BC Hydro Energy Storage Incentive

August 18, 2025

Energy storage systems (ESS) provide reliability and resiliency for businesses and the grid alike while helping to reduce GHG emissions as an alternative to diesel backup generation. Storing energy can help manage peak demand charges, reduce peak loads on the grid and provide electricity during outages. 

The offer

BC Hydro are offering incentives to their business customers to support the acquisition, installation, and operation of ESS. Once installed, BC Hydro will have the ability to dispatch the ESS automatically in response to changing conditions on the grid. These dispatch signals trigger the battery to discharge, powering the facility it’s attached to and reducing demand on the grid. The battery will then recharge later in the day or at night.

How it works

The incentive provided is based on the amount of battery capacity the customer nominates to be available for demand flexibility or demand response events.  The incentive is calculated as the lesser of:

  • $10,000 X kW nominated
  • $10,000 X kWh/4 nominated
  • 80% of eligible project costs.

Eligibility

To be eligible for BC Hydro’s energy storage incentive (ESI), customers must meet the following criteria:

  • Be on a general service or irrigation rate under the Electric Tariff.
  • Plan to install a new battery. Batteries that have already been purchased
    or installed are not eligible.
  • Have an operating smart meter
  • Mustย complete applicable net metering or generator interconnections process. Systemsย must be non-exporting to the grid.
  • Must install and energize an ESS that meets all the system requirementsย of the program within 24 months of completing a distribution generator interconnections facility study or the net metering application process.
  • Agree to a 10-year contract to provide demand flexibility services via the ESS to BC Hydro.
  • Provide reliable demand flexibility year-round within the following
    parameters:
    • Maximum duration (hours /event): 4
    • Maximum daily frequency: 2
    • Minimum hours between events: 5
  • Must reliably respond to flexibility dispatch events. Performance is considered reliable when the ESS is charged to provide at least 85% of its nominated capacity for 85% of all demand response events, as measured at the start of the event. Reliability is assessed annually.
  • Must connect to BC Hydro software platform via IEEE 2030.5, SCADA, established API or other method approved by BC Hydro to receive event signals.

How to apply

See BC Hydro’s energy storage system (ESS) application processย [PDF, 96 KB]ย for details.ย You’ll also need ourย incentive application workbookย [XLS, 167 KB]ย to begin the process.ย 

Resources

For more information, see our Customer manual โ€“ Energy storage systems [PDF, 635 KB].

Note

Tesla products are not eligible

The Government of B.C. and BC Hydro are taking action to preference Canadian goods in our rebate programs going forward and to exclude, where practicable, U.S. produced goods. As of March 12, 2025, Tesla products are not eligible for Energy Storage Incentive offer. If you’re already reviewing Tesla products as a solution for your energy storage system needs, please note that the requirements and technical specifications can readily be transferred to another manufacturer/ vendor.

Go HERE for more information

Related Articles


Latest Articles


Changing Scene

  • Skills Ontario Celebrates Team Ontario Winning 38 Medals atย Skills Canada National Competition 2026

    Skills Ontario Celebrates Team Ontario Winning 38 Medals atย Skills Canada National Competition 2026

    June 8, 2026 After two days of showcasing their skills, youth on Team Ontario are returning home from Skills Canada National Competition 2026 with 308 medals.  At a Closing Ceremony on May 30th following the Skills Canada National Competition in Toronto, which took place from May 28th to May 29th, Team Ontario took home 38 Read More…

  • Spartan Controls Opens New facility in Kitimat to Support Growing Industrial and Energy Sector Demand

    Spartan Controls Opens New facility in Kitimat to Support Growing Industrial and Energy Sector Demand

    June 8, 2026 Spartan Controls, a leading provider of industrial automation solutions, is proud to announce the opening of a new facility in Kitimat. The service centre expands Spartan’s presence in Northwestern British Columbia to support the region’s rapidly growing industrial and energy sector. The new facility strengthens Spartan’s ability to deliver local support to Read More…

  • Laurentide Controls Acquires C. Latendresse Inc., Reinforcing its Integrated Industrial Electrical Offering in Eastern Canada

    Laurentide Controls Acquires C. Latendresse Inc., Reinforcing its Integrated Industrial Electrical Offering in Eastern Canada

    June 8, 2026 Laurentide Controls is proud to announce the acquisition of C. Latendresse Inc., an industrial and commercial electrical contractor founded in 1976, based in Charlemagne, QC. The transaction closed on May 25, 2026. A Targeted Strategic Reinforcement This acquisition is the result of a strategic convergence: Laurentide brings to C. Latendresse Inc. the Read More…

  • ESA Highlights Proactive Maintenance as Part of Building Safety Month

    ESA Highlights Proactive Maintenance as Part of Building Safety Month

    June 8, 2026 Much of Ontarioโ€™s housing stock is aging, and the risks are becoming harder to ignore. More than ๐Ÿด๐Ÿฌ% ๐—ผ๐—ณ ๐—ฝ๐˜‚๐—ฟ๐—ฝ๐—ผ๐˜€๐—ฒ-๐—ฏ๐˜‚๐—ถ๐—น๐˜ ๐—ฟ๐—ฒ๐—ป๐˜๐—ฎ๐—น ๐—ต๐—ผ๐˜‚๐˜€๐—ถ๐—ป๐—ด ๐—ถ๐—ป ๐˜๐—ต๐—ฒ ๐—ฝ๐—ฟ๐—ผ๐˜ƒ๐—ถ๐—ป๐—ฐ๐—ฒ ๐—ถ๐˜€ ๐—ผ๐˜ƒ๐—ฒ๐—ฟ ๐Ÿฐ๐Ÿฑ ๐˜†๐—ฒ๐—ฎ๐—ฟ๐˜€ ๐—ผ๐—น๐—ฑ. Between 2019 and 2023, there was an ๐—ฎ๐˜ƒ๐—ฒ๐—ฟ๐—ฎ๐—ด๐—ฒ ๐—ผ๐—ณ ๐Ÿฏ๐Ÿฎ ๐—ฒ๐—น๐—ฒ๐—ฐ๐˜๐—ฟ๐—ถ๐—ฐ๐—ฎ๐—น ๐—ณ๐—ถ๐—ฟ๐—ฒ๐˜€ ๐—ฒ๐—ฎ๐—ฐ๐—ต ๐˜†๐—ฒ๐—ฎ๐—ฟ in aging multi-unit residential buildings, with the potential Read More…