Arc Flash Incident Involving a Maintenance Switch

Maintenance Switch

 

Feb 12, 2016

This case study article examines the plans and processes reviewed and considered, the strategy deployed to manage/reduce arc flash hazards, and then lessons learned in the implementation of new systems to improve electrical workplace safety. The setting: a chemical processing facility with a robust electrical workplace safety process. The site experienced an actual arc flash event while energized work was being performed.

Photo courtesy: www.utilityproducts.com

The facility was planning energized work for an existing 480 V low voltage switchgear assembly that was an existing piece of equipment in the plant. During a process upgrade in the facility, an energized work permit was issued to remove three abandoned load conductors from an existing 480 V low voltage switchgear assembly cable compartment.

The work permit was very detailed and included tools planned for use in the project and required PPE for workers performing the task based on the incident energy defined by a recently completed arc flash hazard assessment. The defined task for the work order required the site contractor to use a nylon rope, which was typical with this type of project, disconnecting the de-energized cables and working to raise them from the top cable compartment. Figure 10 showsa layout of the low voltage assembly involved in the work.

The de-energized cables were to be removed from Cubicle 5, with still energized conductors existing in Cubical 4 at the bottom of the cable wireway. The rope used was not able to grab the conductors and would slip off of the cable, so the electrical contractor elected to employ a “come along” to assist in the removal, as the come along could apply more force. The first conductor was successfully removed with this new tool. Upon removing the second conductor, a small arc flash was observed in the lower compartment. Simultaneously, the lights to the plant went out.The contractor stopped work and waited for plant electricians to arrive, not knowing what had just occurred.

The event caused the entire plant to shut down, stopping work on the project until an analysis could be completed. It was determined that the chain of the come along had drifted below where the work was being performed and into energized Cubicle 4. Fortunately, the damage to the wall of the switchgear and come along tool was minimal, which is shown in Figure 11.

Post event analysis proved that the chain of the come along had drifted below where the work was being performed and into an energized cubicle. The chain touched an energized terminal and arced to ground, touching both phase conductor and cabinet ground metal below the non-energized cubicle where the electrician was working. After reviewing minimal damage and completing the project while de-energized, the plant switchgear was cleaned and re-energized. Fortunately, total downtime for the plant due to this event was minimal. No loss of equipment or injury to any employee occurred as a result of this event.

 

Eaton Arc Flash Safety

 

Low voltage assembly involved in planned energized work. The planned task included removing cables from de-energized Cubicle 5 while Cubical 4 in an adjacent section was still energized.

The important take-away here is that the arc flash study was completed before energized work was performed. The upstreamlow voltage power circuit breaker with a special maintenance switch setting discussed previously employed technology to clear the fault faster than the microprocessor instantaneous setting of the circuit breaker trip unit.

Calculations were previously performed that quantified a reduction in incident energy from 17.7 cal/cm2 to2.9 cal/cm2 using the special maintenance setting. Both workersand equipment were saved as a result of a total clearing time at 40 milliseconds as defined by the manufacturer’s published trip curves[8].

Lessons learned

This case study unequivocally proves that planning for the unplanned event can save lives. Some of the key lessons learned here:
• mistakes will happen on even the best planned projects. A change in tools is what led to this arc flash event
• proper planning and leveraging of all accessible resources prevented what could have been a catastrophic event
• leveraging technology can often deliver a reduction in the available energy. Using more sensitive settings can save both people and equipment should an arc flash event occur

Eaton Come Along

At left, a “come along” tool used for energized work and at right, damage to panel after phase to ground arc flash event with an upstream device with maintenance setting capabilities.

This case study is one of four published online by Eaton and has been lightly edited by EIN. See all case studies: http://www.eaton.com/ecm/groups/public/@pub/@eaton/@corp/documents/content/pct_1562591.pdf.

 

Related Articles


Latest Articles

  • Building Permits, June 2025

    Building Permits, June 2025

    August 14, 2025 In June, the total value of building permits issued in Canada decreased by $1.2 billion (-9.0%) to $12.0 billion. Ontario’s institutional component (-$1.4 billion) led the decline in construction intentions in June, after driving the growth in May. On a constant dollar basis (2023=100), the total value of building permits issued in June decreased 9.5% from the… Read More…

  • Investment in Building Construction, May 2025

    Investment in Building Construction, May 2025

    August 6, 2025 The total value of investment in building construction decreased by $491.4 million to $21.8 billion in May. Investment in the residential sector fell 3.0%, while the non-residential sector edged down 0.4%. On a constant dollar basis (2023=100), the total value of investment in building construction in May was down 2.3% from the previous month and was up 3.1%… Read More…

  • Ontario Electrical League Welcomes Premier to Highlight Skilled Training Investment

    Ontario Electrical League Welcomes Premier to Highlight Skilled Training Investment

    August 28, 2025 This round of the  Skills Development Fund (SDF) Training Stream will provide $260 million for innovative projects that support the hiring, training and upskilling of workers in manufacturing, health care, construction, automotive and other skilled trades.  Ontario Electrical League will recieve $2,995,000 to help 500 journeypersons, registered apprentices, people residing in remote/rural communities… Read More…

  • ABB Invests in Made in Canada with Installation Products that Electrify Our World 

    ABB Invests in Made in Canada with Installation Products that Electrify Our World 

    August 28, 2025 By Krystie Johnston  ABB recently announced their plan to build a new R&D and manufacturing facility in Canada. It will combine their existing facilities in Iberville and Saint-Jean-sur-Richelieu to increase production capacity and support future growth in key sectors across Canada like utilities, energy, and infrastructure. Michael Shenouda, Canada Region Leader –… Read More…


Changing Scene

  • EB Horsman Introduces Sean O’Brien as New Burnaby Branch Manager

    EB Horsman Introduces Sean O’Brien as New Burnaby Branch Manager

    August 20, 2025 EB Horsman & Son is pleased to announce the promotion of Sean O’Brien to Branch Manager of their Burnaby location, effective August 6, 2025. Sean brings over 15 years of experience in the electrical and lighting industry, with a strong background in sales, technical leadership, project management, and clean energy initiatives. He… Read More…

  • Houle Selected as Electrical and Technology Contractor for the New BC Cancer Centre

    Houle Selected as Electrical and Technology Contractor for the New BC Cancer Centre

    August 25, 2025 Houle are proud to announce they been selected as the electrical and technology contractor for the new BC Cancer centre at the Royal Inland Hospital campus in Kamloops. Located adjacent to Royal Inland Hospital, this five-storey cancer centre will provide people in BC’s Interior with expanded access to cancer care closer to… Read More…

  • Ontario Skilled Training Investment Includes NETCO and IBEW

    Ontario Skilled Training Investment Includes NETCO and IBEW

    August 28, 2025 The Ontario government is investing over $23 million through the Skills Development Fund (SDF) Training Stream to help more than 4,200 people across Mississauga and surrounding areas access better training for in-demand sectors such as construction, health care, transportation, manufacturing, aerospace and the skilled trades. Electrical industry recipients: National Electrical Trade Council (NETCO) Ontario Electrical Industry… Read More…

  • New Solar Lighting Manufacturer, Solvic Joins Contact Delage

    New Solar Lighting Manufacturer, Solvic Joins Contact Delage

    August 25, 2025 Contact Delage are excited to announce the addition of a new trusted partner to their lineup: Solvic, an innovative manufacturer specializing in solar lighting. This new partnership reflects Contact Delage’s ongoing commitment to offering sustainable, high-performance solutions tailored to real-world applications. With Solvic, they’re expanding their range of autonomous solar products—perfect for lighting… Read More…