S&C Self-Healing Technology Saves Enmax 30 Million+ Customer Minutes

Enmax

 Oct 6, 2017

Enmax Power Corporation, an Alberta-based utility, was facing more frequent and longer power interruptions, causing its reliability rating from the Canadian Electricity Association to slide toward the third quartile. With a goal of achieving first-quartile reliability, Enmax took on the challenge to improve its system reliability.

To tackle this task, Enmax put out a call for bids for a five-year distribution automation project that would improve the reliability of its worst-performing circuits and enhance the utility’s ability to operate its distribution system safely and reliably. Enmax set goals to achieve and maintain top-level reliability performance, as measured against peer Canadian utilities through the System Average Interruption Duration Index (SAIDI) and System Average Interruption Frequency Index (SAIFI). Canadian utilities, including Enmax, are held to a more stringent one-minute threshold compared to the five-minute threshold of the IEEE SAIFI calculation.

S&C solution

After a rigorous selection process, Enmax chose S&C, with whom it had a working relationship spanning six decades. This experience enabled S&C to understand Enmax’s needs to improve reliability.

Enmax conducted extensive reliability studies to ascertain the best locations for the automation switching points. S&C conducted a radio-frequency study, training Enmax personnel to perform this work as they expanded the system and the radio communication system that enabled peer-to-peer communication between the switches deploying S&C’s IntelliTeam II Automatic Restoration System. Using the results of that research, S&C and Enmax designed a comprehensive plan, assessing the most cost-effective use of resources to target the worst performing feeders, and to ensure the utility obtained the maximum value from the system.

At the start of the project, ENMAX deployed S&C’s Scada-Mate Switching System along with remote supervisory PMH pad-mounted switchgear controlled by S&C switch controls with radio communication to automatically reroute power in the event of an outage. As the technology evolved, ENMAX decided to deploy IntelliRupter PulseCloser fault interrupters on the overhead system to further improve reliability and address momentary interruptions (shown in photo).

The addition of S&C’s PulseClosing technology to the system, which uses 95% less energy than reclosing when testing for faults, also reduced the mechanical stress exerted on Enmax’s network, thereby increasing asset life. The communication system was also upgraded to S&C’s SpeedNet radios, offering faster communication speeds.

S&C additionally provided technical support and comprehensive training to enable the Enmax team to use the S&C equipment to its full potential.
To date, Enmax has automated 155 feeders using Scada-Mate switching system controls, IntelliRupter PulseCloser fault interrupters, remote supervisory PMH pad-mounted switchgear, and Vista underground distribution switchgear, all controlled by the IntelliTeam II automatic restoration system. This deployment represents 50% of the Enmax distribution system.

Results

Over the course of the five-year project, Enmax realized significant reliability-improvement benefits. These proven benefits, coupled with the potential future benefit of continuing the project, encouraged the utility to continue with an ongoing program, currently in its 15th year.

To date, the project has saved Enmax more than 602,000 customer interruptions and 32.1 million customer minutes of interruption. The resulting reductions in SAIDI and SAIFI have allowed Enmax to become a top performer for utility reliability.

“We are reaching reliability figures that would just not be possible without S&C technology,” says Dean Craig, Manager Grid Modernization, Enmax. “We are proud to have partnered with S&C on this journey and continue to work together to automate the rest of our network.”

Upon reaching its goal of becoming a first-quartile performer for reliability, Enmax decided to examine the overall economics of reliability improvement. To this end, Enmax has conducted multiple studies that incorporate data developed by the U.S. Department of Energy and Lawrence Berkeley National Laboratories to assess the cost of interruptions to all power users. The studies compared the capital cost to the utility of continued deployment of distribution automation to the savings in customer interruption costs from the resulting improvement in reliability. In the most recent study, the projected customer savings outweighed the cost of automating additional feeders by a factor of 2.5 to 1, justifying the automation of 27 more feeders. See the table below.

Together, Enmax and S&C continue to demonstrate the IntelliTeam II restoration system’s self-healing technology provides significant reliability benefits to power utility customers.

Some 27 of the 128 13-kV feeders have higher customer-outage savings than the cost of distribution-automation implementation.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Related Articles


Latest Articles


Changing Scene

  • Siemens to Establish Global AI Manufacturing Technologies R&D Center for Battery & EV Production in Canada

    Siemens to Establish Global AI Manufacturing Technologies R&D Center for Battery & EV Production in Canada

    May 26, 2025 Siemens will invest CAD $150 million over five years to establish a Global AI Manufacturing Technologies Research and Development (R&D) Center for Battery Production in Canada. The new R&D center, located initially at Siemens Canada’s head office in Oakville, as well as in Toronto and Kitchener-Waterloo, Ontario, will focus on developing cutting-edge AI manufacturing technologies with an initial emphasis… Read More…

  • Honda Postponing Ontario EV Supply Chain Investment by Two Years

    Honda Postponing Ontario EV Supply Chain Investment by Two Years

    May 26, 2025 Honda is postponing its plan to invest in a comprehensive EV supply chain in Ontario. The CBC reported that the investment is being push back by two years. “Due to the recent slowdown of the EV market, Honda Motor has announced an approximate two-year postponement of the comprehensive value chain investment project in Canada…. Read More…

  • Serge Leblanc Named Sonepar Canada Interim President

    Serge Leblanc Named Sonepar Canada Interim President

    May 26, 2025 George McClean, former President of Sonepar Canada, has decided to leave Sonepar for an opportunity outside of the electrical industry. Serge Leblanc, current President of Lumen Canada, has been appointed interim President of Sonepar Canada. Leblanc will manage both responsibilities until a successor is named.  Leblanc joined Lumen in 1997 and has… Read More…

  • Ontario Building and Construction Tradeswomen Head to Queens Park to Advocate for Safer, More Inclusive Job Sites

    Ontario Building and Construction Tradeswomen Head to Queens Park to Advocate for Safer, More Inclusive Job Sites

    May 26, 2025 On Monday, May 26, the Ontario Building and Construction Tradeswomen (OBCT), will host its first-ever Advocacy Day at Queen’s Park. Tradeswomen from across the province will gather to meet with Members of Provincial Parliament, including Minister of Labour David Piccini, to advocate for progress in the skilled trades for tradeswomen. OBCT’s top priorities include:… Read More…