Case Study: Temporary Power for Large Scale Residential Construction

Temporary Power

Ever wonder how large construction projects with sales offices and show suites get power when there is only a generator or temporary power established on the construction site?TheBC Safety Authority (BCSA) pays close attention to these types of installations, since fire alarms, sprinklers, and other building code safety systems are not up and running during the construction phase of the project.

Recently, a BCSA safety officer conducted an assessment of a large multi-family residential site under construction. Working collaboratively with electrical contractors, other trades, safety officials, utilities, and building departments to reach safety solutions is an important part of a BCSA safety officer’s role.

During the inspection, several significant hazards were found.Most notably, townhouses had been energized using the temporary construction service, creating a risk of overload to the service. Had these dwellings become occupied, this could have resulted in a serious fire and shock hazard.

An additional hazard was created by the power cable used to provide power from the temporary distribution system to the townhouses, which was not installed with the necessary mechanical protection.Construction sites typically have heavy machinery operating and it is imperative that the power cables be installed in a manner that protects them from mechanical damage.A break in the armoured cable can result in either a fire (if combustible material is near by) or a shock hazard if the bonding provisions have been compromised.

Addressing the hazards
The safety officer first documented his findings in a certificate of inspection and contacted the electrical contractor to develop a plan to rectify the identified non-compliances.The contractor submitted an application for a variance, as required by the Safety Standards Act, to energize the show rooms and sales offices.The variance included a request to energize a specific portion of the site, and outlined the wiring method used to provide power to this area of the site, and the signage required at strategic locations on the site, including mark ups on the site’s safety plans.The safety officer granted the variance and the electrical contractor completed the installation and the obligations outlined in the variance.

To reduce the safety hazards on the site, branch circuits inside each dwelling had all unnecessary circuit conductors disconnected from circuit breakers. The heavy loads such as space heating, furnaces, dryers, ranges were also disconnected.The safety officer then informed BC Hydro and the electrical contractor that a “hold connection” be placed on the permanent installation permit.This ensures that when the permanent installation is ready for power, the necessary work is completed to transfer and disconnect the temporary power in the showrooms to remove the risk of a possible back feed.

When dealing with sites that have both permanent and temporary electrical systems, closely review your electrical code, specifically the stating that interconnection of temporary power installations and permanent installations shall not be interconnected unless by special permission.

This article was first published online by the BC Safety Authority, http://safetyauthority.ca.

 

Related Articles


Latest Articles

  • Just Getting Started – Discussing Milwaukee’s 100 Year Anniversary with President of Milwaukee Tool Canada, John Myers

    Just Getting Started – Discussing Milwaukee’s 100 Year Anniversary with President of Milwaukee Tool Canada, John Myers

    September 23, 2024 By Blake Marchand It goes without saying that the Milwaukee brand is historic. Their longevity is a testament to company culture and innovation. As this year marks Milwaukee’s 100th anniversary, the company held a tree planting ceremony earlier in the year to mark the milestone, planting 100 trees in partnership with Tree… Read More…

  • ECABC Provides Platform Recommendations to BC Political Parties

    ECABC Provides Platform Recommendations to BC Political Parties

    September 23, 2024 The Electrical Contractors Association of British Columbia has provided three platform policy recommendations to each of BC’s major political parties in advance of the October 19, 2024 provincial election: implementing prompt payment legislation, increasing capital and operating funding to support electrical apprentices, and naming a Minister responsible for construction in their Cabinet…. Read More…

  • NETCO 2024 Conference in Victoria: The Evolution of the Electrician

    NETCO 2024 Conference in Victoria: The Evolution of the Electrician

    September 20, 2024 The Evolution of the Electrical Industry was Showcased eariler this month in Victoria, BC with the 2024 installment of NETCO’s Annual Conference Leaders and experts from the electrical industry gathered in Victoria, BC, September 5-6th, at the picturesque Inn at Laurel Point for the annual National Electrical Trade Council (NETCO) educational conference… Read More…

  • Desdowd Icon Patrick Marion Retires

    Desdowd Icon Patrick Marion Retires

    September 20, 2024 On September 11, more than 200 industry guests and colleagues celebrated Patrick Marion’s 35-year career history to the day. Guests travelled from across the country – some from as far as Vancouver and Halifax – to join those from Montreal and Toronto to celebrate Patrick’s career. Held at a prestigious golf club… Read More…


Changing Scene

  • Mitsubishi Electric Sales Canada Inc. and Efficiency Capital Partner to Cross Promote Low-Carbon Building Solutions in Canada

    Mitsubishi Electric Sales Canada Inc. and Efficiency Capital Partner to Cross Promote Low-Carbon Building Solutions in Canada

    September 23, 2024 Efficiency Capital (EC), Canada’s first Energy-as-a-Service (EaaS) company, and Mitsubishi Electric Sales Canada Inc. (MESCA) announced a strategic cross promotional partnership to make low-carbon building solutions more accessible to building owners and operators across Canada. Energy efficiency in buildings, despite being one of the critical pathways to meet Canada’s climate goals, faces… Read More…

  • Siemens to Carve out Electric Vehicle Charging Business to Enable next Level of Growth

    Siemens to Carve out Electric Vehicle Charging Business to Enable next Level of Growth

    September 23, 2024 Siemens has announced the intention to carve out its eMobility business. The company bundled its eMobility charging activities in 2018 and subsequently organized it into a separate business unit in 2022.  The carve out of Siemens eMobility, which has a strong technological core and portfolio, will give the business entrepreneurial freedom to… Read More…

  • FLO Confirms FLO Station Eligibility for ZEVIP Funding

    FLO Confirms FLO Station Eligibility for ZEVIP Funding

    September 24, 2024 Canada recently announced trade measures impacting vehicles from China and limiting eligibility under the Natural Resources Canada (NRCan) Zero Emission Vehicle Infrastructure Program (ZEVIP) to electric vehicle (EV) charging products manufactured in countries that have negotiated free trade agreements with Canada. Effective October 1, 2024, this directive is expected to have an impact on… Read More…

  • Saskatchewan Partners with IBEW to Deliver Union-Led Apprenticeship Training

    Saskatchewan Partners with IBEW to Deliver Union-Led Apprenticeship Training

    September 24, 2024 The Government of Saskatchewan and the International Brotherhood of Electrical Workers (IBEW) signed a letter of intent (LOI) to expand apprenticeship training in Saskatchewan by offering training that is to be union-led and delivered by the IBEW. “Saskatchewan has attracted over $40 billion in new investment in recent years, and this requires… Read More…