PEI Begins Substantial Interconnection Upgrade Project

PEI Interconnection Upgrade

June 31 2016

Prince Edward Island has begun on one of the largest construction projects in its history — replacing and upgrading undersea electrical connections between PEI and New Brunswick.
The Interconnection Upgrade Project, a joint effort with the federal government, will allow PEI to import electricity from New Brunswick through two new 180 MW submarine cables, overhead transmission lines, substation upgrades and more. The submarine cables will be owned by the province and leased to and operated by Maritime Electric. Project costs have been estimated at between $120 million and $140 million.

When the existing submarine cables were installed nearly 40 years ago, the electricity load was 95 MW. In 2015, it peaked at 262 MW. PEI has no natural energy supply sources and relies on off island sources for cost-effective and reliable energy supply. While the province has developed significant wind energy supply, this supply requires back up for times when there is no wind.

The project offers at least five benefits:
• enabling future electrical growth on PEI
• improving reliability for customers
• reducing reliance on fossil-fueled generation
• creating a secure, reliable connection to the mainland
• providing access to a more economic energy supply

What’s involved

The project requires
• installation of two 180 MW submarine cables between Borden, PEI and Cape Tormentine, NB, (16.5 km) in the Northumberland Strait
• construction of 60 km of new overhead transmission line between Cape Tormentine and Memramcook
• construction of a substation extension at Borden, PEI

The project also includes:
• two landfall sites (where the submarine cable trench is brought ashore)
• two termination sites (for converting submarine cables to overhead transmission lines or substation)
• upgrading of the New Brunswick Power Corporation (NB Power) substation in Memramcook, NB

The first construction phase involves pre-trenching. This process involves a marine excavator called a Starfish and two mechanical marine dredges: one at PEI’s Borden-Carleton site and the other at New Brunswick’s Cape Tormentine site.

On the Cape Tormentine side the Starfish will be used excavate approximately 600 metres from shore into the Northumberland Strait. Once that distance is reached the Starfish will be shipped to the PEI side and the mechanical marine dredge will continue to excavate to the 1.8 km mark offshore.

The Starfish will be in operation for 12 hours daily for excavation. The two mechanical marine dredges will be working 24 hours per day on excavation. This process, expected to take 6-8 weeks, will ensure there are no rock obstructions along the route when the cable is laid in mid October.

The two cables will be installed under the seabed in separate trenches, up to 200 m apart. In water depths of greater than 12 m the cables will be buried at 0.6 m, while in areas of less than 12 m of water the cable will be buried at approximately 2 m. Excavating within the marine environment will involve trenching with excavators in water depths up to 2 m and a trenching remotely operated vehicle (TROV) with a saw cutter for the remaining sections. Exclusion zones around the cables are not planned. There will be no fishing restrictions. Once the cables have been installed, navigation charts will be updated.

The entire project is scheduled for completion in late spring or early summer 2017.

 

 

Related Articles


Latest Articles

  • ESA 2025 Annual Licence Holder Meeting

    ESA 2025 Annual Licence Holder Meeting

    December 8, 2025 This year marked ESA’s 20th Annual Licence Holder Meeting — a milestone celebrating two decades of collaboration, innovation and safety leadership made possible by Ontario’s licence holder community. The meeting was held on Wednesday, November 26, 2025 Agenda Highlights Watch a recording of the 2025 Licence Holder Meeting. Read More…

  • BC Hydro’s Updated Business Energy-Saving Incentives, Limited Time Bonus Offer

    BC Hydro’s Updated Business Energy-Saving Incentives, Limited Time Bonus Offer

    December 8, 2025 Get funding from BC Hydro for businesses upgrading eligible equipment with energy-efficient models. Funding rates vary depending on the equipment being upgraded, with past participants receiving an average of 30% for upfront costs. Incentives are available for: Bonus offer BC Hydro is currently offering a 30% bonus incentive on all business energy-saving incentives projects… Read More…

  • Mastering Advanced Bidding Strategies in Electrical Contracting

    Mastering Advanced Bidding Strategies in Electrical Contracting

    December 1, 2025 By Melvin Newman, Patabid CEO & Ian Paterson, Patabid Client Success Manager and journeyman electrician with 30+ years of experience In the competitive world of electrical contracting, knowing how to estimate electrical jobs effectively can make the difference between winning profitable projects and watching opportunities slip away. For electrical contractors, mastering advanced… Read More…

  • Why Choosing the Right USB Charger Matters

    Why Choosing the Right USB Charger Matters

    December 1, 2025 Not all USB Chargers are Created Equal As the number of devices used daily increases, so does the need for a charger that delivers safe speeds and maximum charging potential. A high-quality USB charger delivers efficient charging without risk of damage, but the sea of USB chargers and outlets available on online… Read More…


Changing Scene