Case Study: Guildford, BC’s Recreation Centre Aquatic Addition

December 12, 2016

The Guildford Recreation Centre Aquatic Addition expands an existing facility in Surrey, BC. The 7,000 square meter addition was designed as a destination aquatic facility for both recreation and therapeutic users, offering a 50m Federation Internationale de Natation (FINA) certified lap pool as well as a leisure pool that contains a therapeutic area, waterslide, family friendly hot tub, and children’s area.

The City of Surrey’s initial project objectives were to increase the value of the facility to the city and the community, reduce waste, and maximize efficiency. Surrey’s “Wood First Policy” was achieved in the design of the Guildford Recreation Centre Aquatic Addition, which incorporated the lighting and HVAC for the natatorium. Initially destined to be open web steel joist, the final product consists of three dimensional timber trusses. The trusses were pre-assembled offsite, which allowed for easier installation, reduced waste and cost, and saved construction time to help with the accelerated schedule. This solution became a defining feature of the Guildford Aquatic Centre.

The project earned an IES Edwin R. Guth Award for Interior Lighting Design. 

Project objectives, solutions and achievements

A primary goal of the Guildford Recreation Centre Aquatic Addition was to create a building that would provide the public of all ages with a welcoming swimming pool, where they can compete, exercise, play, and relax. The City of Surrey wanted the lap pool designed to FINA swimming pool guidelines in order to host FINA competitions within the facility, allowing both the public and competitors to enjoy their activities within the same versatile facility.

Electrical engineering design was of key importance to this project in order to meet the competition lighting levels as well as the architectural intent. Meeting the client’s objectives of an aesthetically pleasing and versatile swimming pool, while staying within the energy code requirements, and budget, required creative solutions to minimize equipment costs and maximize equipment efficiency.

AES Engineering Ltd. (AES) worked with other project team members, such as the architectural and mechanical teams, on how their system and design selections would ultimately govern the lighting design throughout the building. Working together in an integrated environment, AES proposed using indirect high efficiency lighting that would create a soft diffused light that would provide the swimming pool with a pleasant glare free light and competition lighting levels, while remaining within energy use requirements.

Light output was maximized through the use of lighting modelling software, high reflectivity paint, high efficiency luminaires, and optimal mounting angles.

Working closely with the multidisciplinary team allowed all systems within the trusses and coves to be configured such that maximum light output was achieved, resulting in a lower overall energy consumption throughout the facility. Various dimensions, angles, material types, and finishes were modelled for the coves and trusses to achieve optimum design characteristics and maximize light output. The resulting design provides the public with comfortable levels of lighting while using minimal amounts of energy.

Project management was crucial to keeping the project on schedule and on budget as the City of Surrey had set an accelerated timeline. In order to meet this, the project had to be designed in multiple packages. The foundation package was designed first, well in advance of the systems inside the building, while the second package contained the remainder of the project design. AES worked in a construction management environment, with contractors who could advise what materials would be available in time to fit the schedule. The prime consultant’s project schedule and AES’s internal deadlines allowed the project to reach substantial completion by the City of Surrey’s deadline.

Technical excellence/innovation: electrical

• Computer modelling — AES utilized various software tools to maximize the light output from both the coves and the trusses. Modelling of various lighting types at multiple angles and positions helped determine which luminaire and layout would provide the best light quality and efficiency within the trusses. To further increase the light output from the truss lighting system, high reflectivity paint was selected and specified by the architect, and the lights were mounted at optimal angles to maximize the amount of light reflected onto the pool. The resulting truss lighting system provides the swimming pool with a very pleasant and even light.

• Low voltage lighting controls — the use of low voltage (LV) lighting controls provided flexibility to the truss lighting system. Three levels of lighting have been implemented within the space to provide selection options to suit its current use. Traditionally, lights are switched in rows or groups, but the lights in the trusses have been configured to switch in an interweaving pattern so that an even light output is achieved no matter what level of light is selected. Providing an even illumination using a minimal number of lights reduces overall energy consumption without sacrificing comfort or safety. The LV system is also scheduled to sweep off all lights when not required, further reducing the carbon footprint of the facility. 

• LED lighting — another energy saving measure includes the use of LED underwater lights rather than traditional halogen lighting. The LV lighting system is also tied in to the underwater lights to provide two user selectable lighting levels.

• Occupancy sensors — working in combination with the LV lighting system, occupancy sensors within enclosed offices, meeting rooms, and washrooms, automatically turn off lights to provide maximum energy savings.

 

A sampling of project luminaires

Among the luminaires used for the project are the following:

• Bartco BFL206 Linear T5s

• Cole Lighting L500 LED Steplites

• Focal Point Avenue D MR 16

• Green Imagetech GX436 vapourproof luminaires

• Kenall Mighty Mac WCBU Series

• Lithonia Lighting AS1 LED, FEM 2s, 4s and 8s, MRP Omero LED, Saturn compact DTT fluorescent, 

• Metalumen Grande RM4DOD

• Pace Illumination Avante-Garde AGSM surface mount

• Paco Lighting Puac T5s and T8s

• Rigalite MHD2/MHDO Series

• Sistemalux Megaeos and Megabrique 

• USAI Lighting BeveLED 2.0

• Winona Winline 309W linear LEDs

 

Project members

• Electrical engineer: AES Engineering Ltd. 

• Project owner/client: City of Surrey 

• Architects: Bing Thom Architects, Shape Architecture 

• Prime consultant: Bing Thom Architects 

• Other consultants involved: The AME Consulting Group Ltd., Fast + Epp, 

• Turnbull Construction Project Managers 

• Contractors: Heatherbrae Builders 

• Photographer: Ema Peter

 

Related Articles


Latest Articles

  • Ontario Solar Incentives with Essex Energy

    Ontario Solar Incentives with Essex Energy

    August 20, 2025 Essex Energy is helping municipalities, universities and colleges across Ontario take advantage of incentives under Ontario’s Retrofit DER Program including solar photovoltaic (PV) systems. What’s Available Significant rebates available to eligible businesses and institutional organizations deploying rooftop or parking lot solar PV systems. These incentives are paid upon completion of the project, accelerating project… Read More…

  • Beyond the Bid: How Modern Estimating Solutions Drive Contractor Success

    Beyond the Bid: How Modern Estimating Solutions Drive Contractor Success

    August 18, 2025 By Brooke Stewart In today’s fast-paced construction landscape, electrical contractors are constantly pressured to keep their estimates competitive, often at the expense of healthy profit margins. Compounding this challenge are rising material costs, a shortage of skilled labor and siloed data, all of which make it increasingly difficult to stay competitive and… Read More…

  • Hammond Power Solutions Helps EFC Champion Sustainability as First Carbon Neutral Sponsor at Annual Industry Conference

    Hammond Power Solutions Helps EFC Champion Sustainability as First Carbon Neutral Sponsor at Annual Industry Conference

    August 18, 2025 By Electro-Federation Canada Did you know that carbon emissions from this year’s Annual Industry Conference were offset? With the help of Hammond Power Solutions (HPS), EFC took an important step toward reducing our environmental impact by offsetting the emissions associated with the event. This milestone reflects a growing commitment within the electrical… Read More…

  • FortisBC Detail Impact of their Energy-Efficiency Programs in 2024

    FortisBC Detail Impact of their Energy-Efficiency Programs in 2024

    August 18, 2025 In 2024, FortisBC Energy Inc. and FortisBC Inc.’s (collectively FortisBC) conservation and energy-efficiency programs helped lower gas and electricity use while helping create more comfortable living and working spaces for customers. Building on 2023 reductions, its gas programs cut close to one million tonnes of carbon dioxide equivalent (tCO₂e) 1 in 2024. “Our customers’… Read More…


Changing Scene

  • Blackline Safety Announces Quality Assurance Program Expansion

    August 18, 2025 Blackline Safety Corp. has announced a major expansion of its quality assurance (QA) program. As part of the expansion, the company has increased its QA team, upgraded its inspection equipment, and boosted in-lab testing of its entire product line. Headquartered in Canada with offices in the UK, France, U.S., and UAE, Blackline… Read More…

  • EB Horsman Introcuce New Burnaby Branch Manager

    EB Horsman Introcuce New Burnaby Branch Manager

    August 18, 2025 EB Horsman & Son is pleased to announce the promotion of Sean O’Brien to Branch Manager of their Burnaby location, effective August 6, 2025. Sean brings over 15 years of experience in the electrical and lighting industry, with a strong background in sales, technical leadership, project management, and clean energy initiatives. He… Read More…

  • BCCA Response to “Report on 2026 Budget Consultation”

    BCCA Response to “Report on 2026 Budget Consultation”

    August 18, 2025 BCCA is pleased to receive the Standing Committee on Finance and Government Services’ Report on the 2026 Budget Consultation, and celebrates the emphasis placed on supporting BC’s construction industry and workforce. Chris Atchison, President of the BCCA, spoke to the Committee on the recommendations and priorities of BC’s construction industry. These included:… Read More…

  • NSAA Introduces Mentorship for Women Apprentices Program

    NSAA Introduces Mentorship for Women Apprentices Program

    August 18, 2025 This program is designed to support the retention and progression to certification of women apprentices in the 39 Red Seal Construction or Manufacturing trades. The program pairs women apprentices with experienced tradespeople to provide guidance, career development, and support throughout their apprenticeship journey. The program is for 6 months, with the mentor and… Read More…