Building a New Power Line Gave BC crews a Chance to Shine

On The Job BC Power

Stringing new power lines, called conductors, requires careful coordination between crews on the ground and helicopter pilots.

Foreman Bill Dalling can’t imagine doing anything else but working in the line trade. His crews worked on slopes of up to 30% grade capable of snapping chains or towing straps securing heavy loads. And then there was the spring thaw, where snow turned to mud “thick like gumbo.”But to hear Dalling describe it, building a new transmission line is about as good as it gets, at least for someone who’s made a career out of building power lines.

Dalling has been working since August 2014 as the foreman for the Merritt Area Transmission Project, leading BC Hydro construction crews as they built the 35-kilometre, 138-kilovolt transmission line, scheduled to be in-service in the fall of 2015.

The new line, which passes through tough mountainous terrain in B.C.’s southern interior, begins near the Highland substation 12 kilometres south of Logan Lake, and continues up over the mountains towards the Coquihalla Highway. It will provide power to the growing community of Merritt and the surrounding area.

The construction services team was responsible for every aspect of constructing the transmission poles and stringing the conductor, and as he explains, it’s not exactly easy.

Crews start by clearing a right-of-way for the new line

Before the familiar power poles can be constructed, and before power lines can be strung into place, crews need to clear the next stretch of right-of-way for the transmission line. Access roads need to be built so that trucks and equipment can access the transmission line route, and vegetation needs to be cleared to ensure crews can work safely.

Once the right-of-way is cleared, setting crews can move in to place the structures. In this case, wooden transmission towers known as “H-frames.” Part of his role was to coordinate construction so that the 30-person crew could always easily and safely move on to work on erecting the next structure. Once the structures are up, the chopper moves in. Thanks to the steep terrain and the difficult access along the transmission line route, the power lines are strung by helicopters, working closely with crews on the ground.

Helicopter pulls lines into place – carefully

“It starts with stringing what’s called hard line steel,” says Dalling, explaining that the hard line steel goes through pulleys called travellers in a series of structures, six kilometres at a time. These act as the ‘bull line” that attaches to the actual power lines, known as conductors, and is pulled by the helicopter to string the conductors through the same travellers. One of the important parts of stringing the lines is ensuring the appropriate “sag” in the line. There aren’t a lot of times in life when something sagging is positive, but building a power line is one of them.

“Every power line in the system has to be sagged according to the outdoor temperature to allow for expanding and contracting,” says Dalling, adding that it’s critical to get just the right amount of slack in the lines. Seasonal fluctuations in temperature, especially in colder climates, can wreak havoc on transmission lines and poles.

“In the winter, the lines can contract so much that they can break structures and poles as they pull tighter if they’re sagged improperly,” he says.

And if contending with helicopters wasn’t enough of a challenge, building a power line in B.C. is never easy. Crews here face some of the toughest terrain around.

“We were working in deep mud, it was like gumbo”

The terrain was steep and rough, says Dalling, and something as simple as keeping your footing while you were working was a challenge. Working through the winter meant slippery, snowy conditions, and the warmer weather wasn’t any easier, creating deep mud everywhere that the crews needed to work.

“We were working in deep mud some of the time, it was thick like gumbo,” says Dalling of the conditions setting crews faced as snows thawed.

And the mountainous location made it harder to keep track of the crews. Like most construction sites, safety is paramount, particularly with helicopters working overhead. Crews need to stay in constant contact, but there’s limited radio communications in the mountains around Merritt.

Crews would be stationed as much as six kilometres apart, so often someone needed to be placed in the middle to relay messages from the yard to the site where the stringing was taking place.

And at one end of the new line, near Highland Substation, crews were working parallel to an existing 138-kilovolt line, creating additional hazards and challenges in order to create proper grounding and work safely near a live power line.

Despite the challenges, Dalling is upbeat and enthusiastic about the whole project, citing it as a great one for the team, which included working with additional BC Hydro construction crews from Prince George and Nanaimo. As he says, everyone really enjoyed the project, did an exceptional job, and there was a great sense of camaraderie around the crew from beginning to end.

And for Dalling, that’s what he’s looking for each time he heads to work in the morning. Construction services gives him the opportunity to work on the whole spectrum of the power line trade, from building transmission lines, working in substations to working on distribution lines.

“I really enjoy this trade, I can’t think of doing anything else,” he says.

 

Related Articles


Latest Articles

  • Efficiency Nova Scotia Rebates

    Efficiency Nova Scotia Rebates

    January 24, 2025 NEW Up to 75% of product costs in rebates for energy efficient products or interest-free financing for up to 24 months. Get rebates Before You Buy, at the counter, or After You Buy with mail-in and instant rebates. Before you Buy Instant Rebates No paperwork required. Save at the counter when you… Read More…

  • The Drive Towards Energy-Efficient Data Centres

    The Drive Towards Energy-Efficient Data Centres

    Data centres are the backbone of our digital world. They serve as the foundation for various online activities like streaming, e-commerce, website/app usage, Digital transformation. Read More…

  • Multi-Unit Construction Intentions Push Down the Residential Sector for November 2024 Building Permits

    Multi-Unit Construction Intentions Push Down the Residential Sector for November 2024 Building Permits

    January 20, 2025 The total value of building permits issued in Canada decreased by $739.5 million (-5.9%) to $11.7 billion in November, a second consecutive monthly decline. The residential sector led the decrease, followed by the non-residential sector. On a constant dollar basis (2017=100), the total value of building permits issued in November declined 5.8% from the previous… Read More…

  • Ontario Save On Energy Home Renovation Savings Program

    Ontario Save On Energy Home Renovation Savings Program

    January 20, 2025 On January 7, the Government of Ontario announced 14 new and expanded energy-efficiency programs, including the Home Renovation Savings Program, as part of a new $10.9 billion investment in energy efficiency to help families and businesses save money. Save on Energy and Enbridge Gas, with endorsement from the Ontario government, have partnered to… Read More…


Changing Scene

  • Agence Ricard Welcomes New Business Development Specialist for the South Shore of Montreal 

    Agence Ricard Welcomes New Business Development Specialist for the South Shore of Montreal 

    January 24, 2025 Agence Ricard is proud to announce the arrival of Fred Dozois as new business development specialist for the South Shore of Montreal. With over 10 years of experience in the electrical industry, Fred brings an impressive wealth of knowledge and skills that will strengthen the team at Ricard.  Recognized for his expertise,… Read More…

  • Graybar Transforming Branches From Coast to Coast

    Graybar Transforming Branches From Coast to Coast

    January 24, 2025 Exciting transformations are happening at Graybar Canada. Across the nation, Graybar branches are getting a refreshed look, inside and out. These updates reflect their dedication to maintaining modern, welcoming spaces that showcase the strength of their brand and world class manufacturer partners. From sleek new shelving to vibrant wall murals, these renovations are designed… Read More…

  • New Address for Franklin Empire London, ON Branch

    New Address for Franklin Empire London, ON Branch

    January 24, 2025 Franklin Empire are pleased to announce the new address of their London, Ontario branch. Address:552 Newbold StreetLondon, Ontario N6E 2S5 Source Read More…

  • Ontario Launches Regional Economic Development Through Immigration Pilot Program 

    Ontario Launches Regional Economic Development Through Immigration Pilot Program 

    January 24, 2025  The Ontario government has launched the Regional Economic Development through Immigration (REDI) pilot program to target highly-skilled immigration for four rural and northern regions with a high demand for skilled labour: Lanark, Leeds and Grenville, Sarnia-Lambton, and Thunder Bay. REDI enables local employers in these communities to attract up to 800 additional… Read More…