GE-Led Consortium Wins Manitoba Hydro Contract to Replace Substation in Winnipeg

Winnipeg Substation

Aconsortium led by GE’s Digital Energy business has won a milestone engineering, procurement and construction contract from Manitoba Hydro to build a new, 66 kilovolt gas-insulated substation that will help meet Winnipeg’s growing energy needs. The contract, valued at $31.4 million, is the first substation order for GE’s Digital Energy business in Canada.

The new Adelaide Street substation will be built in downtown Winnipeg, replacing the utility’s aging substation on King Street in the Exchange District. The project is part of Manitoba Hydro’s plan to upgrade or replace Winnipeg’s aging substations and other equipment with newer, more efficient power delivery systems.

GE submitted the winning EPC bid under an open consortium approach, with GE as the consortium leader and Edmonton, Alberta-based HB Construction Company, Ltd. as the consortium’s engineering and construction partner.Teshmont, a Winnipeg-based provider of high-voltage DC power transmission services, also plays a key role as GE’s key sub-contractor responsible for protection and control engineering and associated testing.

“Electrical substations are a critical part of our distribution system, delivering electricity to homes and businesses throughout the city and driving more sustainable economic growth for our province,” says Manitoba Hydro President and CEO Scott Thomson. “Even as we expand our networks, they are continuously being repaired and upgraded to meet the growing energy needs of our customers.”

Brent Reed, vice president, customer service & distribution for Manitoba Hydro noted that of the 97 stations in the city of Winnipeg, 37 are operating beyond their technical limitations and eight of them are more than 60 years old.
Winnipeg is not alone.A report by the Canadian Electricity Association quotes an International Energy Agency estimate that Canada will need to invest an estimated $350 billion in its electricity sector by 2030, representing a national investment of approximately $17.5 billion per year for 20 years.

The GE-led consortium’s scope of work on the new Adelaide substation includes the design, supply, installation, testing and commissioning support of three 30-megavolt ampere transformers; 66-kilovolt gas-insulated switchgear; and 12-kilovolt metal-clad switchgear. The equipment will be housed in a new building with a perimeter wall surrounding the station.

 

Related Articles


Latest Articles

  • Code Question on Section 24 – Patient Care Areas

    Code Question on Section 24 – Patient Care Areas

    July 14, 2025 The rules for the installation of panelboards, circuits, and bonding in Patient Care Area depends on whether the area is designated as either, Basic Care, Intermediate Care or Critical Care. How are these areas defined? Read more on Section 24 — Health care areas Read More…

  • Ontario’s Institutional Component Drives Non-Residential Construction Intentions in May 2025

    Ontario’s Institutional Component Drives Non-Residential Construction Intentions in May 2025

    July 14, 2025 In May, the total value of building permits issued in Canada rose by $1.4 billion (+12.0%) to reach $13.1 billion. The increase in construction intentions was driven by Ontario’s institutional component (+$1.3 billion). On a constant dollar basis (2023=100), the total value of building permits issued in May increased 11.8% from the previous month and was… Read More…

  • Plan Group Partners in Construction of UHN Surgical Tower at Toronto Western Hospital

    Plan Group Partners in Construction of UHN Surgical Tower at Toronto Western Hospital

    July 14, 2025 Plan Group is proud to be a partner in the construction of the UHN Surgical Tower at Toronto Western Hospital. Plan Group will provide work on the project in: Mechanical: Plumbing, HVAC, Controls, Medical GasElectrical: Lighting & Controls, Power Distribution, Emergency Generators, UPSTechnology: Structured Cabling, AV Systems including Digital Signage and IPTV UHN’s 15-storey Surgical… Read More…

  • How Canada Can Equip Workers for a Low-Carbon Future

    How Canada Can Equip Workers for a Low-Carbon Future

    July 14, 2025 The Canadian economy is shifting towards low-carbon industries, and the workforce is shifting with it. New roles are emerging, traditional ones are evolving and the demand for skilled workers is growing fast — particularly in light of the ambitious nation-building agenda the federal government has set out. In the federal Speech from… Read More…


Changing Scene

  • OEL Apprentice Success Project Available Until March 2026

    OEL Apprentice Success Project Available Until March 2026

    July 14, 2025 With renewed funding by Ontario’s Skills Development Fund, the OEL Apprentice Success Project is now available for another year until March 2026. The project is part of OEL’s Employer Engagement Program (EEP) consisting of wage, training, and equipment subsidies for apprentices. These funding opportunities are available to OEL Members and non-Members. For… Read More…

  • EB Horsman Unveils New Mural at Campbell River Branch

    EB Horsman Unveils New Mural at Campbell River Branch

    July 14, 2025 EB Horsman & Son are thrilled to unveil a new mural at their Campbell River branch, painted by the talented Kwakwaka’wakw artist, Adam Lewis. “This stunning piece celebrates Indigenous heritage and our community spirit,” said EB Horsman on LinkedIn. “As we mark 125 years of serving Western Canada and 55 years in… Read More…

  • Glenco Electric Celebrate New Red Seal Team Members

    Glenco Electric Celebrate New Red Seal Team Members

    July 14, 2025 “The Red Seal Journeyman designation is the highest recognition in the trades, and we’re proud to have seen so many of our team members earn it under our watch,” said Glenco Electric on LinkedIn. “At Glenco, we’re big on mentorship and promoting from within. When you combine that with driven, hard-working professionals,… Read More…

  • Canada and Ontario Investing to Improve Energy Efficiency in Province’s Agri-Food Industry

    Canada and Ontario Investing to Improve Energy Efficiency in Province’s Agri-Food Industry

    July 14, 2025 The governments of Canada and Ontario are investing up to $3 million and launching the third intake of the Agricultural Stewardship Initiative (ASI) to help farmers implement projects to improve the energy efficiency of their farming operations. To support the province’s plan to protect Ontario, this funding will help local agriculture, agri-food… Read More…