PEI Begins Substantial Interconnection Upgrade Project

PEI Interconnection Upgrade

June 31 2016

Prince Edward Island has begun on one of the largest construction projects in its history — replacing and upgrading undersea electrical connections between PEI and New Brunswick.
The Interconnection Upgrade Project, a joint effort with the federal government, will allow PEI to import electricity from New Brunswick through two new 180 MW submarine cables, overhead transmission lines, substation upgrades and more. The submarine cables will be owned by the province and leased to and operated by Maritime Electric. Project costs have been estimated at between $120 million and $140 million.

When the existing submarine cables were installed nearly 40 years ago, the electricity load was 95 MW. In 2015, it peaked at 262 MW. PEI has no natural energy supply sources and relies on off island sources for cost-effective and reliable energy supply. While the province has developed significant wind energy supply, this supply requires back up for times when there is no wind.

The project offers at least five benefits:
• enabling future electrical growth on PEI
• improving reliability for customers
• reducing reliance on fossil-fueled generation
• creating a secure, reliable connection to the mainland
• providing access to a more economic energy supply

What’s involved

The project requires
• installation of two 180 MW submarine cables between Borden, PEI and Cape Tormentine, NB, (16.5 km) in the Northumberland Strait
• construction of 60 km of new overhead transmission line between Cape Tormentine and Memramcook
• construction of a substation extension at Borden, PEI

The project also includes:
• two landfall sites (where the submarine cable trench is brought ashore)
• two termination sites (for converting submarine cables to overhead transmission lines or substation)
• upgrading of the New Brunswick Power Corporation (NB Power) substation in Memramcook, NB

The first construction phase involves pre-trenching. This process involves a marine excavator called a Starfish and two mechanical marine dredges: one at PEI’s Borden-Carleton site and the other at New Brunswick’s Cape Tormentine site.

On the Cape Tormentine side the Starfish will be used excavate approximately 600 metres from shore into the Northumberland Strait. Once that distance is reached the Starfish will be shipped to the PEI side and the mechanical marine dredge will continue to excavate to the 1.8 km mark offshore.

The Starfish will be in operation for 12 hours daily for excavation. The two mechanical marine dredges will be working 24 hours per day on excavation. This process, expected to take 6-8 weeks, will ensure there are no rock obstructions along the route when the cable is laid in mid October.

The two cables will be installed under the seabed in separate trenches, up to 200 m apart. In water depths of greater than 12 m the cables will be buried at 0.6 m, while in areas of less than 12 m of water the cable will be buried at approximately 2 m. Excavating within the marine environment will involve trenching with excavators in water depths up to 2 m and a trenching remotely operated vehicle (TROV) with a saw cutter for the remaining sections. Exclusion zones around the cables are not planned. There will be no fishing restrictions. Once the cables have been installed, navigation charts will be updated.

The entire project is scheduled for completion in late spring or early summer 2017.

 

 

Related Articles


Latest Articles

  • Declines in Ontario and Manitoba Construction Intentions Push Down the Non-Residential Sector

    Declines in Ontario and Manitoba Construction Intentions Push Down the Non-Residential Sector

    December 16, 2024 The total value of building permits issued in Canada decreased by $399.1 million (-3.1%) to $12.6 billion in October. This comes on the heels of a strong September, during which construction intentions rose by $1.3 billion to the second-highest level in the series. Despite the monthly decline in October, the total value of building permits… Read More…

  • Lighting Control Basics for Home Automation

    Lighting Control Basics for Home Automation

    By Matthew Biswas Do your eyes roll when you hear terms like Smart home technology?  Or are you a true believer?  As it turns out controlling electrical devices via low-voltage technology can be easier to implement and use than many of us thought. The Lutron Caseta system uses the internet and Radio Frequency to instantly… Read More…

  • Grounded in Ontario: The Future of Energy Storage Systems

    Grounded in Ontario: The Future of Energy Storage Systems

    December 16, 2024 Technical Advisor Trevor Tremblay explains why following best practices and relying on licensed professionals will ensure a smooth and secure transition when integrating this exciting new technology. Energy Storage Systems (ESS) are revolutionizing the way individuals and businesses manage energy, providing cost-saving opportunities, increased energy reliability, and a pathway toward sustainability. In… Read More…

  • 4 in 5 Canadians See Electrifying Public Transit as Key to Advancing Climate Action, Schneider Electric Survey Finds

    4 in 5 Canadians See Electrifying Public Transit as Key to Advancing Climate Action, Schneider Electric Survey Finds

    December 13, 2024 Schneider Electric has released new survey findings showing Canadians are increasingly concerned about the environmental impact of traditional public transit emissions. According to the survey, 83 per cent of Canadians recognize the need for electrified transit to support a sustainable future and are seeking actionable and innovative solutions to ease the nation’s… Read More…


Changing Scene