The Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook** but will hopefully provide some help in navigating, while reading the code.

The 24th Edition of the CE-C, Part I, (C22.1-18)* is now available from CSA Group. This discussion of Section 78 — Marine Wharves, Docking Facilities, Fixed and Floating Piers, and Boathouses is based on the new edition.

Rule 84-000 notes that this is a supplementary or amendatory section of the code and applies only to the installation of power production sources interconnected with a supply authority system. Appendix B and the CEC Handbook have additional information and descriptions of these installations.

Rule 84-002 states that arrangements for interconnection must be in accordance with the requirements of the supply authority.

Rule 84-004 requires provision of protection against backfeed into a supply authority system fault on all interconnected electric power sources.

Rule 84-006 requires that electric power production sources be equipped with the means and equipment to establish and maintain a synchronous condition with the interconnected supply system and prevent any adverse effect.

Rule 84-008 requires that where there is a loss of voltage in one or more phases of the supply authority system, the interconnected electric power production source must be automatically disconnected and not be reconnected until normal voltage of the supply authority system is restored. An alternate procedure may be followed, if in accordance with the requirements of the supply authority. If approved by the supply authority, an inverter designed to also serve as a disconnection device that is suitable for interconnection with electric power production sources may be used.

Rule 84-010 requires that where energization of conductors and equipment is from both directions, overcurrent protection must be provided from each source of supply.

Rule 84-012 requires that the rating of overcurrent protection for a transformer that is energized from both directions is determined under Section 26, by considering first one side of the transformer and then the other side, as the primary.

Rule 84-014 requires that each interconnected electric power production source installation must have additional devices as necessary for system stability and equipment protection.

Rule 84-016 requires ground fault protection in accordance with Rule 14-102 to be provided.

Rule 84-018 requires that where an electric power production source loses voltage in one or more of its phases it must have provisions to automatically disconnect all phases from the interconnected system.

Rule 84-020 requires that all ungrounded conductors of any electric power production source of an interconnected system, be provided with a disconnecting means that simultaneously disconnects all circuits supplied by the electric power production source equipment.

Rule 84-022 requires that all ungrounded conductors of any electric power production source of an interconnected system, be provided with a disconnecting means that simultaneously disconnects all circuits supplied by the electric power production sources from the supply authority system. This provides the supply authority a single point of access to isolate one or more power production sources.

Rule 84-024 outlines the specifications that the disconnecting means must

• be capable of being energized from both sides
• plainly indicate whether it is in the open or closed position
• have contact operation verifiable by direct visible means if required by the supply authority (in accordance with 84-002, to provide added assurance to supply authority workers that the circuit is open before work is initiated)
• have provision for being locked in the open position
• conform to Sections 14, 28, and 36 if it includes an overcurrent device
• be capable of being opened at rated load
• be capable of being closed with safety to the operator with a fault on the system
• disconnect all ungrounded conductors of the circuit simultaneously
• bear a warning to the effect that inside parts can be energized when the disconnecting means is open
• be readily accessible, and
• where a main fusible disconnecting means is used, an isolating switch must be provided to allow the fuses to be dead during handling

Rule 84-026 requires that isolating means be provided to isolate equipment that is energized from both directions from all ungrounded conductors of each source of supply.

Rule 84-028 specifies that the grounding means at the service entrance may serve as the grounding means for the electric power production source in accordance with Sections 10 and 36. In the case of a dc power source connected through a solid-state inverter, the inverter must not be grounded unless the inverter ac power is separated from the supply authority system by means of an isolating transformer.

Rule 84-030 requires that a warning notice and a single-line, permanent, legible diagram of the interconnected system shall be installed in a conspicuous place at the supply authority disconnecting means of Rule 84-022 and at the supply authority meter location.

In the next instalment, we will be discussing Section 86 – Electrical Vehicle Charging Systems.

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting; billburr@gmail.com

* The source for this series of articles is the Canadian Electrical Code, Part I, published by CSA.
**Note the CEC Handbook is also published by CSA.

 

Related Articles


Latest Articles

  • ABB Wins New Product Award at MCEE Show

    ABB Wins New Product Award at MCEE Show

    April 28, 2025 ReliaHome™ Smart Panel won Best New Product Award in the Software, Controls and Related Components category. Iberville® Gangable boxes with low-voltage cables support bracket was recognized as a finalist in the Commercial, Institutional and Industrial Electrical Products category. ABB was honored with a Best New Product Award in the Software, Controls and… Read More…

  • Weidmuller Celebrating a Legacy: 175 Years Globally, 50 Years in Canada

    Weidmuller Celebrating a Legacy: 175 Years Globally, 50 Years in Canada

    April 28, 2025 The year 2025 is truly special for Weidmüller. The company proudly celebrates not just 50 remarkable years in Canada but also its 175th anniversary globally—an extraordinary achievement few companies can claim. This legacy is a testament to the company’s relentless pursuit of innovation and commitment to refining its offerings. But the journey… Read More…

  • Canada Stands Tall at Hannover Messe 2025

    Canada Stands Tall at Hannover Messe 2025

    April 28, 2025 By Owen Hurst At Hannover Messe earlier this month Canada had a strong presence as the host country with a wide variety of companies and programs focusing on the development of advance technology. The presence was accentuated by numerous halls hosting Canada pavilions. Partner Country Canada presented itself impressively at HANNOVER MESSE…. Read More…

  • BC Prompt Payment Legislation Progressing

    BC Prompt Payment Legislation Progressing

    April 28, 2025 Consistent with its mandate of growing the economy, the government wants to ensure that businesses are paid promptly for work performed on (or material provided to) construction projects. British Columbia’s Ministry of Attorney General staff have been tracking the issue of payment delay in the construction industry, including legislative responses in other… Read More…


Changing Scene

  • Schneider Electric Advances in Product Environmental Data Transparency

    Schneider Electric Advances in Product Environmental Data Transparency

    April 28, 2025 Schneider Electric has launched its Environmental Data Program. This initiative, which builds on the legacy Green Premium label, provides customers with unique access to information on the environmental impact of its products, enabling them to make better informed, data-based decisions and meet evolving regulatory requirements with confidence. Schneider Electric has frequently been recognized… Read More…

  • nVent Sustainability Report Highlights Progress and Focus on Electrification

    nVent Sustainability Report Highlights Progress and Focus on Electrification

    April 15, 2025 nVent Electric plc announced the release of its 2024 Sustainability Report. The new report highlights nVent’s achievements in each of its sustainability focus areas: People, Products, Planet and Governance. The report also highlights how nVent solutions support electrification, digitalization and sustainability efforts around the world. “nVent is becoming a more focused electrical… Read More…

  • Ontario Introduces Legistlation to Unlock Trade and Labour Mobility Within Canada

    Ontario Introduces Legistlation to Unlock Trade and Labour Mobility Within Canada

    April 18, 2025 As a next step in its plan to protect Ontario by unleashing the province’s economy, the Ontario government is introducing the Protect Ontario through Free Trade within Canada Act to unlock free trade and labour mobility within Canada. This legislation will, if passed, create new opportunities for job creation and investment attraction, supporting economic… Read More…

  • Ontario, P.E.I. Join Nova Scotia With Legislation to Remove Internal Trade Barriers

    Ontario, P.E.I. Join Nova Scotia With Legislation to Remove Internal Trade Barriers

    April 18, 2025 Prince Edward Island and Ontario have joined the Nova Scotia by introducing reciprocal legislation that will help foster an environment of mutual recognition of goods, services and labour mobility between these provinces. “Leaders across the country are expressing interest in removing trade barriers, and I’m very pleased that P.E.I. and Ontario have… Read More…