In this article: Section 72 — Mobile home and recreational vehicle parks. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the explanations of individual requirements contained in the CEC Handbook** but will hopefully provide some help in navigating the code.

Rule 72-000 notes that this is a supplementary or amendatory section of the code and applies to the services and distribution facilities for mobile home and recreational vehicle parks.

Rule 72-100 requires that each mobile home and recreational vehicle be provided with service equipment in accordance with Section 6.

Rule 72-102 outlines the demand factors for various service and feeder conductor arrangements:

• for service or feeder conductors supplying an individual mobile home or more than one mobile home — Rules 8-200 and 8-202, respectively

• for the minimum ampacity of the consumer’s service and feeder conductors for recreational vehicle parks, calculated based on the rating of the receptacles and the following demand factors:

o 100% of the first five highest rated, plus
o 75% of the next ten receptacles, plus
o 50% of the next ten receptacles, plus
o 25% of the remainder

• multi-wire circuit receptacles are counted as two receptacles

• the highest rated receptacle is used as the basis for calculation

Rule 72-104 permits feeders for the park consumer’s service equipment and the park distribution centres to be installed as per Section 6.

Rule 72-106 requires that the branch circuit for each recreational vehicle lot receptacle have a suitable, accessible overcurrent device and disconnecting means.

Rule 72-108 requires that the branch circuit for each mobile home lot have a suitable, accessible overcurrent device and disconnecting means and be located within a weatherproof enclosure if installed outdoors.

Rule 72-110 specifies the connection facilities for recreational vehicles and mobile homes and outlines:

• the types of 15A, 20A, 30A, and 50A receptacles required where installed on recreational vehicle lots

• the requirement for a permanent connection to a mobile home, except that for a home with a 50A rated overcurrent protection, a 50 A, 125/250 V, 3-pole, 4-wire Type 14-50R receptacle may be permitted (under Rule 2-030)

• all receptacles must be mounted in a horizontal plane, or so that the u-ground slot is uppermost

• 15A and 20A receptacles must be protected by a Class A type ground fault circuit interrupter

Rule 72-112 states that power supply cords may be permitted for the connection of

• recreational vehicles, only where the cords are not subject to severe physical abuse or extended periods of use

• mobile homes only when the lot is equipped with a 50 A, 3-pole, 4-wire Type 14-50R receptacle (permitted under Rule 2-030)

In the next instalment, we will be discussing Section 74 — Airport installations.

* The source for this series of articles is the Canadian Electrical Code, Part I, published by CSA.

**Note the CEC Handbook is also published by CSA.

William (Bill) Burr is the former Chair of the Canadian Advisory Council on Electrical Safety (CACES), former Director of Electrical and Elevator Safety for the Province of BC, and former Director of Electrical and Gas Standards Development and former Director of Conformity Assessment at CSA Group. Bill can be reached at Burr and Associates Consulting; billburr@gmail.com

 

Related Articles


Latest Articles

  • Guide to the Canadian Electrical Code, Part 1[i], 26th Edition– A Road Map: Section 56

    Guide to the Canadian Electrical Code, Part 1[i], 26th Edition– A Road Map: Section 56

    February 6, 2026 The Code is a comprehensive document. Sometimes it can seem quite daunting to quickly find the information you need. This series of articles provides a guide to help users find their way through this critical document. This is not intended to replace the notes in Appendix B or the explanations of individual Read More…

  • 3D Printing: Inside Lighting’s Next Revolution

    February 5, 2026 While 3D printing in mass production was once a dream, advancements in the technology have moved it more into the mainstream. The technique, which is also referred to as additive manufacturing, has rapidly evolved from a niche prototyping tool into a transformative production method for many sectors, including the lighting industry. As Read More…

  • Microgrids & Power Quality: Designing Resilient, Clean Facility Power

    Microgrids & Power Quality: Designing Resilient, Clean Facility Power

    February 5, 2026 In an era of extreme weather, aging infrastructure, and ever‑rising energy demands, many facility managers are rethinking their relationship with the grid. Microgrids offer a way to take control and operate autonomously when necessary. A microgrid is more than just backup, when designed properly, it becomes a platform for resiliency, efficiency, and Read More…

  • ITC 101: Understanding NEMA Ratings for Electrical Enclosures

    ITC 101: Understanding NEMA Ratings for Electrical Enclosures

    February 5, 2026 Understanding NEMA Ratings for Electrical Enclosures NEMA Ratings are an essential classification system used across North America to define the environmental and mechanical protection provided by electrical enclosures. Developed by the National Electrical Manufacturers Association (NEMA), these ratings help engineers, installers, and specifiers identify the appropriate enclosure type for industrial, commercial, and outdoor Read More…


Changing Scene

  • Lighting What’s Next: Stanpro Celebrates 65 Years

    Lighting What’s Next: Stanpro Celebrates 65 Years

    February 6, 2026 “We didn’t get here by standing still. For 65 years, we’ve shaped how we think, how we design, and what responsibility means,” the company said in a LinkedIn post. “Today, that thinking takes a new form. Not to change who we are, but to express our evolution more clearly. This is Stanpro, Read More…

  • Housing Priorities on Track in New Brunswick, but More Work to do: Hickey

    Housing Priorities on Track in New Brunswick, but More Work to do: Hickey

    February 6, 2026 Efforts to support the creation of new affordable housing and reduce chronic homelessness are on track, but there is still lots of work to do, according to David Hickey, the minister responsible for the New Brunswick Housing Corporation. New data indicates progress has been made on three key government priorities related to Read More…

  • BJ Electric is now Bernie’s Electric Supplies Ltd

    BJ Electric is now Bernie’s Electric Supplies Ltd

    February 6, 2026 BJ Electric has announced the company has rebranded as Bernie’s Electric Supplies Ltd, a nod to their founder. “BJ Electric Supplies is now Bernie’s Electric Supplies—in honor of our founder, Bernard Joseph Thompson, and the values that have guided the company for nearly 50 years. As we grow and evolve, this name Read More…

  • The Government of Canada Introduces the Build Canada Homes Act

    The Government of Canada Introduces the Build Canada Homes Act

    February 6, 2026 The Government of Canada has introduced the Build Canada Homes Act, legislation that will establish Build Canada Homes as a Crown corporation whose mandate will be dedicated to building affordable housing in communities across the country. As Canada’s affordable housing builder, this legislation will equip Build Canada Homes with the necessary tools to Read More…