Case Study: Temporary Power for Large Scale Residential Construction

Temporary Power

Ever wonder how large construction projects with sales offices and show suites get power when there is only a generator or temporary power established on the construction site?TheBC Safety Authority (BCSA) pays close attention to these types of installations, since fire alarms, sprinklers, and other building code safety systems are not up and running during the construction phase of the project.

Recently, a BCSA safety officer conducted an assessment of a large multi-family residential site under construction. Working collaboratively with electrical contractors, other trades, safety officials, utilities, and building departments to reach safety solutions is an important part of a BCSA safety officer’s role.

During the inspection, several significant hazards were found.Most notably, townhouses had been energized using the temporary construction service, creating a risk of overload to the service. Had these dwellings become occupied, this could have resulted in a serious fire and shock hazard.

An additional hazard was created by the power cable used to provide power from the temporary distribution system to the townhouses, which was not installed with the necessary mechanical protection.Construction sites typically have heavy machinery operating and it is imperative that the power cables be installed in a manner that protects them from mechanical damage.A break in the armoured cable can result in either a fire (if combustible material is near by) or a shock hazard if the bonding provisions have been compromised.

Addressing the hazards
The safety officer first documented his findings in a certificate of inspection and contacted the electrical contractor to develop a plan to rectify the identified non-compliances.The contractor submitted an application for a variance, as required by the Safety Standards Act, to energize the show rooms and sales offices.The variance included a request to energize a specific portion of the site, and outlined the wiring method used to provide power to this area of the site, and the signage required at strategic locations on the site, including mark ups on the site’s safety plans.The safety officer granted the variance and the electrical contractor completed the installation and the obligations outlined in the variance.

To reduce the safety hazards on the site, branch circuits inside each dwelling had all unnecessary circuit conductors disconnected from circuit breakers. The heavy loads such as space heating, furnaces, dryers, ranges were also disconnected.The safety officer then informed BC Hydro and the electrical contractor that a “hold connection” be placed on the permanent installation permit.This ensures that when the permanent installation is ready for power, the necessary work is completed to transfer and disconnect the temporary power in the showrooms to remove the risk of a possible back feed.

When dealing with sites that have both permanent and temporary electrical systems, closely review your electrical code, specifically the stating that interconnection of temporary power installations and permanent installations shall not be interconnected unless by special permission.

This article was first published online by the BC Safety Authority, http://safetyauthority.ca.

 

Related Articles


Latest Articles

  • Navigating Tariff Uncertainty as an Electrical Contractor

    April 15, 2025 By Matthew Biswas These three words put me into a catatonic shock – Supply Chain Disruption. It seems like just yesterday I was standing at a counter asking for products I’d bought 100’s of times before and being told they are on backorder with no expected delivery date. Circuit breakers, dimmers, panels,… Read More…

  • Four Ways Permanent Power Enahnces Outdoor Spaces

    Four Ways Permanent Power Enahnces Outdoor Spaces

    April 14, 2025 Today’s workplaces are expanding beyond the four walls of an office. As technology continues to evolve, employees are looking for new and alternative workspaces to inspire creativity and increase productivity. This includes taking their work to outdoor spaces. Bringing technology to outdoor spaces has become a challenge for facility managers and property… Read More…

  • CAF-FCA Provides Recomendations on Apprenticeship Investment

    CAF-FCA Provides Recomendations on Apprenticeship Investment

    April 13, 2025 CAF-FCA have provided an outline of actionable recommendations—developed through national consultation—to enhance accessibility, reduce financial barriers, and better align apprenticeship training with industry needs. Source Read More…

  • New Report: Preparing Alberta’s Buildings for Severe Weather

    New Report: Preparing Alberta’s Buildings for Severe Weather

    April 13, 2025 Alberta is facing more severe weather events, with rising temperatures, wildfires, and more frequent extreme storms threatening homes and businesses. Our report, Preparing Alberta’s Buildings for Severe Weather−written in partnership with the Alberta Ecotrust Retrofit Accelerator program−highlights the need for deep retrofits to ensure the province’s buildings can withstand these changing conditions. Four… Read More…


Changing Scene