PEI Begins Substantial Interconnection Upgrade Project

PEI Interconnection Upgrade

June 31 2016

Prince Edward Island has begun on one of the largest construction projects in its history — replacing and upgrading undersea electrical connections between PEI and New Brunswick.
The Interconnection Upgrade Project, a joint effort with the federal government, will allow PEI to import electricity from New Brunswick through two new 180 MW submarine cables, overhead transmission lines, substation upgrades and more. The submarine cables will be owned by the province and leased to and operated by Maritime Electric. Project costs have been estimated at between $120 million and $140 million.

When the existing submarine cables were installed nearly 40 years ago, the electricity load was 95 MW. In 2015, it peaked at 262 MW. PEI has no natural energy supply sources and relies on off island sources for cost-effective and reliable energy supply. While the province has developed significant wind energy supply, this supply requires back up for times when there is no wind.

The project offers at least five benefits:
• enabling future electrical growth on PEI
• improving reliability for customers
• reducing reliance on fossil-fueled generation
• creating a secure, reliable connection to the mainland
• providing access to a more economic energy supply

What’s involved

The project requires
• installation of two 180 MW submarine cables between Borden, PEI and Cape Tormentine, NB, (16.5 km) in the Northumberland Strait
• construction of 60 km of new overhead transmission line between Cape Tormentine and Memramcook
• construction of a substation extension at Borden, PEI

The project also includes:
• two landfall sites (where the submarine cable trench is brought ashore)
• two termination sites (for converting submarine cables to overhead transmission lines or substation)
• upgrading of the New Brunswick Power Corporation (NB Power) substation in Memramcook, NB

The first construction phase involves pre-trenching. This process involves a marine excavator called a Starfish and two mechanical marine dredges: one at PEI’s Borden-Carleton site and the other at New Brunswick’s Cape Tormentine site.

On the Cape Tormentine side the Starfish will be used excavate approximately 600 metres from shore into the Northumberland Strait. Once that distance is reached the Starfish will be shipped to the PEI side and the mechanical marine dredge will continue to excavate to the 1.8 km mark offshore.

The Starfish will be in operation for 12 hours daily for excavation. The two mechanical marine dredges will be working 24 hours per day on excavation. This process, expected to take 6-8 weeks, will ensure there are no rock obstructions along the route when the cable is laid in mid October.

The two cables will be installed under the seabed in separate trenches, up to 200 m apart. In water depths of greater than 12 m the cables will be buried at 0.6 m, while in areas of less than 12 m of water the cable will be buried at approximately 2 m. Excavating within the marine environment will involve trenching with excavators in water depths up to 2 m and a trenching remotely operated vehicle (TROV) with a saw cutter for the remaining sections. Exclusion zones around the cables are not planned. There will be no fishing restrictions. Once the cables have been installed, navigation charts will be updated.

The entire project is scheduled for completion in late spring or early summer 2017.

 

 

Related Articles


Latest Articles

  • Building a Greener Future – BuildForce Canada Report

    May 3, 2024 Retrofitting Canada’s residential, commercial, and institutional building stock to incorporate sustainable fuel sources, technologies, and materials could require as many as 57,000 additional construction workers and generate more than $81 billion in new construction investments by 2032. A new report prepared by BuildForce Canada, Building a Greener Future: Estimating the impact on construction… Read More…

  • HELUKABEL White Paper: “PUR or PVC”

    HELUKABEL White Paper: “PUR or PVC”

    May 3, 2024 The jacket material is a key factor when looking for the right cables and wires. The outer jacket performs a multitude of functions that ensure the durability, safety and performance of the cable or wire. Users must often choose between polyurethane (PUR) and polyvinyl chloride (PVC). In our new white paper “PUR… Read More…

  • Electric Avenue Annouces Improved Cold Temperature Rating of -40 Degrees

    Electric Avenue Annouces Improved Cold Temperature Rating of -40 Degrees

    April 26, 2024 Electric Avenue, a leading innovator in electric vehicle (EV) charging solutions, is thrilled to announce significant improvements to the cold temperature performance of its flagship products, the Watti Pro Lite and Watti Home Gen2. After comprehensive environmental testing, both chargers now boast an impressive operational rating of -40 degrees Celsius, surpassing the… Read More…

  • Electrical Incidents in Alberta for 2023

    Electrical Incidents in Alberta for 2023

    April 26, 2024 Regulations under the Safety Codes Act require that all electrical accidents and power line contacts be reported. This annual report by Municipal Affairs compiles a summary of incidents reported during the calendar year. Organizations in the electrical industry may wish to use this information for promoting public awareness of electrical safety risks…. Read More…


Changing Scene

  • Alberta Continues Campaign to Attract Skilled Trades People from Other Provinces

    Alberta Continues Campaign to Attract Skilled Trades People from Other Provinces

    May 3, 2024 To help fill critical job vacancies in the skilled trades, Alberta’s government has launched the third phase of the successful Alberta is Calling campaign, which is now in-market in British Columbia, Québec and Ontario. This campaign is bolstered by the Alberta is Calling Moving Bonus – a one time, $5,000 refundable tax… Read More…

  • Siemens Launches Depot360 Zero-Emission Fleet Management in Canada

    Siemens Launches Depot360 Zero-Emission Fleet Management in Canada

    May 3, 2024 With transportation being the second biggest emitter of greenhouse gases and road transport responsible for almost three quarters of these emissions globally*, Siemens Smart Infrastructure has launched Depot360, a portfolio to optimize fleet electrification. The initial focus of the solution is on logistics vehicles, municipal transit and private bus fleets within depot,… Read More…

  • Le Salon Lumen: Lumen Hosts 2024 Quebec Electrical Industry Blockbuster Customer Event

    Le Salon Lumen: Lumen Hosts 2024 Quebec Electrical Industry Blockbuster Customer Event

    (Photo caption: (From left to right) Lumen President, Serge LeBlanc, Sonepar Canada President, George McClean, Sonepar Americas President, Rob Taylor, and Sonepar CEO, Philippe Delpech in the Lumen booth, at Le Salon Lumen.) May 3, 2024 This month, Lumen held their 12th edition of the Salon Lumen, the largest exhibition in Quebec’s electrical industry. The… Read More…

  • Surgepure Announces Partnership with Focus Electrical Sales for the East Coast

    Surgepure Announces Partnership with Focus Electrical Sales for the East Coast

    May 3, 2024 SURGEPURE CORPORATION, a manufacturer of non-degrading hi-energy surge protection devices, announces a strategic partnership with Focus Electrical Sales. Based in the Maritimes, Focus Electrical Sales represents leading edge lighting and electrical manufacturers in North America. Focus adds extensive local application and technical support with offices in Nova Scotia, New Brunswick and Newfoundland,… Read More…