Top 22 Changes You Need to Know About in the 2018 Canadian Electrical Code

EIN Code changes 400

Feb 3, 2020

By Technical Safety BC

BC’s Electrical Safety Regulation has been amended to include the adoption of the 2018 version of the Canadian Electrical Code. The new code includes several changes to support electrical workers in the safe installation and maintenance of electrical equipment and systems. It came into effect on January 1, 2020.

These are the top changes you’ll need to know about when performing regulated electrical work starting January 1, 2020:

Higher Impact Changes

  1. Working Space around transformers has changed – see 2018 CEC Rule 2-312
    ●  Rule now includes requirements for transformer clearances
     
  2. Identified conductors at switch locations – see 2018 CEC Rule 4-022
    ●  You now require an identified conductor (white) at each switch
     
  3. Separation of line and load conductors in service switches – see 2018 CEC Rule 6-212
    ●  In a service switch the line and load conductors cannot cross or contact each other
     
  4. Electrical Vehicle Energy Management Systems – see 2018 CEC Rules 8-002, 8-106, 8-500 and 86-302
    ●  New rules for calculating demand when using an energy management system
     
  5. Bonding cables at service equipment -– see 2018 CEC Rule 10-604
    ●  In previous codes a bond bushing was not required on service cable (ie. TECK/ACWU). Changes to section 10 require bonding bushings unless the cable’s metal sheath is in continuous contact with the cable bonding conductor. This is not the case in most TECK/ACWU cables.
     
  6. Single Point Grounding – see 2018 CEC Rule 10-210
    ●  The new 10-210 allows for only a single connection to the system grounding conductor by the identified conductor through a bonding jumper
     
  7. Cable installations under slabs on grade – see 2018 CEC Rule 12-012
    ●  The code has always allowed conduit to be installed directly below a slab on grade, the new 2018 code now references raceways and armoured or metal sheathed cables as well.
     
  8. Suspended ceiling power distribution systems – see 2018 CEC Rule 12-2300 series
    ●  New rules for new technology – “T-Bar” grid power systems
     
  9. Power over Ethernet – see 2018 CEC Rule 16-300
    ●  New rules for new technology – Power over Ethernet
     
  10. Qualified person (Hazardous Locations) – see 2018 CEC Rule 18-004
    ●  The 2018 code requires that all Hazardous area classifications are to be carried out by a “qualified person” as defined in Section 0 of the code.
     
  11. Smoke Alarm – Battery Back-up – AFCI/GFCI – see 2018 CEC Rule 32-200
    ●  Changes to section 32 regarding allowance for Smoke alarms and Smoke/CO alarms to be connected to branch circuits protected by AFCI or GFCI

Medium/ Lower Impact Changes

  1. Grounding transformer with feeder cable – see 2018 CEC Rule 10-212
    ●  Under 750V the transformer can be grounded by the system bonding conductor in the primary supply
     
  2. AFCI in renovation scenarios – see 2018 CEC Rule 26-656
    ●  In a renovation, adding to an existing circuit does not require the entire circuit to be AFCI protected
     
  3. Splicing of system grounding permitted – see 2018 CEC Rule 10-116
    ●  The code only requires the conductor to be electrically continuous, not without a splice.
     
  4. Grounding of overhead sub distribution (10-208 “other” buildings) – see 2018 CEC Rule 10-212
    ●  There is to be no connection to the non-current carrying conductive parts on either the supply side or load side of the grounding connection. This will have implications for overhead sub-distribution systems using neutral supported cables (ie. triplex)
     
  5. Relaxation of liquid-tight flex use – see 2018 CEC Rule 12-1302
    ●  The proposal allows for liquid-tight flexible metal and non-metallic conduit to be used in a manner less restrictive due to updates in technology of the product.
     
  6. Bathroom receptacles and AFCI protection implications – see 2018 CEC Rule 26-656 and 26-720
    ●  Based on the 2015 wording of rule 26-724(f), as long as a washroom or bathroom receptacle was on a circuit, the entire circuit would be exempt from AFCI requirements. This has been addressed.
     
  7. Kitchen Nook – requirement removed – see 2018 CEC Rule 26-654
    ●  No more requirements for “area’s forming part of a kitchen” to have separate branch circuit
     
  8. Increased voltage for PV systems to 1500V – see 2018 CEC Rule 64-202
    ●  Increased voltages to address new technology
     
  9. Labelling for Maximum Continuous Load – see 2018 CEC Rule 2-100
    ●  Code now requires permanent marking to indicate maximum continuous load permitted.
     
  10. Changes to Photovoltaic Rapid Shutdown requirements – see 2018 CEC Rule 64-218
    ●  Decreased distance from array and increase in time for shutdown initiation
     
  11. Heating Devices and Controls – see 2018 CEC Rule 62-130 and 62-132
    ●  Code now has GFCI requirements for both the heating devices and the controls when in proximity to sinks, tubs, or shower stalls

To support the new code adoption, Technical Safety BC is offering 2018 Electrical Code Change Training in several cities across the province.

Online 2018 code change courses will be available starting February 17, 2020. See the dates and sign up on our Learning Centre.

Technical Safety BC is an independent, self-funded organization that oversees the safe installation and operation of technical systems and equipment across the province. In addition to issuing permits, licences and certificates, we work with industry to reduce safety risks through assessment, education and outreach, enforcement, and research. To learn more, visit www.technicalsafetybc.ca.

Source

Related Articles


Latest Articles


Changing Scene

  • Federal Investment to Add 989 New Montreal Homes

    Federal Investment to Add 989 New Montreal Homes

    November 18, 2024 The federal government is providing nearly $364 million to help build 989 new homes in Montreal. The announcement took place at 5200 rue de la Savane, in Montreal, which received $100 million dollars through the Apartment Loan Construction Program (ACLP) to build 303 homes and will be operated by Olymbec. This rental building, named Lynk, is designed to… Read More…

  • ABB and NIEDAX Group Announce Completion of Joint Venture with the Formation of Abnex Inc.

    ABB and NIEDAX Group Announce Completion of Joint Venture with the Formation of Abnex Inc.

    November 18, 2024 ABB completed the previously announced 50/50 joint venture with Niedax Group. The Abnex Inc. joint venture (JV) will broaden solutions and advance opportunities in the rapidly growing North American cable management market. Integrating engineering and manufacturing capabilities of ABB’s Installation Products Division with Niedax Group will enable the newly formed company to deliver a… Read More…

  • Ontario Building More Electric Vehicle Charging Stations

    Ontario Building More Electric Vehicle Charging Stations

    November 18, 2024 The Ontario government is building over 1,300 new electric vehicle (EV) charging ports in small and medium-sized communities, marking a major milestone in the province’s plan to increase access to EV chargers outside of large urban centres and support the electrification of transportation across the province. As the province continues to see… Read More…

  • Ontario Investing Over $74 Million Through Next Round of Skills Development Fund Capital Stream

    Ontario Investing Over $74 Million Through Next Round of Skills Development Fund Capital Stream

    November 18, 2024 The Ontario government is launching the second round of its Skills Development Fund (SDF) Capital Stream starting November 29, with over $74 million in available funding to build, expand and retrofit training facilities for workers in the trades, including construction, manufacturing technology and health care. The government is also investing nearly $5 million from the first… Read More…