Fort McMurray West 500-kV Transmission Project Energized 3 Months Ahead of Schedule

Fort

Apr 7, 2019
The 500+ km transmission line from Edmonton to Fort McMurray includes two substations and involved 20 months of construction, and 4.5 years from project start to energization.

When the line was commissioned, it was considered the largest engineering, procurement and construction electric transmission project ever awarded in North America. It increases the capacity of the existing system to meet a growing demand for power in this area, and bolsters the overall reliability of the Alberta transmission network.

The line was constructed by Alberta Powerline, a Valard/ATCO partnership. It has already earned several awards. In 2017, the project received the Transmission Deal of the Year Award in 2017. In April 2018, Valard won a Top Employer of Indigenous Apprentices Award, primarily for a training program built specifically for WFMAC.

“I got to take my hat off to the integrated team under Valard, they kept their eye on the prize, some of them of 6-years,” said Valard President, Adam Budzinski, noting that there were some on the project that saw it through from beginning to the end.

The entire project was done in house by Valard, along with their partners in the Valard Group, Phasor Engineering, Domino High Voltage Supply, Northstar Sharp’s, as well as Dashiell Corp.

Budzinski said the dynamic of the project, being completed entirely in-house, was a primary factor in their ability to finish ahead of schedule. There was no conflict throughout the various points of the project’s massive scope. Everyone was pulling in the same direction. Rather than pointing fingers when issues arose, they simply worked together to find the best possible solution, and in a timely manner. Often with projects of this magnitude, relatively minor issues can escalate to point where progress is held up, Budzinski explained, “This execution model kind of avoids that,” he said, “being done under one company.”

And that also factored into Valard being awarded the tender, becuase it was completed under one company they were able to give a detailed cost breakdown, and were able to quantify a lot of their risk, he explained.

Obviously, as it was a major project for Valard there were certainly challenges, although Budzinsky said they were confident they could complete it successfully. They had experience completing all the various aspects of the project from past jobs, just never all in one project as the Fort McMurray West Transmission Project required. The Muskrat Falls Transmission Line project Valard wrapped in 2016 was a comparable experience, although Budzinski said of the Fort McMurray project, “from a full construction perspective it was different than anything we’ve done.”

“It was a world-class project,” he noted, “and it ended up being built by the home team, for a competitve price.”

“We’re proud of the fact it was built by a made in Canada solution and delivered 3-months ahead of schedule. People shouldn’t doubt we have world-class designers and engineers here in Canada.” 

 

Related Articles


Latest Articles

  • Considerations for EV Charging Installation and Site Preparation

    Considerations for EV Charging Installation and Site Preparation

    December 15, 2025 By Blake Marchand As part of our recent discussion with LEDVANCE EVSE Product Manager, Erich Bockley, he emphasized the importance of site preparation Site preparation can be the most complicated part of the project, Bockley emphasized, a lot needs to be considered before the installation work begins. Many public charging applications will… Read More…

  • Ontario’s Multi-Family Component Leads Residential Sector Increases in October Building Permits

    Ontario’s Multi-Family Component Leads Residential Sector Increases in October Building Permits

    December 15, 2025 In October, the total value of building permits issued in Canada rose $1.8 billion (+14.9%) to $13.8 billion. The increase in construction intentions was led by the residential sector (+$1.1 billion). An increase was also observed in the non-residential sector (+$702.8 million). On a constant dollar basis (2023=100), the total value of building permits issued in… Read More…

  • Residential Investment in Building Construction Declines in September

    Residential Investment in Building Construction Declines in September

    December 15, 2025 Overall, investment in building construction decreased 1.1% to $22.4 billion in September. Investment in the residential sector declined 1.7%, while that in the non-residential sector was virtually unchanged. Year over year, investment in building construction grew 6.0% in September. On a constant dollar basis (2023=100), the total value of investment in building construction in September decreased 1.4%… Read More…

  • Nova Scotia Invests in Generational Affordable Housing for Shannon Park

    Nova Scotia Invests in Generational Affordable Housing for Shannon Park

    December 15, 2025 Work to build more than 1,400 new homes across Nova Scotia – about two-thirds at Shannon Park in Dartmouth – will soon begin with funding from the Province and the federal government. Housing Minister John White and federal Minister of Housing and Infrastructure Gregor Robertson announced $300 million to build 1,430 new… Read More…


Changing Scene

  • CSA Group Receives Greater Toronto’s Top Employers Award for 10th Consecutive Year

    CSA Group Receives Greater Toronto’s Top Employers Award for 10th Consecutive Year

    December 15, 2025 For the tenth consecutive year, CSA Group has been awarded as one of Greater Toronto’s Top Employers for 2026 by Mediacorp Canada Inc. This milestone reflects CSA Group’s continued commitment to fostering a workplace culture that supports employee wellbeing, professional growth, and community engagement. CSA Group’s global headquarters, located in Toronto, offers… Read More…

  • Hydro Ottawa to Use AI-Enhanced Predictive Analytics to Improve Energy Efficiency

    Hydro Ottawa to Use AI-Enhanced Predictive Analytics to Improve Energy Efficiency

    December 15, 2025 With $6 million in federal funding, Hydro Ottawa is introducing the Ottawa Distributed Energy Resource Accelerator (ODERA) program. Through this program, Hydro Ottawa will use AI-enhanced predictive analytics to accurately forecast peak demand, which will then inform the real-time balancing of supply and demand. This will be achieved by using a technology… Read More…

  • Stanpro’s Katy’s Donation Day Breaks Record, Giving Back to Communities Across Canada

    Stanpro’s Katy’s Donation Day Breaks Record, Giving Back to Communities Across Canada

    December 15, 2025 Stanpro is proud to announce the results of its annual Katy’s Donation Day, held on December 3, 2025. This year, the initiative resulted in a record donation of over $100,000, making this the highest contribution in the history of this program. The funds raised will be distributed to over 80 charitable organizations… Read More…

  • EB Horsman Introduce Cory Carter as New Victoria Branch Manager

    EB Horsman Introduce Cory Carter as New Victoria Branch Manager

    December 15, 2025 EB Horsman is pleased to announce the appointment of Cory Carter as Branch Manager of our Victoria location, effective November 10, 2025. With over two decades of experience in the electrical, lighting, and retail industries, Cory brings a proven track record of leadership, sales growth, and customer relationship management. Throughout his career,… Read More…