Power Utility in Sarnia-Lambton Fined in Electrocution Death of Worker

Bluewater Power

 

Bluewater Power Distribution Corporation, the utility providing electricity distribution and related services in the Sarnia-Lambton area, has been fined $120,000 in the 2012 death of a worker who was performing repair work following the aftermath of Hurricane Sandy.

The worker was one of two who had been assigned post-storm repair work on Passingham Drive in Sarnia, where trees had downed power lines. On October 31, 2012, the two workers cleared tree limbs and began to repair the electrical lines. One worker was working from an aerial bucket while the other was working from the ground, and they began working on the downed primary neutral line.

Up until that point, the worker in the aerial bucket had been working with leather gauntlet gloves and was preparing to make the final connection by fastening the neutral end to a connector that completes the circuit path. That worker called down to the other to bring rubber gloves from the cab of their truck. While the worker was heading to the truck cab to retrieve the rubber gloves, the truck shook and the boom of the bucket dropped.

The supervisor was immediately called and both ambulance and the fire department were summoned. The worker in the bucket was taken to hospital and could not be revived. Cause of death was determined to be electrocution.
An investigation revealed that no job plan or tailboard was in place prior to the commencement of work. A job plan is typically prepared by a power line technician when the technician arrives at the job site in order to assess the work that needs to be carried out. A tailboard conference – or job site planning meeting – is used to review the job plan, identify hazards and determine how to best mitigate these hazards before work begins.

Job planning and documentation of a tailboard is a requirement under the Electrical Utility Safety (EUSR) Book, Rule 107. These rules have been established as a minimum standard for safety precautions to be followed by employers and workplaces that do not fall under the jurisdiction of Ontario Regulation 851/91 (the Industrial Establishments Regulation) or Ontario Regulation 213/91 (the Construction Projects Regulation).

In this instance, a properlyestablished job plan and tailboard conference would have addressed some of the key hazards and safety failings present at the site. In a statement, the worker who was on site indicated that a job plan was normally completed prior to the project; it was not completed in this instance because they were anxious to bring the power back to the community.

Although both workers had over 20 years of experience each and had been trained on the importance of wearing rubber gloves at all times upon stepping into the aerial bucket on a boom truck, the job plan and tailboard conference would have reiterated the need for using rubber gloves at all times when working on any pole or structure carrying energized conductors. The worker had been wearing leather gloves, which have a reduced electrical resistance compared to rubber gloves. Following the incident, the worker’s gloves were found to contain some dampness, which would have further weakened their resistance to electricity.

The workers should have taken the measure of treating the neutral conductor as energized (“live”) as indicated in Rule 116 of the EUSR Book.

Bluewater Power Distribution Corporation pleaded guilty to failing as an employer to ensure that workers performed a documented job plan before performing work on or in proximity to energized electrical equipment in accordance with Rule 107 of the EUSR.

 

Related Articles


Latest Articles


Changing Scene

  • ABB Among TIME’s World’s Most Sustainable Companies

    ABB Among TIME’s World’s Most Sustainable Companies

    June 30, 2025 ABB has been ranked 14th in TIME’s “World’s Most Sustainable Companies 2025” and third in Switzerland across all industries. TIME and Statista assessed over 5,000 of the world’s largest and most influential companies, considering factors such as revenue, market capitalization, and public prominence. The top 500 companies from 35 countries and 21 industries were… Read More…

  • New Partnership to Deliver 1,000 Affordable Housing Units Across Quebec

    New Partnership to Deliver 1,000 Affordable Housing Units Across Quebec

    June 25, 2025 The governments of Canada and Quebec, together with Desjardins, have announced the construction of 1,000 new affordable housing units over the next three years. These housing units will be created as part of the Desjardins Affordable Housing Initiative, a partnership launched in 2022 that will now enable the delivery of over 3,000 affordable housing units… Read More…

  • CIB Closes $50M Loan with Dream Industrial REIT to Fund Large-Scale Commercial Building Upgrades

    CIB Closes $50M Loan with Dream Industrial REIT to Fund Large-Scale Commercial Building Upgrades

    June 30, 2025 The Canada Infrastructure Bank (CIB) and Dream Industrial Real Estate Investment Trust have finalized a $50 million loan to fund commercial property retrofits related to energy efficiency savings and emissions reductions at 34 warehouses in Alberta, Ontario and Quebec. With buildings currently accounting for 18% of Canada’s total emissions, investments from the… Read More…

  • Province, BC Hydro Launch Pilot Program to Cut Energy Costs, Support Housing Density

    Province, BC Hydro Launch Pilot Program to Cut Energy Costs, Support Housing Density

    June 25, 2025 In a Canadian first, the Province and BC Hydro have launched a pioneering pilot project in Vancouver that has the potential to set new standards for supporting growing housing priorities and densification in Canada. Designed to support the transition from single-family homes to multi-unit residences, the initiative is exploring how full electrification –… Read More…