Transformer Short Circuit Considerations

March 9 2016

Short circuits or faults can and do occur on electric power and distribution systems. When a fault occurs on the load side of a transformer, the fault current will pass through the transformer. As components on these systems, transformers need to be able to withstand these fault currents.

Fault currents flowing through transformers are significantly higher than the rated currents of the transformers. In a worst case scenario, the current would be as high as the current that would flow if system voltage was applied to the primary terminals while the secondary terminals are shorted — limited by the transformer impedance only. These currents produce both mechanical and thermal stresses in the transformers.

Photo credit: Hammond Power Solutions

Forces resulting from the currents passing through the transformer act on the conductors. The forces are a function of the peak asymmetrical current (the highest peak value of any cycle of the current), which is usually at its highest during the first half cycle of the fault. The duration of the fault is not normally a concern for mechanical withstand because the peak value of each cycle of the current reduces as the fault persists. The transformer manufacturer needs to ensure these forces do not damage the transformer.

The thermal stress is caused by the high current causing heating in the transformer. Both the RMS symmetrical current magnitude and duration of the fault contribute to the heating of the transformer. The transformer manufacturer needs to ensure the components of the transformer do not become hot enough to be damaged.

General purpose dry type transformers are typically designed to withstand the mechanical and thermal stresses caused by a short circuit occurring on the secondary terminals of the transformer with rated voltage applied to the primary terminals for a maximum of 2 seconds, provided the current does not exceed 25 times rated current. The fault current magnitude is a function of the transformer impedance. The table below shows the fault current for selected impedances and applies to both line currents and phase currents.

 

Transformer Impedance  Fault Current (times rated)
4.0% 25.0
5.0% 20.0
6.0% 16.7
7.0% 14.3
8.0% 12.5

 

The maximum of 25 times rated current is listed so that transformers with an impedance below 4% need only be able to withstand 25 times rated current, although the fault current could be higher than this. It does not mean that all transformers are able to handle a fault current up to 25 times rated current. With rated voltage applied to the primary a transformer impedance above 4% will not allow 25 times rated current to flow.

Many specifications indicate a fault level at the primary terminals of the transformer. Some customers will ask for a transformer to be braced for the primary fault level. A general purpose transformer is suitable to be connected to a system with the specified fault level, but the transformer impedance will limit the fault current through it to well below the available fault level. As an example, the customer requests a 2500 kVA transformer, 13.8 kV delta to 480Y/277 V, 5.75% impedance to be braced for 750 MVA fault level at 13.8 kV. In this case, the available fault current at the primary terminals is 31.4 kA. For a fault on the secondary side of the transformer, the transformer impedance will limit the fault current that flows in the primary to 1.8 kA in the lines and 1.1 kA in the coils — significantly lower than the available fault level. There is no need for the transformer primary conductors to be sized and braced to handle a 31.4 kA fault current.

Some operating conditions need special attention. Some customers specify the transformer to operate continuously with load at higher than rated voltage. If a fault occurs when the transformer is operating at higher than rated voltage, the resulting fault current would be higher than a typical transformer is designed for. This will increase both the forces in the transformer and the heating of the transformer. Some customers specify a fault duration longer than 2 seconds without specifying a higher voltage. This does not affect the forces but does increase the heating in the transformer. In these cases, a special design may be required.

One case in particular requires special attention: transformers directly connected to a generator. When a generator is supplying a load and the load is suddenly disconnected, the output voltage of the generator rises significantly for a short time until the excitation system decreases the voltage. If a fault occurs on the secondary of a transformer at this time, the fault current can be significantly higher than a typical transformer is designed for. Some applications may not have any overcurrent protection between the generator and the transformer primary winding, resulting in an increased duration. In such cases, it is recommended that IEEE C57.116 IEEE Guide for Transformers Directly Connected to Generators be reviewed to determine the short circuit withstand requirement for the transformer.

General purpose transformers have short circuit withstand capabilities that are sufficient for many applications. The transformer manufacturer needs to be informed of cases where a fault could occur on the secondary of the transformer when the transformer is supplied above rated voltage or the fault duration is longer than two seconds to ensure the transformer is suitably designed to withstand the possible secondary faults.


This document was first published as a white paper by Hammond Power Solutions, the largest manufacturer of dry-type transformers in North America. Hammond Power Solutions engineers and manufactures a wider range of custom transformers that are exported globally in electrical equipment and systems. The firm supports solid industries such as oil and gas, mining, steel, waste and water treatment, and wind power-generation.

 

 

Related Articles


Latest Articles

  • Industry Optimism and Growth: Looking Back on the Hong Kong International Outdoor and Tech Light Expo

    Industry Optimism and Growth: Looking Back on the Hong Kong International Outdoor and Tech Light Expo

    December 2, 2024 By Elle Bremmer Attracting more than 50,000 buyers from around the world, the 26th Hong Kong International Lighting Fair (Autumn Edition) and the 9th Hong Kong International Outdoor and Tech Light Expo was by all definitions, a success. The twin fair events, which were organized by the Hong Kong Trade Development Council… Read More…

  • What Is Corrosion and Why Does VpCI® Help?

    What Is Corrosion and Why Does VpCI® Help?

    December 2, 2024 Rust is a familiar sight for most of us. Rusty cars, rusty nails, rusty locks, and other forms of corrosion are part of everyday life, causing assets to lose their value and functionality. But while the problem is obvious, the cause and the solution are less apparent to most. However, understanding the… Read More…

  • IHSA: Workplace Mental Health Toolkits

    IHSA: Workplace Mental Health Toolkits

    December 1, 2024 IHSA is committed to supporting employers and workers with their occupational health and safety needs. That includes psychological health and safety—a growing and critically important area for workplaces to address. In the sections below, you will find tools, resources, education, and supports from IHSA and our health and safety system partners. They… Read More…

  • New Research on Smart Home Trends & Technology Adoption

    New Research on Smart Home Trends & Technology Adoption

    December 1, 2024 Entertainment systems are becoming a common entry point for smart home technology, with 61% of adopters using smart TVs, displays, or speakers. So says a new consumer research report from the Association for Smart Homes & Buildings (ASHB) that explores the perceptions, preferences, pain points, and challenges of residential renters and owners… Read More…


Changing Scene

  • Legrand Acquires Power Bus Way, a Leading Provider of Fully Customized Power Feeder Systems for Data Center, Industrial and Large-scale Commercial Applications

    Legrand Acquires Power Bus Way, a Leading Provider of Fully Customized Power Feeder Systems for Data Center, Industrial and Large-scale Commercial Applications

    December 3, 2024 Legrand® has announced it has acquired Power Bus Way, a Toronto-based premier provider of custom-designed cable bus solutions for data centers, industrial facilities and commercial projects. Due to increasing demand for more digital infrastructure, Legrand estimates the North American data center market will continue to grow. This accelerated growth is further bolstered by… Read More…

  • Procore Drives Connected Construction Innovation at Groundbreak 2024

    Procore Drives Connected Construction Innovation at Groundbreak 2024

    December 2, 2024 Procore Technologies wrapped up Groundbreak 2024 last month. Procore is unveiled Resource Management, the industry’s first all-in-one solution for comprehensive labor, equipment and materials tracking and planning, along with new AI-powered Scheduling and Safety tools that enhance efficiency and streamline safety management. “Construction is one of the most complex industries in the world,… Read More…

  • Applications Now Open for Next Round of Onatario Skills Development Fund

    Applications Now Open for Next Round of Onatario Skills Development Fund

    December 1, 2024 The Ontario government has launched the second round of its Skills Development Fund (SDF) Capital Stream, with over $74 million in available funding to build, expand and retrofit training facilities for workers in the trades, including construction, manufacturing, technology and health care. Since the province launched the Skills Development Fund in 2021, Ontario is… Read More…

  • New Alberta Industry Skills Grant

    New Alberta Industry Skills Grant

    December 1, 2024 Alberta’s government continues to find creative ways to help employers find the qualified workers they need, especially in industries experiencing labour shortages. The new Alberta Industry Skills Grant will fund industry-led training in high-demand sectors like aviation, aerospace, construction and tech. Alberta’s government is making $5 million available through a pilot program… Read More…