Fort McMurray West 500-kV Transmission Project Energized 3 Months Ahead of Schedule

Fort

Apr 7, 2019
The 500+ km transmission line from Edmonton to Fort McMurray includes two substations and involved 20 months of construction, and 4.5 years from project start to energization.

When the line was commissioned, it was considered the largest engineering, procurement and construction electric transmission project ever awarded in North America. It increases the capacity of the existing system to meet a growing demand for power in this area, and bolsters the overall reliability of the Alberta transmission network.

The line was constructed by Alberta Powerline, a Valard/ATCO partnership. It has already earned several awards. In 2017, the project received the Transmission Deal of the Year Award in 2017. In April 2018, Valard won a Top Employer of Indigenous Apprentices Award, primarily for a training program built specifically for WFMAC.

“I got to take my hat off to the integrated team under Valard, they kept their eye on the prize, some of them of 6-years,” said Valard President, Adam Budzinski, noting that there were some on the project that saw it through from beginning to the end.

The entire project was done in house by Valard, along with their partners in the Valard Group, Phasor Engineering, Domino High Voltage Supply, Northstar Sharp’s, as well as Dashiell Corp.

Budzinski said the dynamic of the project, being completed entirely in-house, was a primary factor in their ability to finish ahead of schedule. There was no conflict throughout the various points of the project’s massive scope. Everyone was pulling in the same direction. Rather than pointing fingers when issues arose, they simply worked together to find the best possible solution, and in a timely manner. Often with projects of this magnitude, relatively minor issues can escalate to point where progress is held up, Budzinski explained, “This execution model kind of avoids that,” he said, “being done under one company.”

And that also factored into Valard being awarded the tender, becuase it was completed under one company they were able to give a detailed cost breakdown, and were able to quantify a lot of their risk, he explained.

Obviously, as it was a major project for Valard there were certainly challenges, although Budzinsky said they were confident they could complete it successfully. They had experience completing all the various aspects of the project from past jobs, just never all in one project as the Fort McMurray West Transmission Project required. The Muskrat Falls Transmission Line project Valard wrapped in 2016 was a comparable experience, although Budzinski said of the Fort McMurray project, “from a full construction perspective it was different than anything we’ve done.”

“It was a world-class project,” he noted, “and it ended up being built by the home team, for a competitve price.”

“We’re proud of the fact it was built by a made in Canada solution and delivered 3-months ahead of schedule. People shouldn’t doubt we have world-class designers and engineers here in Canada.” 

 

Related Articles


Latest Articles

  • Littelfuse: Solid-State Industrial Relays Quality Test Report

    Littelfuse: Solid-State Industrial Relays Quality Test Report

    April 21, 2025 Littelfuse Provides Insights Into Their Solid-State Industrial Relays Introduction Solid-State Relays (SSRs) are a critical component in modern electrical & electronic systems, providing reliable switching capabilities for various applications from industrial automation to consumer electronics. When it comes to choosing the right solid-state relay for your application, it’s important to know the… Read More…

  • PataBid vs. Accubid Classic: How Electrical Estimating Software is Evolving

    PataBid vs. Accubid Classic: How Electrical Estimating Software is Evolving

    April 21, 2025 By Melvin Newman, Patabid CEO The landscape of construction technology — especially in electrical estimating software—is evolving at a rapid pace. With the rise of cloud-based platforms, AI-driven automation, and advanced data integration, contractors now have more options than ever when choosing the right digital estimating tool.    With the rise of… Read More…

  • ESA has Identified Increasing Safety Concern Surrounding Meter Base Installations

    ESA has Identified Increasing Safety Concern Surrounding Meter Base Installations

    April 18, 2025 ESA and EFC are raising awareness on an increasing safety concern the ESA has identified surrounding meter base installations. ESA identified an increase of installed meter bases where the neutral block is isolated from the enclosure. According to OESC Rule 10-210 a bonding conductor must be installed between the meter base and… Read More…

  • Non-residential Construction Investment Continues to Reach Record Highs in January 2025

    Non-residential Construction Investment Continues to Reach Record Highs in January 2025

    April 18, 2025 Overall, investment in building construction rose 1.8% (+$393.7 million) to $22.1 billion in January. The residential sector increased 2.3% to $15.4 billion, while the non-residential sector was up 0.8% to $6.7 billion. Year over year, investment in building construction grew 5.7% in January. On a constant dollar basis (2017=100), investment in building construction increased 1.5% from the previous month to $13.2 billion… Read More…


Changing Scene

  • nVent Sustainability Report Highlights Progress and Focus on Electrification

    nVent Sustainability Report Highlights Progress and Focus on Electrification

    April 15, 2025 nVent Electric plc announced the release of its 2024 Sustainability Report. The new report highlights nVent’s achievements in each of its sustainability focus areas: People, Products, Planet and Governance. The report also highlights how nVent solutions support electrification, digitalization and sustainability efforts around the world. “nVent is becoming a more focused electrical… Read More…

  • Ontario Introduces Legistlation to Unlock Trade and Labour Mobility Within Canada

    Ontario Introduces Legistlation to Unlock Trade and Labour Mobility Within Canada

    April 18, 2025 As a next step in its plan to protect Ontario by unleashing the province’s economy, the Ontario government is introducing the Protect Ontario through Free Trade within Canada Act to unlock free trade and labour mobility within Canada. This legislation will, if passed, create new opportunities for job creation and investment attraction, supporting economic… Read More…

  • Ontario, P.E.I. Join Nova Scotia With Legislation to Remove Internal Trade Barriers

    Ontario, P.E.I. Join Nova Scotia With Legislation to Remove Internal Trade Barriers

    April 18, 2025 Prince Edward Island and Ontario have joined the Nova Scotia by introducing reciprocal legislation that will help foster an environment of mutual recognition of goods, services and labour mobility between these provinces. “Leaders across the country are expressing interest in removing trade barriers, and I’m very pleased that P.E.I. and Ontario have… Read More…

  • New Brunswick Signs MOU with Ontario to Reduce Trade and Labour Mobility Barriers

    New Brunswick Signs MOU with Ontario to Reduce Trade and Labour Mobility Barriers

    April 18, 2025 The governments of New Brunswick and Ontario have signed a memorandum of understanding on free trade and labour mobility. “Ontario is New Brunswick’s second-biggest trading partner, and we are excited to be building on the positive momentum to reduce internal trade barriers across Canada,” said Premier Susan Holt. “Today’s signing of this… Read More…