Case Study: Temporary Power for Large Scale Residential Construction

Temporary Power

Ever wonder how large construction projects with sales offices and show suites get power when there is only a generator or temporary power established on the construction site?TheBC Safety Authority (BCSA) pays close attention to these types of installations, since fire alarms, sprinklers, and other building code safety systems are not up and running during the construction phase of the project.

Recently, a BCSA safety officer conducted an assessment of a large multi-family residential site under construction. Working collaboratively with electrical contractors, other trades, safety officials, utilities, and building departments to reach safety solutions is an important part of a BCSA safety officer’s role.

During the inspection, several significant hazards were found.Most notably, townhouses had been energized using the temporary construction service, creating a risk of overload to the service. Had these dwellings become occupied, this could have resulted in a serious fire and shock hazard.

An additional hazard was created by the power cable used to provide power from the temporary distribution system to the townhouses, which was not installed with the necessary mechanical protection.Construction sites typically have heavy machinery operating and it is imperative that the power cables be installed in a manner that protects them from mechanical damage.A break in the armoured cable can result in either a fire (if combustible material is near by) or a shock hazard if the bonding provisions have been compromised.

Addressing the hazards
The safety officer first documented his findings in a certificate of inspection and contacted the electrical contractor to develop a plan to rectify the identified non-compliances.The contractor submitted an application for a variance, as required by the Safety Standards Act, to energize the show rooms and sales offices.The variance included a request to energize a specific portion of the site, and outlined the wiring method used to provide power to this area of the site, and the signage required at strategic locations on the site, including mark ups on the site’s safety plans.The safety officer granted the variance and the electrical contractor completed the installation and the obligations outlined in the variance.

To reduce the safety hazards on the site, branch circuits inside each dwelling had all unnecessary circuit conductors disconnected from circuit breakers. The heavy loads such as space heating, furnaces, dryers, ranges were also disconnected.The safety officer then informed BC Hydro and the electrical contractor that a “hold connection” be placed on the permanent installation permit.This ensures that when the permanent installation is ready for power, the necessary work is completed to transfer and disconnect the temporary power in the showrooms to remove the risk of a possible back feed.

When dealing with sites that have both permanent and temporary electrical systems, closely review your electrical code, specifically the stating that interconnection of temporary power installations and permanent installations shall not be interconnected unless by special permission.

This article was first published online by the BC Safety Authority, http://safetyauthority.ca.

 

Related Articles


Latest Articles

  • Industrial Wiring Devices: A Brief Intro and How to Choose Them

    Industrial Wiring Devices: A Brief Intro and How to Choose Them

    June 9, 2025 Introduction: With the multitude of options on the market, it can be difficult to decide whether you need a pin and sleeve wiring device or a plug and connector in your industrial plant or facility. You might find your head swirling with thoughts about which option is best. Or you may not… Read More…

  • Industry Leaders Head to Quebec to Strengthen Energy and Supply Chain Resilience

    Industry Leaders Head to Quebec to Strengthen Energy and Supply Chain Resilience

    June 9, 2025 By Electro-Federation Canada On June 3 and 4, a high-level delegation from Canada’s electrical and automation sector travelled to Montreal and Quebec City for a series of strategic meetings with Quebec government officials and key stakeholders. Organized by Electro-Federation Canada (EFC), this mission underscores the critical role the industry plays in advancing… Read More…

  • Electrifying Connections: A Celebration of Legacy, A Vision for the Future

    Electrifying Connections: A Celebration of Legacy, A Vision for the Future

    June 9, 2025 By Electro-Federation Canada This year’s Annual Industry Conference, held against the breathtaking backdrop of Niagara Falls, Ontario, was a landmark event with more than 710 Electro-Federation Canada community members. More than just a celebration of our shared history, it was a launchpad for new ideas, future-based dialogue, and deeper connections.   The energy and… Read More…

  • Code Quiz: Canadian Electrical Code, Part 1, 26th Edition Section 28 – Motors and Generators

    Code Quiz: Canadian Electrical Code, Part 1, 26th Edition Section 28 – Motors and Generators

    by William (Bill) Burr Question:  Adam is working in his garage cutting wood on his table saw. Suddenly the lights go out and the sump pump and the table saw stop running. There is obviously a power outage. After a short time, the lights and the sump pump come back on, but thetable saw stays off. Adam needs to restart it.  Can you explain why the lights and sump pump come back on… Read More…


Changing Scene

  • Andrey Goreev Joins Mersen Electrical Power as Regional Sales Manager

    Andrey Goreev Joins Mersen Electrical Power as Regional Sales Manager

    June 9, 2025 MERSEN CANADA TORONTO INC. is pleased to announce effective June 2nd, 2025, Andrey Goreev has joined Mersen Electrical Power as Regional Sales Manager for the Western Canada Region. He will report to Tom Arbanas, Vice President of Distribution Sales and Customer Care, Canada. Andrey has over 18 years of experience in industrial… Read More…

  • Electric Avenue Powers Ahead with Major Win and New Flagship Product: Watti Pro Echo

    Electric Avenue Powers Ahead with Major Win and New Flagship Product: Watti Pro Echo

    June 9, 2025 In an industry dominated by global giants, a startup from Canada’s East Coast is quickly becoming one of the most compelling cleantech success stories in the country. Electric Avenue, a Nova Scotia–based EV charging manufacturer, is making waves in the North American market with the official launch of its Watti Pro Echo… Read More…

  • Manitoba and BC Establish Free Trade Agreements

    June 9, 2025 The Manitoba government will sign a new memorandum of understanding with British Columbia to advance free trade between the two provinces and cabinet will pass regulations by July 1 to ensure mutual recognition of other provinces by Canada Day, Premier Wab Kinew announced today at the MBiz Breakfast Series hosted by the… Read More…

  • Nova Scotia Removing Trade Barriers With Other Provinces, Federal Government

    Nova Scotia Removing Trade Barriers With Other Provinces, Federal Government

    June 9, 2025 Trade barriers between Nova Scotia, several provinces and the federal government will soon be removed. Nova Scotia, along with Alberta, British Columbia, Manitoba, Ontario and Prince Edward Island have taken action to remove barriers and red tape that will open up new trade and investment opportunities. It is also anticipated that the… Read More…