Nova Scotia White Rock Hydro System Turns 65

Nova Scotia Power

November 30, 2017

The White Rock hydro facility is celebrating its 65th birthday this year, and it’s a good time to undertake repairs that will help extend its useful life.

Work has gottten underway on the dam embankment to ensure it remains stable, prevent future leaks and to meet current Canadian Dam Safety guidelines. This work will require drainage of the White Rock canal, which is scheduled to begin early next week.

“A lot of us think about retiring when we turn 65, but not our hydro systems – they have decades of great working life left ahead them,” said Tim Curry, Hydro Supervisor with Nova Scotia Power. “Just like the rest of us, though, they benefit from good upkeep, so we regularly assess our hydroelectric facilities and perform maintenance to ensure they will continue to provide clean, renewable energy for future generations.”

Nova Scotia Power are working with federal Fisheries staff to safely relocate any fish in the canal while the work is underway, and minimize any impacts on the local fish habitat.

Crews will set up a perimeter and warning signs at the White Rock dam site entrance and the area of the canal to be drained. The public is asked to take safety precautions while this work is underway by avoiding travel through this area until the project is wrapped up over the next three weeks.

“The safety of our employees, contractors, and the public is our top priority,” Curry said. “So we’d really ask for the public’s cooperation in ensuring we can carry out this work safely.”

The 3.4 megawatt hydroelectric station at White Rock was built in 1952. It is part of the Black River hydro system, which also includes generating stations at Methals, Hollow Bridge, Lumsden, and Hell’s Gate. White Rock is the youngest station on the Black River system; Hell’s Gate dates back to 1931. Together, the generators on the Black River system produce enough electricity to power more than 10,000 homes.

Nova Scotia Power owns and maintains 33 hydro generating stations positioned along 17 river systems across the province. In 2016, 28 per cent of Nova Scotia’s electricity came from renewable sources, including eight per cent from hydro and tidal generation. Hydro will help us achieve our 2020 requirement for 40 per cent of electricity to be generated from renewable energy sources.

Related Articles


Latest Articles

  • ABB Wins New Product Award at MCEE Show

    ABB Wins New Product Award at MCEE Show

    April 28, 2025 ReliaHome™ Smart Panel won Best New Product Award in the Software, Controls and Related Components category. Iberville® Gangable boxes with low-voltage cables support bracket was recognized as a finalist in the Commercial, Institutional and Industrial Electrical Products category. ABB was honored with a Best New Product Award in the Software, Controls and… Read More…

  • Weidmuller Celebrating a Legacy: 175 Years Globally, 50 Years in Canada

    Weidmuller Celebrating a Legacy: 175 Years Globally, 50 Years in Canada

    April 28, 2025 The year 2025 is truly special for Weidmüller. The company proudly celebrates not just 50 remarkable years in Canada but also its 175th anniversary globally—an extraordinary achievement few companies can claim. This legacy is a testament to the company’s relentless pursuit of innovation and commitment to refining its offerings. But the journey… Read More…

  • Canada Stands Tall at Hannover Messe 2025

    Canada Stands Tall at Hannover Messe 2025

    April 28, 2025 By Owen Hurst At Hannover Messe earlier this month Canada had a strong presence as the host country with a wide variety of companies and programs focusing on the development of advance technology. The presence was accentuated by numerous halls hosting Canada pavilions. Partner Country Canada presented itself impressively at HANNOVER MESSE…. Read More…

  • BC Prompt Payment Legislation Progressing

    BC Prompt Payment Legislation Progressing

    April 28, 2025 Consistent with its mandate of growing the economy, the government wants to ensure that businesses are paid promptly for work performed on (or material provided to) construction projects. British Columbia’s Ministry of Attorney General staff have been tracking the issue of payment delay in the construction industry, including legislative responses in other… Read More…


Changing Scene

  • Schneider Electric Advances in Product Environmental Data Transparency

    Schneider Electric Advances in Product Environmental Data Transparency

    April 28, 2025 Schneider Electric has launched its Environmental Data Program. This initiative, which builds on the legacy Green Premium label, provides customers with unique access to information on the environmental impact of its products, enabling them to make better informed, data-based decisions and meet evolving regulatory requirements with confidence. Schneider Electric has frequently been recognized… Read More…

  • nVent Sustainability Report Highlights Progress and Focus on Electrification

    nVent Sustainability Report Highlights Progress and Focus on Electrification

    April 15, 2025 nVent Electric plc announced the release of its 2024 Sustainability Report. The new report highlights nVent’s achievements in each of its sustainability focus areas: People, Products, Planet and Governance. The report also highlights how nVent solutions support electrification, digitalization and sustainability efforts around the world. “nVent is becoming a more focused electrical… Read More…

  • Ontario Introduces Legistlation to Unlock Trade and Labour Mobility Within Canada

    Ontario Introduces Legistlation to Unlock Trade and Labour Mobility Within Canada

    April 18, 2025 As a next step in its plan to protect Ontario by unleashing the province’s economy, the Ontario government is introducing the Protect Ontario through Free Trade within Canada Act to unlock free trade and labour mobility within Canada. This legislation will, if passed, create new opportunities for job creation and investment attraction, supporting economic… Read More…

  • Ontario, P.E.I. Join Nova Scotia With Legislation to Remove Internal Trade Barriers

    Ontario, P.E.I. Join Nova Scotia With Legislation to Remove Internal Trade Barriers

    April 18, 2025 Prince Edward Island and Ontario have joined the Nova Scotia by introducing reciprocal legislation that will help foster an environment of mutual recognition of goods, services and labour mobility between these provinces. “Leaders across the country are expressing interest in removing trade barriers, and I’m very pleased that P.E.I. and Ontario have… Read More…