Shock Risk Assessment and the Detailed Warning Label “Electrical Safety Zone”

Safety

 

June 4, 2018

By Len Cicero

Does this detailed warning label look familiar? Perhaps you have seen one, or at least one that resembles this in a commercial or industrial facility.

With all of the hype and conversation in recent years revolving around “arc flash,” it is likely due-time that we all start talking about shock, shock hazard and shock risk assessment.

Depending on how you break it down, there are about seven steps in the Canadian Electrical Code for completing a good shock risk assessment. Specific details are in the standard (2015 edition) but in Clause 4.3.4.1 “Shock risk assessment,” you will find three basic determinations:

1. Voltage to which personnel will be exposed
2. Boundary requirements
3. PPE necessary to minimize the possibility of electric shock

A competent and qualified electrical person can usually, and quite easily, determine the voltage(s) to which personnel could be exposed, when they know the work at hand.

As seen in the warning label, there are two boundary requirements in Z462-15 (the third boundary requirement — Prohibited — was removed from the 2015 version). Clause 4.3.4.3 gives specific details for the Limited Approach Boundary, which applies to approach by unqualified persons, working at or close to the Limited Approach Boundary, and entering the Limited Approach Boundary.

Having said all of this, what is actually meant by the “Limited and Restricted Approach Boundaries?” It can be referred to as the “Electrical Safety Zone” or “Safe Work Area.” The Limited Approach Boundary is the furthest of the two boundaries (within the electrical safety zone). Both, the limited approach, and the restricted approach, are dependent on the nominal system voltage in AC systems and the difference in potential in DC systems.

As many of us are aware when we troubleshoot or perform diagnostic work in a busy or high traffic area, it tends to draw an audience of spectators. Whether it’s asking questions or taking pictures, people’s curiosity can unintentionally put them in harms way. Something that we as tradespeople have allowed to happen for decades. This is where CSA Z462-15, and in particular the Limited Approach Boundary, comes in and lends us a hand. It must be stressed that the Limited Approach Boundary (Electrical Safety Zone) be established. Do not necessarily be focused on the exact distances prescribed in CSA Z462-15 or on the warning label. Be more focused on overseeing this work area and not permitting the spectators, including supervisors and managers, to gather around or encroach. CSA Z462-15 does allow an unqualified worker to cross the Limited Approach Boundary, however they must be escorted and briefed on the hazards by the qualified worker. In addition, by no means can an unqualified worker cross the Restricted Approach Boundary.

So, the next time you are performing diagnostics or troubleshooting in an open panel while energized, remember to establish a safe work area and ensure to keep the unqualified persons away and out of harms way.

Len Cicero is the owner and president of Lenco Training and Technical Services. He is a master electrician, and a certified electrical safety compliance professional. He is recognized by the industry, and his colleagues as a specialist in lockout and workplace electrical safety. Len is involved with CSA-460 as the technical committee chairperson, and is a founding and executive member of CSA-462. He is also a member of the Canadian Society of Safety Engineers and is the past president of the Halton Chapter of the Ontario Electrical League. For more information about Lenco Training and Technical Services, visit www.archflash.ca.

This article was reprinted with permission from Ontario Electrical League. It was first published in the Spring 2018 issue of OEL Dialogue; www.oel.org

 

Related Articles


Latest Articles


Changing Scene

  • IDEAL Electrical Partners with Habitat for Humanity Greater Toronto Area to Support Affordable Housing Initiatives

    IDEAL Electrical Partners with Habitat for Humanity Greater Toronto Area to Support Affordable Housing Initiatives

    August 17, 2026 Earlier this month, approximately 30 IDEAL Electrical employees and skilled electricians volunteered alongside Habitat for Humanity Greater Toronto Area (GTA) to help construct Countryside, an affordable 15-unit townhome development in Brampton that will welcome families later this year. Volunteers assisted with electrical wiring and rough-in installation and provide general construction support, helping… Read More…

  • Hubbell Canada Forms Strategic Alliance with Mac’s II Agencies to Strengthen Harsh & Hazardous Market Presence in British Columbia

    Hubbell Canada Forms Strategic Alliance with Mac’s II Agencies to Strengthen Harsh & Hazardous Market Presence in British Columbia

    August 17, 2026 Hubbell Canada is pleased to announce a new strategic partnership with Mac’s II Agencies, effective August 1, 2026, to represent Hubbell Canada’s Harsh & Hazardous portfolio throughout British Columbia. This newly formed alliance further strengthens Hubbell Canada’s commitment to serving customers operating in some of the most demanding industrial environments, while supporting… Read More…

  • AEA Scholarships and Bursaries Apply by August 31st

    AEA Scholarships and Bursaries Apply by August 31st

    August 17, 2026 The Alberta Electrical Alliance is proud to support our industry with over $320,500 of postsecondary scholarships for current members and their children. Your participation in AEA events helps fund AEA scholarships and build our industry’s future. AEA Sponsored Scholarships Open to employees, dependents, and children of parents who are members of the… Read More…

  • Contractors’ Corner at the 2026 NETCO Conference

    Contractors’ Corner at the 2026 NETCO Conference

    August 17, 2026 ECAO and CECA look forward to joining industry leaders at the NETCO – National Electrical Trade Council 2026 Conference for an important conversation on AI and its growing role in electrical contracting. R. Graeme Aitken, Executive Director of ECAO, Terry Milot, President of the Canadian Electrical Contractors Association, and Témoc Vega, PhD,… Read More…