Guide to the Canadian Electrical Code, Part I – Instalment 3

Electrical Conductors

William (Bill) Burr

The CE Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. In this article: Section 4. It is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook, but will hopefully provide some help in navigating the code.

Section 4 – Conductors

The definition of conductor, from Section 0, is a wire or cable, or other form of metal, installed for the purpose of conveying electric current from one piece of electrical equipment to another or to ground.

Section 4 deals with the selection of type, ampacity and installation conditions of insulated conductors. It is a general section and therefore it applies to all conductors supplying lighting, appliances and power circuits. The selection of other conductors, such as for control, grounding, emergency, safety, fire alarms, airport installations, renewable energy, communications, cathodic protection, and others, will be governed by individual sections covering these situations. Individual sections may also apply as general sections, or may have rules that reference or amend Section 4.

For example, Sections

• 6 — Services and service equipment
• 8 — Circuit loading and demand factors
• 10 — Grounding and bonding
• 12 — Wiring methods
• 14 — Protection and control
• 16 — Class I and Class II circuits
• 26 — Installation of electrical equipment

For this reason it is important to compare the rules in Section 4 with the rules governing conductors in the section dealing with your particular installation. For instance, Rule 4-002 requires that the minimum size for all copper conductors, except for flexible cord, equipment wire, or control circuit wire, and cable (which are specifically covered by other sections) is No.14 AWG and No. 12 AWG if aluminum. However, in Section 6, Rule 6-302 Installation of overhead consumer’s service conductors requires that the minimum size for overhead consumer’s service conductors is No.10 AWG copper or No. 8 AWG aluminum. Even though there are amendatory sections and rules later in the code, it is still important that you refer to Section 4 first when selecting and installing any conductor.

Conductor selection factors

When selecting a conductor there are a number of factors to be considered. Because of the complexity of conditions, you need to have a process to determine the correct type and size for your application. The first consideration is to choose the size of conductor you need based on the

• current it will be required to carry
• conditions under which it will be installed
• type of conductor or cable to be used

Rule 4-004 Ampacity of wires and cables contains 7 items each in subrules (1) and (2) covering scenario options each for copper and aluminum that need to be studied and chosen. In addition, there are 21 other factors in the subsequent subrules to be considered.

Although this may seem daunting at first, it is simply a matter of going through the list of options and conditions and choosing the ones that apply to your situation. Rule 4-004 will then direct you to the correct table and correction factor for your situation.In some cases you will be directed to use the IEEE 385 calculation method or the tabulated information tables in Appendix D. The IEEE 385 Standard Power Cable Ampacity Tables contains all pertinent equations and has the electrical/thermal analog circuit and calculation examples in the annex.

Once the right ampacity has been chosen or calculated, the next factor to consider, according to Rule 4-006, is the temperature limitations on the conductor ampacity you have chosen. Where the maximum conductor termination temperature is marked on the equipment, you will have already chosen the minimum size of conductor based on the correct temperature column of tables 1, 2, 3 or 4. Where the maximum conductor termination temperature is not marked on the equipment, the temperature to be used is: 600 C for equipment rated 100 A or less or marked for use with No.1 AWG or smaller conductors, or 750 C for equipment rated more than 100 A or marked for use with conductors larger than No. 1 AWG.

These conditions apply only to the first 1.2 meters of conductor length measured from the termination point of the equipment.One other condition to note when using a single conductor cable with a metal sheath or armour: induced voltages may cause the conductor insulation temperature to exceed its rating. In this case,Rule 4-010 Induced voltages and currents in metal armour or sheaths of single-conductor cables requires you to derate the conductor along with some other procedures to mitigate this situation.

The next important consideration outlined in Rules 4-008, 4-012, 4-014, 4-016, 4-018, 4-020, 4-040 and 4-042 is the selection of the type of insulated conductor, flexible cord, equipment wire or portable power cable. In some cases these rules will specify minimum sizes and ampacities for the various types.

Finally we go back to Rules 4-022, 4-024, 4-026, 4-028, 4-030, 4-032, 4-034, and 4-036, which provide for the use of a common neutral, installation, identification and use of neutral and identified conductors. Rule 4-038 Colour of conductorscovers the colouring of insulated grounding and bonding conductors, and where colour-coded circuits are required.

You will note that Section 4 does not apply to non-insulated grounding or bonding conductors. The use, size and ampacity of these conductors are covered by Section 10, which we will deal with in subsequent instalments.

In the next installment we will explore Section 6 — Services and service equipment.

Read the rest of the instalments in the series:

Part 1: Guide to the CE Code, Part I — A Roadmap (Instalment 1 in a Series)
Part 2:
A Road Map to the CE Code, Part I — Instalment 2
Part 3: Guide to the Canadian Electrical Code, Part I — Instalment 3
Part 4: A Road Map to the CE Code, Part 1 — Instalment 4
Part 5: Guide to the Canadian Electrical Code, Part I — Instalment 5
Part 6: Guide to the Canadian Electrical Code, Part I — Instalment 6
Part 7: Guide to the Canadian Electrical Code, Part I — Instalment 7
Part 8: Guide to the Canadian Electrical Code, Part I — Instalment 8
Part 9:
Guide to the Canadian Electrical Code, Part I — Installment 9
Part 10: Guide to the Canadian Electrical Code, Part 1 — Instalment 10
Part 11: Guide to the Canadian Electrical Code, Part 1 — Instalment 11


 

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com.

 

Related Articles


Latest Articles

  • NETCO 2024 Conference in Victoria: The Evolution of the Electrician

    NETCO 2024 Conference in Victoria: The Evolution of the Electrician

    September 20, 2024 The Evolution of the Electrical Industry was Showcased eariler this month in Victoria, BC with the 2024 installment of NETCO’s Annual Conference Leaders and experts from the electrical industry will gather in Victoria, BC, September 5-6th, at the picturesque Inn at Laurel Point for the annual National Electrical Trade Council (NETCO) educational… Read More…

  • Desdowd Icon Patrick Marion Retires

    Desdowd Icon Patrick Marion Retires

    September 20, 2024 On September 11, more than 200 industry guests and colleagues celebrated Patrick Marion’s 35-year career history to the day. Guests travelled from across the country – some from as far as Vancouver and Halifax – to join those from Montreal and Toronto to celebrate Patrick’s career. Held at a prestigious golf club… Read More…

  • EFC Letter on China Tariffs

    EFC Letter on China Tariffs

    September 15, 2024 The Canadian federal government intends to apply a 25 per cent surtax on imports of steel and aluminum products from China, effective October 15, 2024. See announcement here. The initial list of impacted goods was released for public comment and submissions are due September 20, 2024.  The list of products is available… Read More…

  • Changing How we Build Homes: A Year of the Housing Accelerator Fund

    Changing How we Build Homes: A Year of the Housing Accelerator Fund

    September 15, 2024 The Government of Canada is highlighting key results that have come from the first Housing Accelerator Fund since the start of the Program. This week marks the closure of the application portal for the second round of the HAF. HAF was created to incentivize local governments to implement structural and lasting reforms that will increase… Read More…


Changing Scene

  • Southwire Signs Contract for Solar System at North Campus Plant

    Southwire Signs Contract for Solar System at North Campus Plant

    September 20, 2024 Southwire is pleased to announce that it has signed an agreement with Statewide Renewable, a solar project developer, to install a solar array at its North Campus Plant.  The company has a long-standing commitment to environmental stewardship and corporate sustainability, and in support of that commitment, is investing in renewable energy as… Read More…

  • Schneider Electric Foundation Turns 25 and Launches the ‘25 Years Young’ Campaign in Canada

    Schneider Electric Foundation Turns 25 and Launches the ‘25 Years Young’ Campaign in Canada

    September 20, 2024  To mark the 25th anniversary of its foundation, Schneider Electric is launching a global campaign in celebration of both this key milestone and the next generation of young leaders committed to building a fairer, low-carbon society. Non-profits could win a 50K€ grand prize and one of five local prizes totaling 75K€ to… Read More…

  • New Funding Announced to Install Over 3,000 EV Chargers Across Canada

    New Funding Announced to Install Over 3,000 EV Chargers Across Canada

    September 20, 2024 The federal government has announced investments of $14.9 million for 20 projects that will install more than 3,000 EV chargers across Canada, while raising awareness of the benefits of EVs and advancing training and code upgrades to ensure more communities have access to current information and opportunities to seize the potential of… Read More…

  • ECABC Statement on the Response to BC Hydro’s Call for Clean Power Projects

    ECABC Statement on the Response to BC Hydro’s Call for Clean Power Projects

    September 20, 2024 Electrical Contractors Association of British Columbia President Matt MacInnis issued the following statement on the response to BC Hydro’s call for clean electricity project proposals: “It is very encouraging to see the private sector bring forward projects offering nearly three times the generation capacity BC Hydro is seeking in this first call… Read More…