada

    September 26, 2024 INNOVELEC, a supplier of products and services for the electrical industry in Western Canada for over 25 years,  and NOARK Electric, global manufacturer of low-voltage electrical components for industrial applications, have partnered to electrify Western Canada. Specializing in motor controls and protection for Original Equipment Manufacturers, System Integrators and Panel Builders, Noark Electric… Read More…

  • Mitsubishi Electric Sales Canada Inc. and Efficiency Capital Partner to Cross Promote Low-Carbon Building Solutions in Canada

    Mitsubishi Electric Sales Canada Inc. and Efficiency Capital Partner to Cross Promote Low-Carbon Building Solutions in Canada

    September 23, 2024 Efficiency Capital (EC), Canada’s first Energy-as-a-Service (EaaS) company, and Mitsubishi Electric Sales Canada Inc. (MESCA) announced a strategic cross promotional partnership to make low-carbon building solutions more accessible to building owners and operators across Canada. Energy efficiency in buildings, despite being one of the critical pathways to meet Canada’s climate goals, faces… Read More…

  • Siemens to Carve out Electric Vehicle Charging Business to Enable next Level of Growth

    Siemens to Carve out Electric Vehicle Charging Business to Enable next Level of Growth

    September 23, 2024 Siemens has announced the intention to carve out its eMobility business. The company bundled its eMobility charging activities in 2018 and subsequently organized it into a separate business unit in 2022.  The carve out of Siemens eMobility, which has a strong technological core and portfolio, will give the business entrepreneurial freedom to… Read More…

  • FLO Confirms FLO Station Eligibility for ZEVIP Funding

    FLO Confirms FLO Station Eligibility for ZEVIP Funding

    September 24, 2024 Canada recently announced trade measures impacting vehicles from China and limiting eligibility under the Natural Resources Canada (NRCan) Zero Emission Vehicle Infrastructure Program (ZEVIP) to electric vehicle (EV) charging products manufactured in countries that have negotiated free trade agreements with Canada. Effective October 1, 2024, this directive is expected to have an impact on… Read More…