Ever wonder how large construction projects with sales offices and show suites get power when there is only a generator or temporary power established on the construction site?TheBC Safety Authority (BCSA) pays close attention to these types of installations, since fire alarms, sprinklers, and other building code safety systems are not up and running during the construction phase of the project.

Recently, a BCSA safety officer conducted an assessment of a large multi-family residential site under construction. Working collaboratively with electrical contractors, other trades, safety officials, utilities, and building departments to reach safety solutions is an important part of a BCSA safety officer’s role.

During the inspection, several significant hazards were found.Most notably, townhouses had been energized using the temporary construction service, creating a risk of overload to the service. Had these dwellings become occupied, this could have resulted in a serious fire and shock hazard.

An additional hazard was created by the power cable used to provide power from the temporary distribution system to the townhouses, which was not installed with the necessary mechanical protection.Construction sites typically have heavy machinery operating and it is imperative that the power cables be installed in a manner that protects them from mechanical damage.A break in the armoured cable can result in either a fire (if combustible material is near by) or a shock hazard if the bonding provisions have been compromised.

Addressing the hazards
The safety officer first documented his findings in a certificate of inspection and contacted the electrical contractor to develop a plan to rectify the identified non-compliances.The contractor submitted an application for a variance, as required by the Safety Standards Act, to energize the show rooms and sales offices.The variance included a request to energize a specific portion of the site, and outlined the wiring method used to provide power to this area of the site, and the signage required at strategic locations on the site, including mark ups on the site’s safety plans.The safety officer granted the variance and the electrical contractor completed the installation and the obligations outlined in the variance.

To reduce the safety hazards on the site, branch circuits inside each dwelling had all unnecessary circuit conductors disconnected from circuit breakers. The heavy loads such as space heating, furnaces, dryers, ranges were also disconnected.The safety officer then informed BC Hydro and the electrical contractor that a “hold connection” be placed on the permanent installation permit.This ensures that when the permanent installation is ready for power, the necessary work is completed to transfer and disconnect the temporary power in the showrooms to remove the risk of a possible back feed.

When dealing with sites that have both permanent and temporary electrical systems, closely review your electrical code, specifically the stating that interconnection of temporary power installations and permanent installations shall not be interconnected unless by special permission.

This article was first published online by the BC Safety Authority, http://safetyauthority.ca.

 

Related Articles


Latest Articles

  • ABB Wins New Product Award at MCEE Show

    ABB Wins New Product Award at MCEE Show

    April 28, 2025 ReliaHome™ Smart Panel won Best New Product Award in the Software, Controls and Related Components category. Iberville® Gangable boxes with low-voltage cables support bracket was recognized as a finalist in the Commercial, Institutional and Industrial Electrical Products category. ABB was honored with a Best New Product Award in the Software, Controls and… Read More…

  • Weidmuller Celebrating a Legacy: 175 Years Globally, 50 Years in Canada

    Weidmuller Celebrating a Legacy: 175 Years Globally, 50 Years in Canada

    April 28, 2025 The year 2025 is truly special for Weidmüller. The company proudly celebrates not just 50 remarkable years in Canada but also its 175th anniversary globally—an extraordinary achievement few companies can claim. This legacy is a testament to the company’s relentless pursuit of innovation and commitment to refining its offerings. But the journey… Read More…

  • Canada Stands Tall at Hannover Messe 2025

    Canada Stands Tall at Hannover Messe 2025

    April 28, 2025 By Owen Hurst At Hannover Messe earlier this month Canada had a strong presence as the host country with a wide variety of companies and programs focusing on the development of advance technology. The presence was accentuated by numerous halls hosting Canada pavilions. Partner Country Canada presented itself impressively at HANNOVER MESSE…. Read More…

  • BC Prompt Payment Legislation Progressing

    BC Prompt Payment Legislation Progressing

    April 28, 2025 Consistent with its mandate of growing the economy, the government wants to ensure that businesses are paid promptly for work performed on (or material provided to) construction projects. British Columbia’s Ministry of Attorney General staff have been tracking the issue of payment delay in the construction industry, including legislative responses in other… Read More…


Changing Scene

  • Schneider Electric Advances in Product Environmental Data Transparency

    Schneider Electric Advances in Product Environmental Data Transparency

    April 28, 2025 Schneider Electric has launched its Environmental Data Program. This initiative, which builds on the legacy Green Premium label, provides customers with unique access to information on the environmental impact of its products, enabling them to make better informed, data-based decisions and meet evolving regulatory requirements with confidence. Schneider Electric has frequently been recognized… Read More…

  • nVent Sustainability Report Highlights Progress and Focus on Electrification

    nVent Sustainability Report Highlights Progress and Focus on Electrification

    April 15, 2025 nVent Electric plc announced the release of its 2024 Sustainability Report. The new report highlights nVent’s achievements in each of its sustainability focus areas: People, Products, Planet and Governance. The report also highlights how nVent solutions support electrification, digitalization and sustainability efforts around the world. “nVent is becoming a more focused electrical… Read More…

  • Ontario Introduces Legistlation to Unlock Trade and Labour Mobility Within Canada

    Ontario Introduces Legistlation to Unlock Trade and Labour Mobility Within Canada

    April 18, 2025 As a next step in its plan to protect Ontario by unleashing the province’s economy, the Ontario government is introducing the Protect Ontario through Free Trade within Canada Act to unlock free trade and labour mobility within Canada. This legislation will, if passed, create new opportunities for job creation and investment attraction, supporting economic… Read More…

  • Ontario, P.E.I. Join Nova Scotia With Legislation to Remove Internal Trade Barriers

    Ontario, P.E.I. Join Nova Scotia With Legislation to Remove Internal Trade Barriers

    April 18, 2025 Prince Edward Island and Ontario have joined the Nova Scotia by introducing reciprocal legislation that will help foster an environment of mutual recognition of goods, services and labour mobility between these provinces. “Leaders across the country are expressing interest in removing trade barriers, and I’m very pleased that P.E.I. and Ontario have… Read More…