The CE Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook, but will hopefully provide some help in navigating the code. In this article: Section 18 Hazardous locations, Part 2.

Section 18 covers installation of electrical equipment in hazardous locations as defined in Section 0, such as areas in which there is a potential for the ignition of explosive or combustible gases, dusts, fibres or flyings due to the design, installation or use of electrical equipment. Since the information in this instalment is extensive it is presented in two parts. This Instalment is Part 2.

Explosive gas atmospheres

This part contains rules for the installation of electrical equipment in all locations where explosive gas may be present.

Installations in Zone 0 locations

Rule 18-090 — Zone O is the hazardous location where explosive gas atmospheres are present continuously or for long periods and is the most restrictive. No electrical equipment or wiring may be installed in a Zone 0 hazardous location unless it meets the requirements of subrule 18-090 (2). Also note the marking requirements for Zone 0.

Rule 18-092 — seals are required where conduit leaves a Zone 0 location, and at the first point of termination of cables after entry to the Zone 0 location. Unbroken rigid conduit passing through a Zone 0 need not be sealed if the termination points are outside Zone 0. Seals are not required to be explosion-proof or flame-proof but must be identified for minimizing the passage of fluids or dusts and be accessible.

Installations in Zone 1 locations

Rule 18-100 — electrical equipment suitable for Class I Division 1 with protection level Ga or Gb and protection levels as outlined in 18-100(c) may be installed in a Zone 1 location.

Rule 18-102 — rigid metal conduit, hazardous location cables, explosion proof or flame proof “d” boxes, and fittings with threaded connection to conduit and cable glands shall be used for wiring in Zone 1. In addition, threads and joints need to comply with 18-102 (3), (4) and (5), and cables need to be supported to prevent stress at cable glands.

Rule 18-104 provides the rules for sealing conduits and cables entering enclosures in and leaving Zone 1 locations.

Rule 18-106 provides requirements for the installation of motors in Zone 1 locations. Additional guidance is given in Appendix B.

Rule 18-108 provides the rules for installation of Luminaires in Zone 1.

Rule 18-110 — flexible cords are permitted in Zone 1 where flexibility is required but must be installed in accordance with 18-110 (1) and (2).

Installations in Zone 2 locations

Rule 18-150 provides the rules for the installation of equipment in Zone 2. Note that equipment suitable for Class I Division 2 and Zone 0 and Zone 1 are permitted to be installed in Zone 2. Also note that transformers, capacitors, solenoids, and other non-arcing, non-sparking or non-heat-producing devices are permitted in Zone 2 locations.

Rule 18-152 provides rules for wiring methods in Zone 2.

Rule 18-154 provides rules for sealing conduit, cable and equipment in Zone 2.

Rule 18-156 provides rules on installation of luminaires in Zone 2.

Rule 18-158 — flexible cords are permitted in Zone 2 where flexibility is required but must be installed in accordance with 18-158 (1).

Explosive dust atmospheres

This part contains rules for the installation of electrical equipment in all locations where combustible and explosive metal dust may be present.
Installations in Zone 20 locations

Rule 18-190 — like Zone O, Zone 20 is the most restrictive hazardous location where explosive dust atmospheres are present in the form of a cloud of dust in air continuously or for long periods. No electrical equipment or wiring may be installed in a Zone 20 hazardous location unless it meets the requirements of Subrule 18-190.

Rule 18-192 provides requirements for wiring methods in Zone 20.

Rule 18-194 provides requirements for seals for a Zone 20 location.

Rule 18-196 — flexible cords are permitted in Zone 20 where flexible connections are required and shall be extra-hard-usage cord with cable glands.
Installations in Zone 21 locations

Rule 18-200 provides rules for installation of equipment in Zone 21. Equipment suitable for Class II Division 1 is permissible as well as equipment with the noted types of protection in (b) and ©.

Rule 18-202 — rigid metal conduit, hazardous location cables, explosion proof or flame proof “d” boxes, and fittings with threaded connection to conduit and cable glands shall be used for wiring in Zone 21. In addition, threads and joints need to comply with 18-202 (3), (4) and (5), and cables need to be supported to prevent stress at cable glands.

Rule 18-204 provides rules for sealing raceway equipment in Zone 21.

Installations in Zone 22 locations

Rule 18-250 provides rules for installation of equipment in Zone 22. Equipment suitable for Class II Division 2 is permissible as well as equipment with the noted types of protection in (b) and (c). This rule also provides rules for installation of cranes, hoists and other material handling equipment in Zone 22 locations.

Rule 18-252 provides rules for wiring methods in Zone 22.

Rule 18-254 provides the same sealing requirements as Zone 21.

In the next instalment we will discuss Section 20 — Flammable liquid and gasoline dispensing, service stations, garages, bulk storage plants, finishing Processes and aircraft hangars.

* The source for this series of articles is the Canadian Electrical Code, Part I, published by CSA.

Read the rest of the instalments in the series:
Part 1: Guide to the CE Code, Part I – A Roadmap (Installment 1 in a Series)
Part 2:
A Road Map to the CE Code, Part I – Installment 2
Part 3: Guide to the Canadian Electrical Code, Part I – Installment 3
Part 4: A Road Map to the CE Code, Part 1 – Installment 4
Part 5: Guide to the Canadian Electrical Code, Part I — Installment 5
Part 6: Guide to the Canadian Electrical Code, Part I — Installment 6
Part 7: Guide to the Canadian Electrical Code, Part I — Installment 7
Part 8: Guide to the Canadian Electrical Code, Part I — Installment 8
Part 9:
Guide to the Canadian Electrical Code, Part I — Installment 9
Part 10: Guide to the Canadian Electrical Code, Part 1 – Installment 10
Part 11: Guide to the Canadian Electrical Code, Part 1 – Installment 11


 

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting billburr@gmail.com.

 

Related Articles


Latest Articles

  • Code Quiz: Section 26 – Installation of Electrical Equipment

    Code Quiz: Section 26 – Installation of Electrical Equipment

    April 7, 2025 By Bill Burr Section 26 – Installation of Electrical Equipment Receptacles Question: Rule 26-706 specifies that all receptacles of CSA configuration 5-15R and 5-20R installed in: …must have a particular feature, what is this feature? Source: CSA C22.1:24, Canadian Electrical Code, Part 1 – Safety Standard for Electrical Installations. © 2021 Canadian… Read More…

  • Guide to the Canadian Electrical Code, Part 1[i], 26th Edition – A Road Map: Section 32

    Guide to the Canadian Electrical Code, Part 1[i], 26th Edition – A Road Map: Section 32

    Section 32, as outlined in rule 32 -000 Scope, is a supplementary or amendatory section of the code and provides additional and specific requirements for the location, installation, wiring, and protection, of fire alarm systems… Read More…

  • Alberta Municipalities EV Charging Installation Rebate

    Alberta Municipalities EV Charging Installation Rebate

    April 4, 2025 Alberta Municipalities are proud to provide financial rebates for applicants to purchase and install electric vehicle charging stations in Alberta as part of the Electric Vehicle Charging Program (EVCP), funded by Natural Resources Canada (NRCan) & Alberta Municipalities.  The funding will cover up to 46% of your total project cost, which can… Read More…

  • Industry Legend Bill Smith Retires

    Industry Legend Bill Smith Retires

    April 4, 2025 By Electro-Federation Canada On March 25, Electrozad, a Sonepar Company, hosted a special retirement reception at Caesars Windsor for industry titan Bill Smith who marked an incredible 50-year career with the company.  The reception was held in the elegant Caesars Ballroom, which featured an array of food stations and elegant decor. In… Read More…


Changing Scene

  • NSAA Fee Change Effective April 1, 2025

    NSAA Fee Change Effective April 1, 2025

    As of April 1, 2025, the Nova Scotia Apprenticeship Agency’s fees have changed due to the 1% reduction in HST in Nova Scotia. NSAA noted on their website that due to the number of references across various pages, you may still come across old fee amounts as they work through updating their website. Here is… Read More…

  • Nominations Open for 2024 NETCO Leadership Excellence Award

    Nominations Open for 2024 NETCO Leadership Excellence Award

    Established in 2016, the NETCO Leadership Excellence award honours an industry training professional for his/her role for the success and their outstanding contributions to apprenticeship training and continuing electrical training. Read More…

  • Munded Partners with Kane Test Equipment in Atlantic Canada

    Munded Partners with Kane Test Equipment in Atlantic Canada

    April 4, 2025 Munden Enterprises has announced a partnership with Kane Test Equipment to bring their test and measurement solutions to Atlantic Canada. “We are now excited to announce a new and promising partnership with Kane Test Equipment. Kane Test Equipment brings innovative solutions that align with our dedication to providing the best tools for… Read More…

  • Nedco Announces Western Canadian Wire & Cable Sales Manager

    Nedco Announces Western Canadian Wire & Cable Sales Manager

    April 4, 2025 Don Blake has joined Nedco as their Western Canadian Wire & Cable Sales Manager. “With over 20 years of experience in the Wire & Cable industry, Don brings a wealth of knowledge and expertise to our Nedco West team,” said the company on LinkedIn. “His focus will be on expanding our product… Read More…