Arc Flash Alphabet Soup: Understanding the Hazard Behind the Acronyms and Technical Terms (Part 3)

Arc Flash Risk Assessment

 

Jim Pollard

In Arc Flash Part 1, Jim Pollard reviews technical terminology and acronyms.
In Arc Flash Part 2, what causes an arc flash and how to prevent it.

The latest edition of CSA Z462, published in January, requires an arc flash risk assessment. This process is used to determine if an arc flash hazard exists (hazard identification), estimating the potential severity of injury or damage to health and estimating the likelihood of the occurrence. Risk is defined as being a combination of the severity and likelihood. The requirement to perform an arc flash risk assessment is a fundamental part of any comprehensive electrical safety program. Different types of risk assessment processes can be used, including the arc flash PPE category method within the CSA Z462-15 standard.

The arc flash PPE category method requires the use of tables from within the CSA Z462-15 standard. The following steps are completed when using this method:
• Determine if arc flash PPE is required through arc flash hazard identification (work task and equipment condition)
• Determine arc flash PPE categories for AC and DC systems (equipment types, voltage levels and specific electrical parameters)
• Outline arc flash PPE and other personal protective equipment requirements for each of the arc flash PPE categories (1-4)

The incident energy analysis method requires the use of engineering based calculations using the IEEE 1584 standard to estimate the incident energy exposure level. Arc flash PPE is then selected based on the incident energy so the arc rating matches or exceeds the incident energy calculated.

PPE is one of the most readily available solutions to protect workers; however, it should be used as a last line of defense.

Arc flash PPE consists of specially designed and appropriately tested products suitable for use by workers that need protection from the heat of an arc flash hazard. Employers are required to ensure workers within the arc flash boundary wear appropriate full body protection when it is determined that arc flash PPE is necessary based on an arc flash risk assessment.

There are hundreds, if not thousands, of different arc flash PPE products available on the market. Arc-rated PPE product segments include clothing, face shields, arc flash suits, outerwear and specialized equipment. All arc-rated PPE is available with the associated laboratory testing documentation — employers just need to ask for it. Unlikeshock protective PPE, arc flash PPE doesn’t require recertification. At the very least, all arc-rated PPE shall indicate compliance with ASTM F1506, which outlines performance specification for flame resistant and arc flash textiles specifically for electrical workers.

The product label is the best indication of its compliance, but only destructive testing can verify a manufacturer’s claims.

Training is also an important component and there are several formats available, including on-the-job, e-learning, instructor-led and blended learning (e-learning and instructor-led training). Both e-learning and instructor-led training formats can be considered classroom training, either in the traditional sense or virtual. Any worker exposed to electrical hazards in the workplace requires adequate training suitable for their role and appropriate for the risk of their exposure. This includes both electrical and non-electrical workers.

In Arc Flash Part 1, Jim Pollard reviews technical terminology and acronyms.
In Arc Flash Part 2, what causes an arc flash and how to prevent it.

 


Jim Pollard is a member of several technical committees, including CSA Z462. He is the owner of Unlimited PPE in Stoney Creek, Ont., and he can be reached at jim@unlimitedppe.com or (905) 573-0300.

Reprinted by permission of Canadian Occupational Safety © Thomson Reuters Canada Ltd., April/May 2015, Toronto, Ontario, 1-800-387-5164. Web: www.cos-mag.com.

 

Related Articles


Latest Articles


Changing Scene

  • Thermon Expands Electric Heater Offering Through Aquisition of F.A.T.I.

    Thermon Expands Electric Heater Offering Through Aquisition of F.A.T.I.

    October 25, 2024 Thermon has announced the acquisition of Fabbrica Apparecchiature Termoelettriche Industriali S.r.L. (F.A.T.I.), a manufacturer of electric heaters for industrial applications, based in Milan, Italy. F.A.T.I. is a leading designer and manufacturer of electrical heaters and heating systems for a broad range of industrial end markets, including oil & gas, pharmaceutical, renewables, nuclear… Read More…

  • CDM2 Partners with ELEC-TECH Sales to Expand Emergency Lighting Solutions Across BC

    CDM2 Partners with ELEC-TECH Sales to Expand Emergency Lighting Solutions Across BC

    October 25, 2024 CDm2 LIGHTWORKS is pleased to announce a strategic partnership with Elec-Tech Sales to bring ABB LUMACELL emergency lighting products and systems into their diverse application-driven solutions. “This partnership with Elec-Tech Sales strengthens our ability to deliver a robust portfolio of integrated lighting, controls, and electrical solutions,” noted Darren Luce, President + Principal of CDm2 LIGHTWORKS. “Together,… Read More…

  • Manitoba Government Introduces Legislation to Help Build New Housing Faster

    Manitoba Government Introduces Legislation to Help Build New Housing Faster

    October 25, 2024 The Manitoba government has introduced amendments to the Planning Act and the City of Winnipeg Charter Act that would change the appeals process for zoning changes by removing a requirement that made it difficult for municipalities to change local zoning bylaws and allowing faster new housing construction, Municipal and Northern Relations Minister… Read More…

  • Piloting New Ways to Make Homes More Energy-Efficient and Affordable

    Piloting New Ways to Make Homes More Energy-Efficient and Affordable

    October 22, 2024  Canada’s buildings sector is the third-largest contributor to greenhouse gas emissions across the country.  We must increase the scale and pace of retrofitting buildings across the country to make them more energy-efficient, increasing savings and reducing emissions. A federal investment totalling $4.3 million has been announced for five projects funded under the Greener Neighbourhoods Pilot Program (GNPP)… Read More…