Prince Edward Island has begun on one of the largest construction projects in its history — replacing and upgrading undersea electrical connections between PEI and New Brunswick.
The Interconnection Upgrade Project, a joint effort with the federal government, will allow PEI to import electricity from New Brunswick through two new 180 MW submarine cables, overhead transmission lines, substation upgrades and more. The submarine cables will be owned by the province and leased to and operated by Maritime Electric. Project costs have been estimated at between $120 million and $140 million.

When the existing submarine cables were installed nearly 40 years ago, the electricity load was 95 MW. In 2015, it peaked at 262 MW. PEI has no natural energy supply sources and relies on off island sources for cost-effective and reliable energy supply. While the province has developed significant wind energy supply, this supply requires back up for times when there is no wind.

The project offers at least five benefits:
• enabling future electrical growth on PEI
• improving reliability for customers
• reducing reliance on fossil-fueled generation
• creating a secure, reliable connection to the mainland
• providing access to a more economic energy supply

What’s involved

The project requires
• installation of two 180 MW submarine cables between Borden, PEI and Cape Tormentine, NB, (16.5 km) in the Northumberland Strait
• construction of 60 km of new overhead transmission line between Cape Tormentine and Memramcook
• construction of a substation extension at Borden, PEI

The project also includes:
• two landfall sites (where the submarine cable trench is brought ashore)
• two termination sites (for converting submarine cables to overhead transmission lines or substation)
• upgrading of the New Brunswick Power Corporation (NB Power) substation in Memramcook, NB

The first construction phase involves pre-trenching. This process involves a marine excavator called a Starfish and two mechanical marine dredges: one at PEI’s Borden-Carleton site and the other at New Brunswick’s Cape Tormentine site.

On the Cape Tormentine side the Starfish will be used excavate approximately 600 metres from shore into the Northumberland Strait. Once that distance is reached the Starfish will be shipped to the PEI side and the mechanical marine dredge will continue to excavate to the 1.8 km mark offshore.

The Starfish will be in operation for 12 hours daily for excavation. The two mechanical marine dredges will be working 24 hours per day on excavation. This process, expected to take 6-8 weeks, will ensure there are no rock obstructions along the route when the cable is laid in mid October.

The two cables will be installed under the seabed in separate trenches, up to 200 m apart. In water depths of greater than 12 m the cables will be buried at 0.6 m, while in areas of less than 12 m of water the cable will be buried at approximately 2 m. Excavating within the marine environment will involve trenching with excavators in water depths up to 2 m and a trenching remotely operated vehicle (TROV) with a saw cutter for the remaining sections. Exclusion zones around the cables are not planned. There will be no fishing restrictions. Once the cables have been installed, navigation charts will be updated.

The entire project is scheduled for completion in late spring or early summer 2017.

 

 

Related Articles


Latest Articles


Changing Scene

  • Thermon Expands Electric Heater Offering Through Aquisition of F.A.T.I.

    Thermon Expands Electric Heater Offering Through Aquisition of F.A.T.I.

    October 25, 2024 Thermon has announced the acquisition of Fabbrica Apparecchiature Termoelettriche Industriali S.r.L. (F.A.T.I.), a manufacturer of electric heaters for industrial applications, based in Milan, Italy. F.A.T.I. is a leading designer and manufacturer of electrical heaters and heating systems for a broad range of industrial end markets, including oil & gas, pharmaceutical, renewables, nuclear… Read More…

  • CDM2 Partners with ELEC-TECH Sales to Expand Emergency Lighting Solutions Across BC

    CDM2 Partners with ELEC-TECH Sales to Expand Emergency Lighting Solutions Across BC

    October 25, 2024 CDm2 LIGHTWORKS is pleased to announce a strategic partnership with Elec-Tech Sales to bring ABB LUMACELL emergency lighting products and systems into their diverse application-driven solutions. “This partnership with Elec-Tech Sales strengthens our ability to deliver a robust portfolio of integrated lighting, controls, and electrical solutions,” noted Darren Luce, President + Principal of CDm2 LIGHTWORKS. “Together,… Read More…

  • Manitoba Government Introduces Legislation to Help Build New Housing Faster

    Manitoba Government Introduces Legislation to Help Build New Housing Faster

    October 25, 2024 The Manitoba government has introduced amendments to the Planning Act and the City of Winnipeg Charter Act that would change the appeals process for zoning changes by removing a requirement that made it difficult for municipalities to change local zoning bylaws and allowing faster new housing construction, Municipal and Northern Relations Minister… Read More…

  • Piloting New Ways to Make Homes More Energy-Efficient and Affordable

    Piloting New Ways to Make Homes More Energy-Efficient and Affordable

    October 22, 2024  Canada’s buildings sector is the third-largest contributor to greenhouse gas emissions across the country.  We must increase the scale and pace of retrofitting buildings across the country to make them more energy-efficient, increasing savings and reducing emissions. A federal investment totalling $4.3 million has been announced for five projects funded under the Greener Neighbourhoods Pilot Program (GNPP)… Read More…