Arc Flash Incident Involving a Maintenance Switch

Maintenance Switch

 

Feb 12, 2016

This case study article examines the plans and processes reviewed and considered, the strategy deployed to manage/reduce arc flash hazards, and then lessons learned in the implementation of new systems to improve electrical workplace safety. The setting: a chemical processing facility with a robust electrical workplace safety process. The site experienced an actual arc flash event while energized work was being performed.

Photo courtesy: www.utilityproducts.com

The facility was planning energized work for an existing 480 V low voltage switchgear assembly that was an existing piece of equipment in the plant. During a process upgrade in the facility, an energized work permit was issued to remove three abandoned load conductors from an existing 480 V low voltage switchgear assembly cable compartment.

The work permit was very detailed and included tools planned for use in the project and required PPE for workers performing the task based on the incident energy defined by a recently completed arc flash hazard assessment. The defined task for the work order required the site contractor to use a nylon rope, which was typical with this type of project, disconnecting the de-energized cables and working to raise them from the top cable compartment. Figure 10 showsa layout of the low voltage assembly involved in the work.

The de-energized cables were to be removed from Cubicle 5, with still energized conductors existing in Cubical 4 at the bottom of the cable wireway. The rope used was not able to grab the conductors and would slip off of the cable, so the electrical contractor elected to employ a “come along” to assist in the removal, as the come along could apply more force. The first conductor was successfully removed with this new tool. Upon removing the second conductor, a small arc flash was observed in the lower compartment. Simultaneously, the lights to the plant went out.The contractor stopped work and waited for plant electricians to arrive, not knowing what had just occurred.

The event caused the entire plant to shut down, stopping work on the project until an analysis could be completed. It was determined that the chain of the come along had drifted below where the work was being performed and into energized Cubicle 4. Fortunately, the damage to the wall of the switchgear and come along tool was minimal, which is shown in Figure 11.

Post event analysis proved that the chain of the come along had drifted below where the work was being performed and into an energized cubicle. The chain touched an energized terminal and arced to ground, touching both phase conductor and cabinet ground metal below the non-energized cubicle where the electrician was working. After reviewing minimal damage and completing the project while de-energized, the plant switchgear was cleaned and re-energized. Fortunately, total downtime for the plant due to this event was minimal. No loss of equipment or injury to any employee occurred as a result of this event.

 

Eaton Arc Flash Safety

 

Low voltage assembly involved in planned energized work. The planned task included removing cables from de-energized Cubicle 5 while Cubical 4 in an adjacent section was still energized.

The important take-away here is that the arc flash study was completed before energized work was performed. The upstreamlow voltage power circuit breaker with a special maintenance switch setting discussed previously employed technology to clear the fault faster than the microprocessor instantaneous setting of the circuit breaker trip unit.

Calculations were previously performed that quantified a reduction in incident energy from 17.7 cal/cm2 to2.9 cal/cm2 using the special maintenance setting. Both workersand equipment were saved as a result of a total clearing time at 40 milliseconds as defined by the manufacturer’s published trip curves[8].

Lessons learned

This case study unequivocally proves that planning for the unplanned event can save lives. Some of the key lessons learned here:
• mistakes will happen on even the best planned projects. A change in tools is what led to this arc flash event
• proper planning and leveraging of all accessible resources prevented what could have been a catastrophic event
• leveraging technology can often deliver a reduction in the available energy. Using more sensitive settings can save both people and equipment should an arc flash event occur

Eaton Come Along

At left, a “come along” tool used for energized work and at right, damage to panel after phase to ground arc flash event with an upstream device with maintenance setting capabilities.

This case study is one of four published online by Eaton and has been lightly edited by EIN. See all case studies: http://www.eaton.com/ecm/groups/public/@pub/@eaton/@corp/documents/content/pct_1562591.pdf.

 

Related Articles


Latest Articles


Changing Scene

  • Nedco Opens New Kelowna Branch

    Nedco Opens New Kelowna Branch

    May 21, 2026 In a recent announcement from Nedco, the company celebrated the Grand Opening of the new Kelowna branch on Friday, May 8, 2026. Nedco invited attendees to explore the new 11,000 sq. ft. facility designed to conveniently serve Okanagan customers. The tour of the new facility took place from 11:00 AM to 2:00 Read More…

  • Leviton Canada Partners with NRG INTENSI‑T Inc. to Strengthen the Presence of Lighting Controls in the Quebec Region

    Leviton Canada Partners with NRG INTENSI‑T Inc. to Strengthen the Presence of Lighting Controls in the Quebec Region

    May 21, 2026 Leviton Canada is proud to announce its partnership with NRG INTENSI-T Inc., who will now represent Leviton’s Lighting Controls product line throughout the Quebec region, effective May 1, 2026. This new partnership reflects Leviton’s commitment to strengthening its lighting controls presence in Quebec through experienced, market-focused representation. With deep regional knowledge, an Read More…

  • Mac’s II Agencies Expands ABB Partnership into UPS Solutions

    Mac’s II Agencies Expands ABB Partnership into UPS Solutions

    May 21, 2026 As demand increases for resilient, always-on power for commercial, industrial, and mission-critical environments, Mac’s II Agencies is strengthening its Power Quality portfolio with ABB systems engineered for diverse conditions. With a broad range of sizes and configurations available, engineers, contractors, and end users can specify power backup and protection solutions with continued confidence, backed Read More…

  • EFC Conference Returns to Halifax with Focus on Industry Disruption and Growth

    EFC Conference Returns to Halifax with Focus on Industry Disruption and Growth

    May 20, 2026 Electro-Federation Canada (EFC) will bring together the electrical industry for its 2026 Annual Industry Conference, taking place June 2-4 at the Halifax Convention Centre. Under the theme “WaveMakers: Where Disruption Meets Direction,” the event will focus on the forces reshaping Canada’s electrical supply chain, including electrification, infrastructure investment, digital transformation, and evolving Read More…