Guide to the Canadian Electrical Code, Part I — Instalment 18

November 7, 2016 

By William (Bill) Burr

In this article: Section 32 — Fire Alarm Systems, Fire Pumps, and Carbon Monoxide Alarms. The code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook, but will hopefully provide some help in navigating the code.

Section 32, as outlined in rule 32-000 Scope, is a supplementary or amendatory section of the code and provides additional and specific requirements for the location, installation, wiring, and protection of fire alarm systems, fire pumps and smoke and carbon monoxide alarms required by the National Building Code of Canada as referenced in Appendix G. For further information, refer to Canadian Standard CAN/ULC – S524 Standard for the Installation of Fire Alarm Systems published by ULC Canada. Appendix B contains important additional helpful notes, and the CEC Handbook also contains helpful information.

Fire alarm systems

Rule 32-100 specifies the requirements for conductors in fire alarm systems, which include copper material, ampacity, use of optical fibre cables, use of stranded conductors, insulation rated at 300 volts, determining wire size for raceways or integral assemblies, and selection in accordance with rules 4-008(1) or 4-020(1).

Rule 32-102 outlines wiring methods for installation of conductors either in metal, non-metallic raceway, or having a metal armour or sheath. Where installed in buildings of combustible construction, conductors may be installed in accordance with Section 12. Conductors need to be installed independent of any other wiring except for point of supply, signal, ancillary device or communication circuits and must be insulated for the highest voltage rated conductor. Communication circuits must conform to Section 60.

Rule 32-104 requires that all exposed non-current-carrying parts of electrical equipment be bonded to ground in accordance with Section 10. In addition, non-metallic fire alarm wiring systems must incorporate a bonding conductor.

Rule 32-106 denotes that for electrical supervision, each circuit conductor terminal shall be independently terminated.

Rule 32-108 specifies that the fire alarm system power supply, except for included additional control units or transponders, be on a separate circuit and that the overcurrent devices and disconnecting means be permanently identified as a fire alarm system, be coloured red, and lockable in the on position.

Rule 32-110 provides installation requirements for permanently connected smoke alarms and carbon monoxide alarms in dwelling units that are required by the National Building Code of Canada (see Appendix G). The rule requires that smoke and carbon monoxide alarms be supplied from a circuit, such as a lighting only or mixed lighting and receptacle circuit, that will provide an indication if shut off. The circuit shall also have no disconnect or a GFCI or AFCI device between the alarms and the branch circuit overcurrent device. Interconnection of alarms may use a class 2 power supply in accordance with Rules 12-506 to 12-524.

Fire pumps

Rule 32-200 requires that conductors for the supply of a fire pump supplied from the emergency power source have an ampacity not less than 125% of the full load current rating of the motor or sum of multiple motors and auxiliary motors, and be protected from fire exposure to provide continuing operation during a fire as required by the National Building Code of Canada (see Appendix G).

Rule 32-202 outlines the requirements for wiring methods of fire pumps to be installed in metal raceways, in armour or metal sheathed cable, selected in accordance with Rule 4-888(1), in rigid non-metallic conduit embedded in concrete, or electrical non-metallic tubing embedded in concrete.

Rule 32-204 provides that a separate service box for a fire pump and equipment may be installed in conformance with rule 32-206 below and, notwithstanding rule 6-102(2), may be located remote from other service boxes.

Rule 32-206 requires that no disconnecting means, overcurrent protection or device capable of interrupting the fire pump circuit may be placed between the service box and the fire pump transfer switch or controller, except a circuit breaker that is permanently labelled identifying it as a fire pump disconnect. In addition, the circuit breaker must be lockable in the closed position and may be in the separate service box as in rule 32-204 above. In the case where this circuit breaker is installed in an emergency power supply circuit between the emergency power source and the fire pump transfer switch, the rating of the circuit breaker shall be as per rule 28-200. Where it is installed in a normal supply circuit the rating should be not less than the overcurrent protection of the fire pump controller.

Rule 32-208 requires that where an on-site electrical transfer switch is used to provide emergency power supply to a fire pump, it must be provided solely for the fire pump, located in a barriered or separate compartment or enclosure, permanently labelled as the fire pump power transfer switch, and approved for fire pump service. Where more than one fire pump is provided, a transfer switch is required for each fire pump.

Rule 32-208 provides that overload and overheating protection for branch circuit, control or equipment conductors shall not be required but shall be protected by the motor branch circuit overcurrent device.

Rule 32-210 specifies that ground fault protection shall not be installed in a fire pump circuit.

In the next instalment, we will be discussing Section 34 – Signs and Outline Lighting.

* The source for this series of articles is the Canadian Electrical Code, Part I, published by CSA

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting, billburr@gmail.com.

Related Articles


Latest Articles

  • Considerations for EV Charging Installation and Site Preparation

    Considerations for EV Charging Installation and Site Preparation

    December 15, 2025 By Blake Marchand As part of our recent discussion with LEDVANCE EVSE Product Manager, Erich Bockley, he emphasized the importance of site preparation Site preparation can be the most complicated part of the project, Bockley emphasized, a lot needs to be considered before the installation work begins. Many public charging applications will… Read More…

  • Ontario’s Multi-Family Component Leads Residential Sector Increases in October Building Permits

    Ontario’s Multi-Family Component Leads Residential Sector Increases in October Building Permits

    December 15, 2025 In October, the total value of building permits issued in Canada rose $1.8 billion (+14.9%) to $13.8 billion. The increase in construction intentions was led by the residential sector (+$1.1 billion). An increase was also observed in the non-residential sector (+$702.8 million). On a constant dollar basis (2023=100), the total value of building permits issued in… Read More…

  • Residential Investment in Building Construction Declines in September

    Residential Investment in Building Construction Declines in September

    December 15, 2025 Overall, investment in building construction decreased 1.1% to $22.4 billion in September. Investment in the residential sector declined 1.7%, while that in the non-residential sector was virtually unchanged. Year over year, investment in building construction grew 6.0% in September. On a constant dollar basis (2023=100), the total value of investment in building construction in September decreased 1.4%… Read More…

  • Nova Scotia Invests in Generational Affordable Housing for Shannon Park

    Nova Scotia Invests in Generational Affordable Housing for Shannon Park

    December 15, 2025 Work to build more than 1,400 new homes across Nova Scotia – about two-thirds at Shannon Park in Dartmouth – will soon begin with funding from the Province and the federal government. Housing Minister John White and federal Minister of Housing and Infrastructure Gregor Robertson announced $300 million to build 1,430 new… Read More…


Changing Scene

  • CSA Group Receives Greater Toronto’s Top Employers Award for 10th Consecutive Year

    CSA Group Receives Greater Toronto’s Top Employers Award for 10th Consecutive Year

    December 15, 2025 For the tenth consecutive year, CSA Group has been awarded as one of Greater Toronto’s Top Employers for 2026 by Mediacorp Canada Inc. This milestone reflects CSA Group’s continued commitment to fostering a workplace culture that supports employee wellbeing, professional growth, and community engagement. CSA Group’s global headquarters, located in Toronto, offers… Read More…

  • Hydro Ottawa to Use AI-Enhanced Predictive Analytics to Improve Energy Efficiency

    Hydro Ottawa to Use AI-Enhanced Predictive Analytics to Improve Energy Efficiency

    December 15, 2025 With $6 million in federal funding, Hydro Ottawa is introducing the Ottawa Distributed Energy Resource Accelerator (ODERA) program. Through this program, Hydro Ottawa will use AI-enhanced predictive analytics to accurately forecast peak demand, which will then inform the real-time balancing of supply and demand. This will be achieved by using a technology… Read More…

  • Stanpro’s Katy’s Donation Day Breaks Record, Giving Back to Communities Across Canada

    Stanpro’s Katy’s Donation Day Breaks Record, Giving Back to Communities Across Canada

    December 15, 2025 Stanpro is proud to announce the results of its annual Katy’s Donation Day, held on December 3, 2025. This year, the initiative resulted in a record donation of over $100,000, making this the highest contribution in the history of this program. The funds raised will be distributed to over 80 charitable organizations… Read More…

  • EB Horsman Introduce Cory Carter as New Victoria Branch Manager

    EB Horsman Introduce Cory Carter as New Victoria Branch Manager

    December 15, 2025 EB Horsman is pleased to announce the appointment of Cory Carter as Branch Manager of our Victoria location, effective November 10, 2025. With over two decades of experience in the electrical, lighting, and retail industries, Cory brings a proven track record of leadership, sales growth, and customer relationship management. Throughout his career,… Read More…