Pattern Development and Henvey Inlet First Nation Start Construction of Largest First Nation Wind Project in Canada

Pattern Development

January 12, 2018

Pattern Energy Group LP announced the completion of a C$1 billion financing for the 300 megawatt (MW) Henvey Inlet Wind project located on Henvey Inlet First Nation Reserve No. 2 on the northeast shore of the Georgian Bay in Ontario. Pattern Development and Nigig Power Corporation, a wholly-owned subsidiary of Henvey Inlet First Nation, are joint venture partners in the project.

“This landmark project is a first on many fronts: largest wind project in Ontario, largest on-reserve wind installation in Canada, highest hub heights in North America, and the first to develop a First Nation Environmental Stewardship Regime under the First Nations Lands Management Act,” said Mike Garland, CEO of Pattern Development. “We are proud to be partners with Henvey Inlet First Nation. Together we’re excited to kick off construction on this historic project that will harness the strong and steady winds blowing across the Georgian Bay to create hundreds of local jobs and provide a significant new source of revenue for Henvey Inlet First Nation.”

“This will be the first wind power project on First Nation land, representing an economic turning point in which we are creating a prosperous future,” said Chief Wayne McQuabbie of Henvey Inlet First Nation. “This project’s watershed permitting and real estate regime sets an example for responsible economic development that protects and preserves First Nation land while also generating revenue for future generations. The project also benefits Magnetawan and Shawanaga First Nations with income and employment opportunities.”

“We aren’t just building a wind farm, we’re building an economy,” said Ken Noble, President and CEO, Nigig Power Corporation. “The net proceeds over the next two decades of operations will provide the financial resources to transform the local economy, expand all community services, relieve poverty, and create employment.” 

Henvey Inlet Wind will utilize 87 Vestas 3.45 MW turbines with a 136-meter rotor diameter and 132-meter hub height. The project has a 20-year Power Purchase Agreement with the Independent Electricity System Operator (IESO) for 100% of its production.

The project will create up to 500 jobs during construction. Once operational the project will employ approximately 15 permanent full-time workers and also create the need for more than 100 ongoing indirect jobs.

Once operational in the first half of 2019, Henvey Inlet Wind will generate clean power for approximately 100,000 Ontario homes each year. It is expected to generate lease royalties of more than C$8 million annually for the Henvey Inlet First Nation, in addition to significant income from project distributions.  

Henvey Inlet Wind is being jointly developed and will continue to be jointly owned and operated by Pattern Development and Henvey Inlet First Nation. Pattern Development owns a 50% interest in the project, and Nigig Power Corporation owns the other 50% of the project.

Related Articles


Latest Articles

  • Lever Connectors and Twist-Ons: How to Decide Which is Right for the Job

    Lever Connectors and Twist-Ons: How to Decide Which is Right for the Job

    There are many different types of wire connectors, and sometimes it can be hard for electricians to determine which one is best to use. Read More…

  • Winnipeg Information Bulletin: Low-Risk Voice, Data, Video & Security System Installations

    Winnipeg Information Bulletin: Low-Risk Voice, Data, Video & Security System Installations

    September 17, 2026 Certain types of installations may qualify for a low-risk voice, data, video (VDV) and security system electrical permit. For information related to regular VDV/security system installations, see winnipeg.ca/vdvsystems. Applications must be submitted through Permits Online. Electrical permits and inspections are needed for certain installations of security and similar alarm systems. This makes… Read More…

  • What Type of Outdoor Light Do I Need for My Application?

    What Type of Outdoor Light Do I Need for My Application?

    September 17, 2026 By Stanpro The right outdoor light starts with the space you need to illuminate and how that space is used. For commercial projects, parking lots and large exterior areas point toward area lights; entrances and building perimeters toward wall-mounted or security lighting; signs, facades and targeted areas toward flood lights; pathways toward… Read More…

  • Alberta Employers and Tradespeople Share their Perspectives

    Alberta Employers and Tradespeople Share their Perspectives

    September 16, 2026 In Alberta’s skilled trades labour market employers and tradespeople are facing growing pressure from tariffs, rising costs, hiring challenges and labour mobility barriers. CAF-FCA’s new report, Hiring, Mobility and Needed Supports: Alberta Employers and Tradespeople Share Their Perspectives, takes a closer look at what’s happening on the ground. Based on surveys of… Read More…


Changing Scene

  • Government of Canada Introduces Legislation to Transform how Canada Builds

    Government of Canada Introduces Legislation to Transform how Canada Builds

    October 2, 2026 The world is changing rapidly. In response, Canada is focused on what we can control: building a stronger, more independent, and more sustainable economy. We are leveraging our strengths and moving with speed to open new markets, strengthen supply chains, accelerate projects, and unlock our natural resources. As we build, we are… Read More…

  • Ontario Awards Construction Contract for New Little Current Swing Bridge

    Ontario Awards Construction Contract for New Little Current Swing Bridge

    October 2, 2026 The Ontario government has named a construction manager for the Little Current Swing Bridge replacement project. The new bridge will replace the existing bridge on Highway 6 connecting Manitoulin Island to the mainland, providing reliable, year-round access to the provincial highway network and making it easier for workers and families to connect… Read More…

  • Construction Starting on new Pitt Meadows Secondary School in BC

    Construction Starting on new Pitt Meadows Secondary School in BC

    October 2, 2026 Construction is beginning on the new Pitt Meadows Secondary school, which will provide students with a safer and more modern environment to learn. “Pitt Meadows is a vibrant community with a bright future and I’m proud that the local high school will soon better reflect the community it serves,” said Lisa Beare,… Read More…

  • Major Construction Underway at Woodbine GO Station

    Major Construction Underway at Woodbine GO Station

    October 2, 2026 Major construction is underway at Woodbine GO Station, marking another significant milestone in the Ontario government’s plan to provide two-way, all-day service across core segments of the GO Transit network. Crews are now building station platforms that will connect thousands of daily riders to the Kitchener GO Line, Union-Pearson (UP) Express and… Read More…