Transformer Short Circuit Considerations

March 9 2016

Short circuits or faults can and do occur on electric power and distribution systems. When a fault occurs on the load side of a transformer, the fault current will pass through the transformer. As components on these systems, transformers need to be able to withstand these fault currents.

Fault currents flowing through transformers are significantly higher than the rated currents of the transformers. In a worst case scenario, the current would be as high as the current that would flow if system voltage was applied to the primary terminals while the secondary terminals are shorted — limited by the transformer impedance only. These currents produce both mechanical and thermal stresses in the transformers.

Photo credit: Hammond Power Solutions

Forces resulting from the currents passing through the transformer act on the conductors. The forces are a function of the peak asymmetrical current (the highest peak value of any cycle of the current), which is usually at its highest during the first half cycle of the fault. The duration of the fault is not normally a concern for mechanical withstand because the peak value of each cycle of the current reduces as the fault persists. The transformer manufacturer needs to ensure these forces do not damage the transformer.

The thermal stress is caused by the high current causing heating in the transformer. Both the RMS symmetrical current magnitude and duration of the fault contribute to the heating of the transformer. The transformer manufacturer needs to ensure the components of the transformer do not become hot enough to be damaged.

General purpose dry type transformers are typically designed to withstand the mechanical and thermal stresses caused by a short circuit occurring on the secondary terminals of the transformer with rated voltage applied to the primary terminals for a maximum of 2 seconds, provided the current does not exceed 25 times rated current. The fault current magnitude is a function of the transformer impedance. The table below shows the fault current for selected impedances and applies to both line currents and phase currents.

 

Transformer Impedance  Fault Current (times rated)
4.0% 25.0
5.0% 20.0
6.0% 16.7
7.0% 14.3
8.0% 12.5

 

The maximum of 25 times rated current is listed so that transformers with an impedance below 4% need only be able to withstand 25 times rated current, although the fault current could be higher than this. It does not mean that all transformers are able to handle a fault current up to 25 times rated current. With rated voltage applied to the primary a transformer impedance above 4% will not allow 25 times rated current to flow.

Many specifications indicate a fault level at the primary terminals of the transformer. Some customers will ask for a transformer to be braced for the primary fault level. A general purpose transformer is suitable to be connected to a system with the specified fault level, but the transformer impedance will limit the fault current through it to well below the available fault level. As an example, the customer requests a 2500 kVA transformer, 13.8 kV delta to 480Y/277 V, 5.75% impedance to be braced for 750 MVA fault level at 13.8 kV. In this case, the available fault current at the primary terminals is 31.4 kA. For a fault on the secondary side of the transformer, the transformer impedance will limit the fault current that flows in the primary to 1.8 kA in the lines and 1.1 kA in the coils — significantly lower than the available fault level. There is no need for the transformer primary conductors to be sized and braced to handle a 31.4 kA fault current.

Some operating conditions need special attention. Some customers specify the transformer to operate continuously with load at higher than rated voltage. If a fault occurs when the transformer is operating at higher than rated voltage, the resulting fault current would be higher than a typical transformer is designed for. This will increase both the forces in the transformer and the heating of the transformer. Some customers specify a fault duration longer than 2 seconds without specifying a higher voltage. This does not affect the forces but does increase the heating in the transformer. In these cases, a special design may be required.

One case in particular requires special attention: transformers directly connected to a generator. When a generator is supplying a load and the load is suddenly disconnected, the output voltage of the generator rises significantly for a short time until the excitation system decreases the voltage. If a fault occurs on the secondary of a transformer at this time, the fault current can be significantly higher than a typical transformer is designed for. Some applications may not have any overcurrent protection between the generator and the transformer primary winding, resulting in an increased duration. In such cases, it is recommended that IEEE C57.116 IEEE Guide for Transformers Directly Connected to Generators be reviewed to determine the short circuit withstand requirement for the transformer.

General purpose transformers have short circuit withstand capabilities that are sufficient for many applications. The transformer manufacturer needs to be informed of cases where a fault could occur on the secondary of the transformer when the transformer is supplied above rated voltage or the fault duration is longer than two seconds to ensure the transformer is suitably designed to withstand the possible secondary faults.


This document was first published as a white paper by Hammond Power Solutions, the largest manufacturer of dry-type transformers in North America. Hammond Power Solutions engineers and manufactures a wider range of custom transformers that are exported globally in electrical equipment and systems. The firm supports solid industries such as oil and gas, mining, steel, waste and water treatment, and wind power-generation.

 

 

Related Articles


Latest Articles

  • Beyond the Bid: How Modern Estimating Solutions Drive Contractor Success

    Beyond the Bid: How Modern Estimating Solutions Drive Contractor Success

    August 18, 2025 By Brooke Stewart In today’s fast-paced construction landscape, electrical contractors are constantly pressured to keep their estimates competitive, often at the expense of healthy profit margins. Compounding this challenge are rising material costs, a shortage of skilled labor and siloed data, all of which make it increasingly difficult to stay competitive and… Read More…

  • Hammond Power Solutions Helps EFC Champion Sustainability as First Carbon Neutral Sponsor at Annual Industry Conference

    Hammond Power Solutions Helps EFC Champion Sustainability as First Carbon Neutral Sponsor at Annual Industry Conference

    August 18, 2025 By Electro-Federation Canada Did you know that carbon emissions from this year’s Annual Industry Conference were offset? With the help of Hammond Power Solutions (HPS), EFC took an important step toward reducing our environmental impact by offsetting the emissions associated with the event. This milestone reflects a growing commitment within the electrical… Read More…

  • FortisBC Detail Impact of their Energy-Efficiency Programs in 2024

    FortisBC Detail Impact of their Energy-Efficiency Programs in 2024

    August 18, 2025 In 2024, FortisBC Energy Inc. and FortisBC Inc.’s (collectively FortisBC) conservation and energy-efficiency programs helped lower gas and electricity use while helping create more comfortable living and working spaces for customers. Building on 2023 reductions, its gas programs cut close to one million tonnes of carbon dioxide equivalent (tCO₂e) 1 in 2024. “Our customers’… Read More…

  • BC Hydro Energy Storage Incentive

    BC Hydro Energy Storage Incentive

    August 18, 2025 Energy storage systems (ESS) provide reliability and resiliency for businesses and the grid alike while helping to reduce GHG emissions as an alternative to diesel backup generation. Storing energy can help manage peak demand charges, reduce peak loads on the grid and provide electricity during outages.  The offer BC Hydro are offering… Read More…


Changing Scene

  • Blackline Safety Announces Quality Assurance Program Expansion

    August 18, 2025 Blackline Safety Corp. has announced a major expansion of its quality assurance (QA) program. As part of the expansion, the company has increased its QA team, upgraded its inspection equipment, and boosted in-lab testing of its entire product line. Headquartered in Canada with offices in the UK, France, U.S., and UAE, Blackline… Read More…

  • EB Horsman Introcuce New Burnaby Branch Manager

    EB Horsman Introcuce New Burnaby Branch Manager

    August 18, 2025 EB Horsman & Son is pleased to announce the promotion of Sean O’Brien to Branch Manager of their Burnaby location, effective August 6, 2025. Sean brings over 15 years of experience in the electrical and lighting industry, with a strong background in sales, technical leadership, project management, and clean energy initiatives. He… Read More…

  • BCCA Response to “Report on 2026 Budget Consultation”

    BCCA Response to “Report on 2026 Budget Consultation”

    August 18, 2025 BCCA is pleased to receive the Standing Committee on Finance and Government Services’ Report on the 2026 Budget Consultation, and celebrates the emphasis placed on supporting BC’s construction industry and workforce. Chris Atchison, President of the BCCA, spoke to the Committee on the recommendations and priorities of BC’s construction industry. These included:… Read More…

  • NSAA Introduces Mentorship for Women Apprentices Program

    NSAA Introduces Mentorship for Women Apprentices Program

    August 18, 2025 This program is designed to support the retention and progression to certification of women apprentices in the 39 Red Seal Construction or Manufacturing trades. The program pairs women apprentices with experienced tradespeople to provide guidance, career development, and support throughout their apprenticeship journey. The program is for 6 months, with the mentor and… Read More…