Arc Flash Incident Involving a Maintenance Switch

Maintenance Switch

 

Feb 12, 2016

This case study article examines the plans and processes reviewed and considered, the strategy deployed to manage/reduce arc flash hazards, and then lessons learned in the implementation of new systems to improve electrical workplace safety. The setting: a chemical processing facility with a robust electrical workplace safety process. The site experienced an actual arc flash event while energized work was being performed.

Photo courtesy: www.utilityproducts.com

The facility was planning energized work for an existing 480 V low voltage switchgear assembly that was an existing piece of equipment in the plant. During a process upgrade in the facility, an energized work permit was issued to remove three abandoned load conductors from an existing 480 V low voltage switchgear assembly cable compartment.

The work permit was very detailed and included tools planned for use in the project and required PPE for workers performing the task based on the incident energy defined by a recently completed arc flash hazard assessment. The defined task for the work order required the site contractor to use a nylon rope, which was typical with this type of project, disconnecting the de-energized cables and working to raise them from the top cable compartment. Figure 10 showsa layout of the low voltage assembly involved in the work.

The de-energized cables were to be removed from Cubicle 5, with still energized conductors existing in Cubical 4 at the bottom of the cable wireway. The rope used was not able to grab the conductors and would slip off of the cable, so the electrical contractor elected to employ a “come along” to assist in the removal, as the come along could apply more force. The first conductor was successfully removed with this new tool. Upon removing the second conductor, a small arc flash was observed in the lower compartment. Simultaneously, the lights to the plant went out.The contractor stopped work and waited for plant electricians to arrive, not knowing what had just occurred.

The event caused the entire plant to shut down, stopping work on the project until an analysis could be completed. It was determined that the chain of the come along had drifted below where the work was being performed and into energized Cubicle 4. Fortunately, the damage to the wall of the switchgear and come along tool was minimal, which is shown in Figure 11.

Post event analysis proved that the chain of the come along had drifted below where the work was being performed and into an energized cubicle. The chain touched an energized terminal and arced to ground, touching both phase conductor and cabinet ground metal below the non-energized cubicle where the electrician was working. After reviewing minimal damage and completing the project while de-energized, the plant switchgear was cleaned and re-energized. Fortunately, total downtime for the plant due to this event was minimal. No loss of equipment or injury to any employee occurred as a result of this event.

 

Eaton Arc Flash Safety

 

Low voltage assembly involved in planned energized work. The planned task included removing cables from de-energized Cubicle 5 while Cubical 4 in an adjacent section was still energized.

The important take-away here is that the arc flash study was completed before energized work was performed. The upstreamlow voltage power circuit breaker with a special maintenance switch setting discussed previously employed technology to clear the fault faster than the microprocessor instantaneous setting of the circuit breaker trip unit.

Calculations were previously performed that quantified a reduction in incident energy from 17.7 cal/cm2 to2.9 cal/cm2 using the special maintenance setting. Both workersand equipment were saved as a result of a total clearing time at 40 milliseconds as defined by the manufacturer’s published trip curves[8].

Lessons learned

This case study unequivocally proves that planning for the unplanned event can save lives. Some of the key lessons learned here:
• mistakes will happen on even the best planned projects. A change in tools is what led to this arc flash event
• proper planning and leveraging of all accessible resources prevented what could have been a catastrophic event
• leveraging technology can often deliver a reduction in the available energy. Using more sensitive settings can save both people and equipment should an arc flash event occur

Eaton Come Along

At left, a “come along” tool used for energized work and at right, damage to panel after phase to ground arc flash event with an upstream device with maintenance setting capabilities.

This case study is one of four published online by Eaton and has been lightly edited by EIN. See all case studies: http://www.eaton.com/ecm/groups/public/@pub/@eaton/@corp/documents/content/pct_1562591.pdf.

 

Related Articles


Latest Articles

  • New STANDATA Interpretation & Variance: Use of Neutral Conductors in Consumer’s Service Reporting of Electrical Incidents

    New STANDATA Interpretation & Variance: Use of Neutral Conductors in Consumer’s Service Reporting of Electrical Incidents

    October 6, 2025 There are two new STANDATA releases for the province of Alberta: The purpose of these two releases is to clarify requirements for reporting electrical incidents in Alberta and to permit the use of underground service entrance cable (USEB) with a bare neutral conductor in underground installations at service entrance equipment. STANDATA variance… Read More…

  • BizEnergySaver Program Available in Toronto & Ottawa

    BizEnergySaver Program Available in Toronto & Ottawa

    October 6, 2025 Commercial buildings in Ottawa and Toronto’s Richview South area can receive direct installation and instant discounts on energy-saving equipment upgrades for lasting benefits. The Save on Energy BizEnergySaver program is designed to help industrial, commercial and institutional (ICI), and multi-residential building owners and operators make equipment improvements to reduce their energy consumption…. Read More…

  • Electrical Industry Day of Recognition – October 6, 2025: John’s Story

    Electrical Industry Day of Recognition – October 6, 2025: John’s Story

    October 6, 2025 The Electrical Injury Day of Recognition is sponsored by the Electrical Contractors Association of Alberta, the Canadian Electrical Contractors Association, the Electrical Contractors Association of British Columbia, and the National Electrical Trade Council. The Canadian electrical industry is calling on all tradespeople and those who benefit from them, to set aside October 6 as a day… Read More…

  • Research Report: Visible and Invisible Consequences of Electrical Injury

    Research Report: Visible and Invisible Consequences of Electrical Injury

    October 6, 2025 This report was produced by the Infrastructure Health & Safety Association (ISHA). You can find the report, as well as sources on their website. This report has been written by Dr. Manuel Gomez, director of the St. John’s Rehab Research Program at Sunnybrook Health Sciences Centre in Toronto. Electricity is an important… Read More…


Changing Scene

  • Ontario Takes Next Step in Bowmanville Hospital Expansion

    Ontario Takes Next Step in Bowmanville Hospital Expansion

    October 6, 2025 The Ontario government is marking a key milestone in delivering high-quality hospital care for families in Durham Region by issuing a Request for Proposals (RFP) to select the team that will lead the expansion and revitalization of Lakeridge Health’s Bowmanville Hospital. This project will mark one of the largest redevelopments at Lakeridge… Read More…

  • Nova Scotia Takes Further Steps to Unlock Development in Halifax

    Nova Scotia Takes Further Steps to Unlock Development in Halifax

    October 6, 2025 Nova Scotia is taking more action to support housing growth in Halifax Regional Municipality (HRM), issuing new orders and moving policies forward. The measures include Municipal Affairs Minister John Lohr designating HRM as an interim planning area. Under this order, new minimum planning requirements for HRM take effect immediately. The designation also enables… Read More…

  • E.B. Horsman & Son Announces Stephen Murray as New Calgary Branch Manager

    E.B. Horsman & Son Announces Stephen Murray as New Calgary Branch Manager

    October 6, 2025 EB Horsman & Son is pleased to announce the appointment of Stephen Murray as Branch Manager of its Calgary location, effective Tuesday, September 3, 2025. Stephen Murray brings over two decades of experience in the industrial automation sector, where he has built a strong reputation for driving growth, expanding market presence, and… Read More…

  • E.B. Horsman & Son Announces Maxim Laberge as New Process Instrumentation Manager

    E.B. Horsman & Son Announces Maxim Laberge as New Process Instrumentation Manager

    October 6, 2025 EB Horsman is excited to welcome Maxim Laberge as its new Process Instrumentation Manager. Maxim Laberge brings over 25 years of experience in electrical, instrumentation, and control systems, with a proven record in business development, client engagement, and strategic project leadership. He is known for his consultative approach, combining technical insight with… Read More…