Cabling Certification: Multi-Everything Is the New Normal — Part 2

Cabling Certification

 

Feb 26, 2016

The industry is awash in “multiples” — multiple cables, multiple standards, multiple teams, multiple tools, multiple projects, multiple test regimes, multiple skill levels and more. That puts two opposing forces — increasing complexity and thinly stretched expertise — on a collision course that affects the fundamental connectivity of technology.

The implication is that if something doesn’t change, then some other factor has to give.

Part 1 discussed the evolution of datacom cabling and emerging challenges. Here in Part 2: the 6 steps of a certification process and the future of certification.Let’s take a look at what that certification looks like at the project level.

Cabling Fig 1
1. Planning — the first part of the install and certification process is typically left to the project manager. Most installers these days are managing the testing and certification of multiple jobs simultaneously, each with multiple teams, test tools and requirements. This is not only time consuming, but the increased complexity can, and is, leading to costly errors.

2. Setup — the next phase is setup, ensuring that the requirements are known and the tool is correctly configured to test those param¬eters. Complexity is growing in this area as well: we have multiple media types, different categories and varying standards. For frontline technicians, the impact is either in needing to wait for a particular expert to set up the tool or run the risk of making costly errors that require rework.

3. Testing — testing can always be faster. But again, the speed of current testers is such that the ability to gain huge advantages in this part of the process is limited — there are now much greater gains to be had elsewhere.

4. Troubleshooting —the varying skill levels of technicians, or even simple lack of familiarity with certain types of installations or different standards, typically means that projects are delayed until the needed expertise is available to troubleshoot.

5. Reporting — in many ways, reporting has become the bane of installation. Not only is it increasingly complex — working in an environ¬ment with multiple testers, teams, standards and test regimes makes generating the requisite reports a time consuming process — but this is also the point at which errors and oversights from earlier in the certification become apparent, resulting in delays.

6. System acceptance — this is a growing challenge for customers. If installers, who live and breathe cabling, are overwhelmed by the increasing complexity, one can only imagine what it’s like for customers. Multiple complex reports, varying test regimes, etc., can all impact system acceptance.

The future of certification

All things being equal, a possible answer to these requirements would be adding more expert project managers to the process, so that they could apply the insight, training and oversight needed to eliminate errors and improve efficiency. Unfortunately this isn’t economically feasible.

The solution then is a testing tool that helps take on that role, managing the test process as well as the test itself.

What’s needed is a new solution that would be much more agile, able to address every part of the certification process from planning through system acceptance, and multiplex testing scenarios. It would also incorporate built-in intelligence and a revolutionary touch-screen interface that would walk technicians through testing and project requirements, regardless of training. It would be built from the ground up for the “multi” environment, and help project managers and technicians meet the evolving challenges associated with cable certification.

Looking at the six-step certification process again, such a solution would deliver significant benefits:

• Planning — the appropriate tool would incorporate project management capabilities to seamlessly plan and manage multiple jobs, different cable types or testing regimes, multiple teams, and more. In short, it would be adept at simultaneously handling all the complexity thrown at the typical cable infrastruc¬ture installation, thus improving efficiency and eliminating costly errors.

• Setup — test setup wizards would deliver guided referencing and link budget configuration, as well as incorporating built-in standards to ensure the right tests are performed (see Figure 5). This approach eliminates the “wait for an expert” delay as well as further reducing errors.

• Testing — as we’ve said, testing can always be faster, and tools continue to improve in speed. More importantly, built-in wizards and a graphical interface will quickly get the user to the right test configuration, also improving speed.

• Troubleshooting — the ability to drill down to identify root cause (see Figure 6), as opposed to a simple pass-fail, is critical to effective troubleshooting. This drill-down, along with precision graphical wiremaps, allows technicians of varying skill levels to quickly pinpoint and correct problems. 

• Reporting — reporting, as we’ve shown, is evolving and the need for flexibility and agility never ends. To eliminate this challenge, test tools should incorporate a project system that manages results across multiple teams, media and testers to control and integrate results into a single report across an entire project (see Figure 7). Moreover, the dramatic improvements made in earlier segments of the certifica¬tion process should largely eliminate common errors and oversights, speeding project completion.

• System acceptance — if complexity tends to “complicate” system acceptance, then the antidote is a clear system that uses concise statistics, event maps and ISO Level V accuracy certification to deliver instant insight into job quality without the need to page through thousands of reports.

• Remain Agile — if the future of cable infrastructure, and technology in general, is ever increasing complexity, then we must demand more from our tools to keep up. We must be more agile. And today that means much more than just raw speed. Keeping the cable infrastructure healthy and on-pace with the rest of the industry means focusing on the entire certification process, optimizing workflow as needed around the ever-increasing multitude of job requirements to speed system acceptance. Contractors that do not successfully evolve to address these complexities will simply be replaced by those that can.

Cabling infrastructure is evolving, fast. Everything else must evolve with it.

About Fluke Networks
Fluke Networks is the world-leading provider of network test and monitoring solutions to speed the deployment and improve the perfor¬mance of networks and applications. Leading enterprises and service providers trust Fluke Networks’ products and expertise to help solve today’s toughest issues and emerging challenges in WLAN security, mobility, unified communications and data centres. Based in Everett, Washington, the company distributes products in more than 50 countries. For more information, visit www.FlukeNetworks.com or call +1 (425) 446-4519.

*All research in this white paper is based on a Fluke Networks research study.

 

Related Articles


Latest Articles

  • EFC Letter on China Tariffs

    EFC Letter on China Tariffs

    September 15, 2024 The Canadian federal government intends to apply a 25 per cent surtax on imports of steel and aluminum products from China, effective October 15, 2024. See announcement here. The initial list of impacted goods was released for public comment and submissions are due September 20, 2024.  The list of products is available… Read More…

  • Changing How we Build Homes: A Year of the Housing Accelerator Fund

    Changing How we Build Homes: A Year of the Housing Accelerator Fund

    September 15, 2024 The Government of Canada is highlighting key results that have come from the first Housing Accelerator Fund since the start of the Program. This week marks the closure of the application portal for the second round of the HAF. HAF was created to incentivize local governments to implement structural and lasting reforms that will increase… Read More…

  • Multi-Unit Construction Intentions Fuel Growth in the Residential Sector for July Building Permits

    Multi-Unit Construction Intentions Fuel Growth in the Residential Sector for July Building Permits

    September 15, 2024 Month over month, the total value of building permits in Canada surged 22.1% to $12.4 billion in July, rebounding from two consecutive monthly declines. Both the residential and non-residential sectors expanded in July. On a constant dollar basis (2017=100), the total value of building permits in July was up 22.9% compared with the previous month,… Read More…

  • B.C. Building Code Updated to Support More Homes

    B.C. Building Code Updated to Support More Homes

    September 15, 2024 Changes to the BC Building Code (BCBC) will allow single egress stair (SES) designs in low- and mid-rise buildings to support more multi-bedroom apartment options. The Province has updated the BCBC to remove the code requirement for a second egress, or exit, stairwell per floor in buildings up to six storeys. This change will… Read More…


Changing Scene

  • Leviton Canada Achieves Another Year of Carbon Neutrality

    Leviton Canada Achieves Another Year of Carbon Neutrality

    September 15, 2024 Leviton Canada proudly reaffirms its commitment to sustainability by achieving carbon neutrality once again in 2023. The company has significantly reduced their environmental footprint by 32% compared to 2022, with a substantial impact on transportation. Despite having energy-efficient lighting and relying on hydropower—a clean and renewable energy source—for their facility, transportation (both… Read More…

  • Grand Opening: Legrand BCS Office in Markham

    Grand Opening: Legrand BCS Office in Markham

    September 15, 2024 Legrand is thrilled to announce the grand opening of their new BCS facility in the heart of downtown Markham, ON, located at 85 Enterprise Blvd, Suite 400, which is set to take place on Thursday, September 19th, 2024. “Our facility in Vaughan will remain open to continue to stock inventory for Canada… Read More…

  • Gescan Announces Partnership with PataBid

    Gescan Announces Partnership with PataBid

    September 15, 2024 Gescan is excited to announce our partnership with PataBid Quantify. PataBid is a Canadian company, with software built for contractors which integrates live supplier pricing, manual drafting, and AI technology with human expertise to maximize take offs and bidding. Patabid’s Quantify software will allow contractors to access live pricing from Gescan’s website… Read More…

  • Electrical Safety Authority Unveils ‘A-MAZE-ing’ Interactive Experience to Keep Kids Safe from Electrical Harm

    Electrical Safety Authority Unveils ‘A-MAZE-ing’ Interactive Experience to Keep Kids Safe from Electrical Harm

    September 15, 2024 The Electrical Safety Authority (ESA) cut the ribbon on its new interactive experience, “The A-MAZE-ing Adventures of Carter Current”, located at the Peel Children’s Safety Village. The interactive space is designed to help educate and keep kids safe from electrical harm by learning about electrical hazards through play. “We are excited to partner with… Read More…