PEI Begins Substantial Interconnection Upgrade Project

PEI Interconnection Upgrade

June 31 2016

Prince Edward Island has begun on one of the largest construction projects in its history — replacing and upgrading undersea electrical connections between PEI and New Brunswick.
The Interconnection Upgrade Project, a joint effort with the federal government, will allow PEI to import electricity from New Brunswick through two new 180 MW submarine cables, overhead transmission lines, substation upgrades and more. The submarine cables will be owned by the province and leased to and operated by Maritime Electric. Project costs have been estimated at between $120 million and $140 million.

When the existing submarine cables were installed nearly 40 years ago, the electricity load was 95 MW. In 2015, it peaked at 262 MW. PEI has no natural energy supply sources and relies on off island sources for cost-effective and reliable energy supply. While the province has developed significant wind energy supply, this supply requires back up for times when there is no wind.

The project offers at least five benefits:
• enabling future electrical growth on PEI
• improving reliability for customers
• reducing reliance on fossil-fueled generation
• creating a secure, reliable connection to the mainland
• providing access to a more economic energy supply

What’s involved

The project requires
• installation of two 180 MW submarine cables between Borden, PEI and Cape Tormentine, NB, (16.5 km) in the Northumberland Strait
• construction of 60 km of new overhead transmission line between Cape Tormentine and Memramcook
• construction of a substation extension at Borden, PEI

The project also includes:
• two landfall sites (where the submarine cable trench is brought ashore)
• two termination sites (for converting submarine cables to overhead transmission lines or substation)
• upgrading of the New Brunswick Power Corporation (NB Power) substation in Memramcook, NB

The first construction phase involves pre-trenching. This process involves a marine excavator called a Starfish and two mechanical marine dredges: one at PEI’s Borden-Carleton site and the other at New Brunswick’s Cape Tormentine site.

On the Cape Tormentine side the Starfish will be used excavate approximately 600 metres from shore into the Northumberland Strait. Once that distance is reached the Starfish will be shipped to the PEI side and the mechanical marine dredge will continue to excavate to the 1.8 km mark offshore.

The Starfish will be in operation for 12 hours daily for excavation. The two mechanical marine dredges will be working 24 hours per day on excavation. This process, expected to take 6-8 weeks, will ensure there are no rock obstructions along the route when the cable is laid in mid October.

The two cables will be installed under the seabed in separate trenches, up to 200 m apart. In water depths of greater than 12 m the cables will be buried at 0.6 m, while in areas of less than 12 m of water the cable will be buried at approximately 2 m. Excavating within the marine environment will involve trenching with excavators in water depths up to 2 m and a trenching remotely operated vehicle (TROV) with a saw cutter for the remaining sections. Exclusion zones around the cables are not planned. There will be no fishing restrictions. Once the cables have been installed, navigation charts will be updated.

The entire project is scheduled for completion in late spring or early summer 2017.

 

 

Related Articles


Latest Articles

  • ABB Wins New Product Award at MCEE Show

    ABB Wins New Product Award at MCEE Show

    April 28, 2025 ReliaHome™ Smart Panel won Best New Product Award in the Software, Controls and Related Components category. Iberville® Gangable boxes with low-voltage cables support bracket was recognized as a finalist in the Commercial, Institutional and Industrial Electrical Products category. ABB was honored with a Best New Product Award in the Software, Controls and… Read More…

  • Weidmuller Celebrating a Legacy: 175 Years Globally, 50 Years in Canada

    Weidmuller Celebrating a Legacy: 175 Years Globally, 50 Years in Canada

    April 28, 2025 The year 2025 is truly special for Weidmüller. The company proudly celebrates not just 50 remarkable years in Canada but also its 175th anniversary globally—an extraordinary achievement few companies can claim. This legacy is a testament to the company’s relentless pursuit of innovation and commitment to refining its offerings. But the journey… Read More…

  • Canada Stands Tall at Hannover Messe 2025

    Canada Stands Tall at Hannover Messe 2025

    April 28, 2025 By Owen Hurst At Hannover Messe earlier this month Canada had a strong presence as the host country with a wide variety of companies and programs focusing on the development of advance technology. The presence was accentuated by numerous halls hosting Canada pavilions. Partner Country Canada presented itself impressively at HANNOVER MESSE…. Read More…

  • BC Prompt Payment Legislation Progressing

    BC Prompt Payment Legislation Progressing

    April 28, 2025 Consistent with its mandate of growing the economy, the government wants to ensure that businesses are paid promptly for work performed on (or material provided to) construction projects. British Columbia’s Ministry of Attorney General staff have been tracking the issue of payment delay in the construction industry, including legislative responses in other… Read More…


Changing Scene

  • Schneider Electric Advances in Product Environmental Data Transparency

    Schneider Electric Advances in Product Environmental Data Transparency

    April 28, 2025 Schneider Electric has launched its Environmental Data Program. This initiative, which builds on the legacy Green Premium label, provides customers with unique access to information on the environmental impact of its products, enabling them to make better informed, data-based decisions and meet evolving regulatory requirements with confidence. Schneider Electric has frequently been recognized… Read More…

  • nVent Sustainability Report Highlights Progress and Focus on Electrification

    nVent Sustainability Report Highlights Progress and Focus on Electrification

    April 15, 2025 nVent Electric plc announced the release of its 2024 Sustainability Report. The new report highlights nVent’s achievements in each of its sustainability focus areas: People, Products, Planet and Governance. The report also highlights how nVent solutions support electrification, digitalization and sustainability efforts around the world. “nVent is becoming a more focused electrical… Read More…

  • Ontario Introduces Legistlation to Unlock Trade and Labour Mobility Within Canada

    Ontario Introduces Legistlation to Unlock Trade and Labour Mobility Within Canada

    April 18, 2025 As a next step in its plan to protect Ontario by unleashing the province’s economy, the Ontario government is introducing the Protect Ontario through Free Trade within Canada Act to unlock free trade and labour mobility within Canada. This legislation will, if passed, create new opportunities for job creation and investment attraction, supporting economic… Read More…

  • Ontario, P.E.I. Join Nova Scotia With Legislation to Remove Internal Trade Barriers

    Ontario, P.E.I. Join Nova Scotia With Legislation to Remove Internal Trade Barriers

    April 18, 2025 Prince Edward Island and Ontario have joined the Nova Scotia by introducing reciprocal legislation that will help foster an environment of mutual recognition of goods, services and labour mobility between these provinces. “Leaders across the country are expressing interest in removing trade barriers, and I’m very pleased that P.E.I. and Ontario have… Read More…